1.The development to which this permission relates must be commenced not later than three years from the date of this permission. Reason:- To comply with the requirements of Section 91 of the Town and Country Planning Act 1990 (as amended by Section 51 of the Planning and Compulsory Purchase Act 2004).
2.The development hereby permitted shall not be carried out otherwise than in complete accordance with the approved plans (as set out on page one of this decision notice). Reason:- The Local Planning Authority consider it essential that the whole of the development is carried out and that no departure whatsoever is made from the details approved, since the development would not necessarily be acceptable if partly carried out or carried out differently in any degree from the details submitted. Also, in order that the development accords with Development Control Policies Development Plan Document Policy DC61.
3.The proposed extension hereby approved shall be constructed in accordance with the materials detailed under Section 9 of the application form unless otherwise agreed in writing by the Local Planning Authority. Reason: To ensure that the appearance of the proposed development will harmonise with the character of the surrounding area and comply with Development Control Policies Development Plan Document Policy DC61.
4.Before the extension hereby permitted is first occupied, the area set aside for car parking shall be laid out and surfaced to the satisfaction of the Local Planning Authority and retained permanently thereafter for the accommodation of vehicles visiting the site and shall not be used for any other purpose. Reason:- To ensure that car parking accommodation is made permanently available to the standards adopted by the Local Planning Authority in the interest of highway safety, and that the development accords with the Development Control Policies Development Plan Document Policy DC33.
5.No works shall take place in relation to any of the development hereby approved until details, are submitted to and agreed in writing by the Local Planning Authority, setting out suitable gas protection measures to be employed on site including, but not necessarily limited to, the installation of a suitable gas resistant membrane. The gas protection measures shall be carried out in strict accordance with the agreed details. Within three months of completion of installation, a 'Verification Report' must be submitted to the Local Planning Authority demonstrating that the works have been carried out satisfactorily. Reason:- Insufficient information has been supplied with the application to ensure that the occupants of the development are not subject to any risks from soil gas and/or vapour in accordance with Development Control Policies Development Plan Document Policy DC53.
6.Due to the presence of UK Power Network and National Grid apparatus and cables in proximity to the application site, the applicant is advised to contact both companies before any works are carried out to ensure that the aforementioned apparatus and cables are not affected by the development. Further information on safe digging techniques around electricity cables can also be found at www.hse.gov.uk.
7.The proposal is liable for the Mayor of London Community Infrastructure Levy (CIL). Based upon the information supplied with the application, the CIL payable would be £8,160 (this figure may go up or down, subject to indexation). CIL is payable within 60 days of commencement of development. A Liability Notice will be sent to the applicant (or anyone else who has assumed liability) shortly and you are required to notify the Council of the commencement of the development before works begin. Further details with regard to CIL are available from the Council's website.
8.Statement Required by Article 35 (2) of the Town and Country Planning (Development Management Procedure) (England) Order 2015: No significant problems were identified during the consideration of the application, and therefore it has been determined in accordance with paragraphs 186-187 of the National Planning Policy Framework 2012.