No.Condition Text
1.The development to which this permission relates must be commenced not later than three years from the date of this permission. Reason:- To comply with the requirements of Section 91 of the Town and Country Planning Act 1990 (as amended by Section 51 of the Planning and Compulsory Purchase Act 2004).
2.The proposed development hereby approved shall be constructed in accordance with the materials detailed under Section 9 of the application form unless otherwise agreed in writing by the Local Planning Authority. Reason: To ensure that the appearance of the proposed development will harmonise with the character of the surrounding area and comply with Policy DC61 of the Development Control Policies Development Plan Document
3.The permission hereby granted shall be for a limited period only, expiring on 28 February 2021, by which date the use of the temporary buildings shall be discontinued and the building removed from the site and the site reinstated to its former condition, or as otherwise approved, to the satisfaction of the Local Planning Authority. Reason:- To enable the Local Planning Authority to retain control, to ensure that the planning permission granted is temporary in nature and to comply with Development Control Policies Development Plan Document Policy DC61.
4.The development hereby permitted shall not be carried out otherwise than in complete accordance with the approved plans (as set out on page one of this decision notice). Reason:- The Local Planning Authority consider it essential that the whole of the development is carried out and that no departure whatsoever is made from the details approved, since the development would not necessarily be acceptable if partly carried out or carried out differently in any degree from the details submitted. Also, in order that the development accords with Development Control Policies Development Plan Document Policy DC61.
5.Statement Required by Article 35 (2) of the Town and Country Planning (Development Management Procedure) (England) Order 2015: No significant problems were identified during the consideration of the application, and therefore it has been determined in accordance with paragraphs 186-187 of the National Planning Policy Framework 2012.