No.Condition Text
1.Prior Approval is given in accordance with the details as provided within the application.
2.No part of the development hereby approved shall be occupied until access to the highway has been completed in accordance with the details that have been previously submitted to and approved in writing by the Local Planning Authority, including the redundant vehicle crossing current serving the front of the site from Harold Court Road. Reason: In the interests of ensuring good design and ensuring public safety and to comply with policies of the Core Strategy and Development Control Policies DPD, namely CP10, CP17, and DC61.
3.The development hereby approved shall not be occupied until a scheme detailing the measures to protect residents from noise is submitted to and approved in writing by the Local Planning Authority. Reason: To protect residents from noise and in accordance with Policy DC55 and DC61 of LBH's 'Development Plan Document' 2008.
4.The development hereby approved shall not be occupied until cycle parking is provided in accordance with details to be previously submitted to and approved in writing by the Local Planning Authority. Cycle parking shall be to the standards set out in Table 6.3 of the London Plan. Such cycle parking shall thereafter be retained to the satisfaction of the Local Planning Authority. Reason:- Insufficient information has been supplied with the application to demonstrate what facilities will be available for cycle parking. Submission of this detail prior to occupation is in the interests of providing a wide range of facilities for non-motor car residents and sustainability.
5.No building shall be occupied or use commenced until refuse and recycling facilities are provided in accordance with details which shall previously have been submitted to and approved in writing by the Local Planning Authority. The refuse and recycling facilities shall be permanently retained thereafter. Reason:- Insufficient information has been supplied with the application to judge how refuse and recycling will be managed on site. Submission of this detail prior to occupation in the case of new building works or prior to the use commencing in the case of changes of use will protect the amenity of occupiers of the development and also the locality generally and ensure that the development accords with the Development Control Policies Development Plan Document Policy DC61.
6.The proposed 5no. car parking spaces shall be permanently retained for use by occupants of the residential conversion and for no other purposes whatsoever. Reason: To ensure that the car parking is retained for the purposes intended, in the interests of amenity.
7.No building shall be occupied or use commenced until refuse and recycling facilities are provided in accordance with details which shall previously have been submitted to and approved in writing by the Local Planning Authority. The refuse and recycling facilities shall be permanently retained thereafter. Reason:- Insufficient information has been supplied with the application to judge how refuse and recycling will be managed on site. Submission of this detail prior to occupation in the case of new building works or prior to the use commencing in the case of changes of use will protect the amenity of occupiers of the development and also the locality generally and ensure that the development accords with the Development Control Policies Development Plan Document Policy DC61.
8.Changes to the public highway (including permanent or temporary access) Planning approval does not constitute approval for changes to the public highway. Highway Authority approval will only be given after suitable details have been submitted considered and agreed. If new or amended access as required (whether temporary or permanent), there may be a requirement for the diversion or protection of third party utility plant or highway authority assets and it is recommended that early involvement with the relevant statutory undertaker takes place. The applicant must contact Engineering Services on 01708 433751 to discuss the scheme and commence the relevant highway approvals process. Please note that unauthorised work on the highway is an offence. Highway legislation The developer (including their representatives and contractors) is advised that planning consent does not discharge the requirements of the New Roads and Street Works Act 1991 and the Traffic Management Act 2004. Formal notifications and approval will be needed for any highway works (including temporary works of any nature) required during the construction of the development. Please note that unauthorised work on the highway is an offence. Temporary use of the public highway The developer is advised that if construction materials are proposed to be kept on the highway during construction works then they will need to apply for a license from the Council. If the developer requires scaffolding, hoarding or mobile cranes to be used on the highway, a licence is required and Street Management should be contacted make the necessary arrangements. Please note that unauthorised use of the highway for construction works is an offence. Surface water management The developer is advised that surface water from the development in both its temporary and permanent states should not be discharged onto the highway. Failure to prevent such is an offence.
9.The change of use as described in this Prior Approval notification must be commenced not later than three years from the date of this decision.