1.The development to which this permission relates must be commenced not later than three years from the date of this permission. Reason:- To comply with the requirements of Section 91 of the Town and Country Planning Act 1990 (as amended by Section 51 of the Planning and Compulsory Purchase Act 2004).
2.The development hereby permitted shall not be carried out otherwise than in complete accordance with the approved plans (as set out on page one of this decision notice). Reason:- For the avoidance of doubt and to ensure that the development is carried out as approved.
3.All new external finishes shall be carried out in materials to match those of the existing building(s) to the satisfaction of the Local Planning Authority. Reason:- To safeguard the appearance of the premises and the character of the immediate area.
4.Notwithstanding the provisions of the Town and Country Planning (General Permitted Development) (England) Order 2015, no window or other opening (other than those shown on the submitted and approved plan,) shall be formed in the flank wall(s) of the building(s) hereby permitted, unless specific permission under the provisions of the Town and Country Planning Act 1990 has first been sought and obtained in writing from the Local Planning Authority. Reason:- In order to ensure a satisfactory development that will not result in any loss of privacy or damage to the environment of neighbouring properties which exist or may be proposed in the future.
5.The roof area of the extension hereby permitted shall not be used as a balcony, roof garden or similar amenity area without the grant of further specific permission from the Local Planning Authority. Reason:- In the interests of the amenity of the occupiers of neighbouring dwelling.
6.No demolition or development shall take place until a written scheme of investigation (WSI) has been submitted to and approved by the local planning authority in writing. For land that is included within the WSI, no demolition or development shall take place other than in accordance with the agreed WSI, which shall include the statement of significance and research objectives, and A. The programme and methodology of site investigation and recording and the nomination of a competent person(s) or organisation to undertake the agreed works. B. Where appropriate, details of a programme for delivering related positive public benefits. C. The programme for post-investigation assessment and subsequent analysis, publication & dissemination and deposition of resulting material. This part of the condition shall not be discharged until these elements have been fulfilled in accordance with the programme set out in the WSI Reason: Heritage assets of archaeological interest survive on the site. Insufficient information has been supplied with the application in relation to these matters. The planning authority wishes to secure the provision of archaeological investigation and the subsequent recording of the remains prior to development (including historic buildings recording), in accordance with the NPPF.
7.For any development where a flood risk is identified, the Council as the Lead Local Flood Authority want to see developers consider and implement flood resilience/resistance measures into the buildings themselves. This is not to stop development but to ensure the protection for future residents is maintained and enhanced. The following measures are strongly recommended, although this list is not exhaustive:- - Raising the level of the building by at least 300mm above local levels; - Waterproof membrane in the ground floor; - Waterproof plaster and waterproofing to ground floor; - Electrics from the upstairs down and sockets high up off the ground floor; - Non return valves on the sewerage pipes; - Emergency escape plan for each individual property; - Air brick covers; and - Movable flood barriers for entrances
8.The implementation of both D0460.24 and P0033.25 at the same time may invalidate one or both of these applications and as a result a fresh planning application may be required as the proposal would be contrary to the approved plans and the resultant volume may exceed the 50 cubic metres allowance allowed for the proposed loft extension under permitted development.
9.In reference to submission and dischage of conditon 6, you are adviced that the written scheme of investigation will need to be prepared and implemented by a suitably professionally accredited archaeological practice in accordance with Historic England's Guidelines for Archaeological Projects in Greater London. This condition is exempt from deemed discharge underschedule 6 of The Town and Country Planning (Development Management Procedure) (England) Order 2015.
10.This planning permission does not remove the need to obtain any separate consent of the owner of the adjoining property prior to commencing building works on, under, above or immediately adjacent to their property (e.g. foundations or guttering). The Party Wall Etc. Act 1996 contains requirements to serve notice on adjoining owners of property under certain circumstances, and a procedure exists for resolving disputes. This is a matter of civil law between the two parties, and the Local Planning Authority are not involved in such matters. A free guide called "The Party Wall Etc Act 1996: Explanatory Booklet" is available on the website of the Department for Communities and Local Government. https://www.gov.uk/government/publications/the-party-wall-etc-act-1996-revised-explanatory-booklet
11.You should also check whether the development requires separate Building Regulation consent. Information is available on the Building Control webpages and the team is available between 9am and 10am Monday to Friday via 01708 432700.
12.Statement Required by Article 35(2) of the Town and Country Planning (Development Management) Order 2015: No significant problems were identified during the consideration of the application, and therefore it has been determined in accordance with paragraph 38 of the National Planning Policy Framework.