| No. | Condition Text |
|---|
| 1. | The development to which this consent relates must be commenced not later than three years from the date of this consent.
Reason:-
To comply with the requirements of Section 18(1) of the Planning (Listed Building and Conservation Areas) Act 1990 (as amended by Section 51 of the Planning Compulsory Purchase Act 2004). |
| 2. | Before any investigative opening-up work hereby granted consent is carried out, drawings and a method statement, which demonstrate the exact locations, tools and techniques proposed, are submitted to and approved in writing by the Local Planning Authority.
Reason;
To preserve the character and appearance of the Listed Building and its setting. |
| 3. | Following the approval of Condition 1, the Local Planning Authority shall be notified in writing of the date on which works are proposed to commence on site (at least 14 days prior to such commencement) in order to provide an opportunity, for a site meeting involving a representative from the Local Planning Authority, the applicant/ agent and contractor to consider detailed elements of the works and to allow for inspections during the opening-up works.
Reason;
To preserve the character and appearance of the Listed Building and its setting. |
| 4. | Following the approval of Condition 2, details of any necessary repair work agreed following the opening-up works shall be submitted to and approved in writing by the local planning authority and the repairs shall then be carried in accordance with the approved details.
Reason;
To preserve the character and appearance of the Listed Building and its setting. |
| 5. | The raking out of loose mortar for the purpose of re-pointing hereby granted consent shall be carried out by tools held in the hand and not by power-driven tools. Details of the extent of the re-pointing and details of the mortar to be used for re- pointing (including mortar mix, colour, texture and pointing finish) shall be submitted to and agreed in writing by the Local Planning Authority before the repointing is carried out. The works shall be carried out only in accordance with the agreed repointing details.
Reason;
To preserve the character and appearance of the Listed Building and its setting. |
| 6. | Statement Required by Article 35(2) of the Town and Country Planning (Development Management) Order 2015: No significant problems were identified during the consideration of the application, and therefore it has been determined in accordance with paragraph 38 of the National Planning Policy Framework. |