The London Borough Of Havering - Home page

No.Condition Text
1.The operations come within the provisions of Schedule 2, Part 1, Class B of the Town and Country Planning (General Permitted Development) (England) Order 2015, thereby not requiring planning permission.
2.The operations come within the provisions of Schedule 2, Part 1, Class C of the Town and Country Planning (General Permitted Development) (England) Order 2015, thereby not requiring planning permission.
3.The development is permitted by Class B subject to the following conditions- (a) the materials used in any exterior work must be of a similar appearance to those used in the construction of the exterior of the existing dwellinghouse; (b) the enlargement must be constructed so that- (i) other than in the case of a hip-to-gable enlargement or an enlargement which joins the original roof to the roof of a rear or side extension- (aa) the eaves of the original roof are maintained or reinstated; and (bb) the edge of the enlargement closest to the eaves of the original roof is, so far as practicable, not less than 0.2 metres from the eaves, measered along the roof slope from the outside edge of the eaves; and (ii) other than in the case of an enlargement which joins the original roof to the roof of a rear or side extension, no part of the enlargement extends beyond the outside face of any external wall of the original dwellinghouse; and (c) any window inserted on a wall or roof slope forming a side elevation of the dwellinghouse must be- (i) obscure-glazed, and (ii) non-opening unless the parts of the window which can be opened are more than 1.7 metres above the floor of the room in which the window is installed.
4.Development is permitted by Class C subject to the condition that any window located on a roof slope forming a side elevation of the dwellinghouse shall be- (a) obscure-glazed; and (b) non-opening unless the parts of the window which can be opened are more than 1.7 metres above the floor of the room in which the window is installed.
5.Building Regulations You are reminded that this decision notice only addresses requirements under Planning Legislation. You also need to check that whether or not the development requires consent under the Building Regulations, as this is an entirely separate process. Further information on the requirements of the Building Regulations can be found at: https://www.havering.gov.uk/building control.
6.Highways Matters You are reminded that this decision notice only addresses requirements under Planning Legislation. It does not give consent for an permanent or temporary changes to the public highway, the use of the public highway for the storage of materials or placing of apparatus associated with the construction or other processes, nor does it permit the discharge of surface water onto the public highway. You are encouraged to check whether or not works or activities necessitate separate consents under the requirements of other, non-planning legislation at the earliest opportunity by emailing environmentbusinesssupport@havering.gov.uk for further information. Unauthorised work on or use of the public highway and a failure to prevent the discharge of surface water on to the public highway area all an offence.
7.Party Wall Act You are reminded that this decision notice only addresses requirements under Planning Legislation. You also need to check whether or not the development necessitates an agreement under the requirements of the Party Wall etc. Act 1996, as this is an entirely separate process. Further guidance on the Party Wall etc. Act 1996 can be found at: https;//www,gov.uk/housing-local-and-community/party-walls.