No.Condition Text
1.The development to which this permission relates must be commenced not later than three years from the date of this permission. Reason:- To comply with the requirements of Section 91 of the Town and Country Planning Act 1990 (as amended by Section 51 of the Planning and Compulsory Purchase Act 2004).
2.Prior to any above ground works, a written specification of external walls and roof materials to be used in the construction of the building(s) shall be submitted to and approved in writing by the Local Planning Authority and thereafter the development shall be constructed with the approved materials. Reason:- Insufficient information has been supplied with the application to judge the appropriateness of the materials to be used. Submission of a written specification prior to any above ground works will ensure that the appearance of the proposed development will harmonise with the character of the surrounding area.
3.The development hereby permitted shall not be carried out otherwise than in complete accordance with the approved plans (as set out on page one of this decision notice). Reason:- For the avoidance of doubt and to ensure that the development is carried out as approved.
4.Before the building(s) hereby permitted is first occupied, the area set aside for car parking and turning as shown on the approved plans, including Drawing No. 1244.28-PA-052 Revision D, shall be laid out and surfaced to the satisfaction of the Local Planning Authority and retained permanently thereafter for the proposed dwellings and shall not be used for any other purpose. Reason:- To ensure that car parking accommodation is made permanently available to the standards adopted by the Local Planning Authority and the permanent availability of the manoeuvring area, in the interest of highway safety.
5.Prior to the first occupation of the dwellings hereby permitted, a scheme of hard and soft landscaping shall be carried out in accordance with the approved plans including Drawing No.'s LB327_D02, LB347_D01 - Soft Landscape Proposals (Sheet 1 of 2) and LB347_D01 - Soft Landscape Proposals (Sheet 2 of 2). All planting, seeding or turfing comprised within the scheme shall be carried out in the first planting season following completion of the development and any trees or plants which within a period of 5 years from completion of the development die, are removed or become seriously damaged or diseased shall be replaced in the next planting season with others of a similar size and species, unless otherwise agreed in writing by the local Planning Authority. Reason:- Reason: To ensure that the development achieves a satisfactory level of landscape quality.
6.Prior to the first occupation of the development hereby approved, details of all proposed walls, fences and boundary treatment shall be submitted to, and approved in writing by, the Local Planning Authority. The boundary development shall then be carried out in accordance with the approved details and retained permanently thereafter to the satisfaction of the Local Planning Authority. Reason: Insufficient information has been supplied with the application to judge the appropriateness of any boundary treatment. Submission of this detail prior to the first occupation of the development hereby approved will protect the visual amenities of the development, prevent undue overlooking of adjoining property.
7.No building shall be occupied or use commenced until external lighting is provided in accordance with details previously submitted to and approved in writing by the Local Planning Authority. The lighting shall be provided and operated in strict accordance with the approved scheme. Reason:- Insufficient information has been supplied with the application to judge the impact arising from any external lighting required in connection with the building or use. Submission of this detail prior to occupation in the case of new building works or prior to the use commencing in the case of changes of use will protect residential amenity and in accordance with the principles of Designing Out Crime.
8.Prior to the first occupation of the dwellings hereby permitted, the proposed bin stores for the dwellings and the communal bin stores shown on drawing No.'s 1244.28-PA-052 Revision D, 1244.28-600 and 1244.28-PA-601 shall be provided to the satisfaction of the Local Planning Authority and retained permanently thereafter to the satisfaction of the Local Planning Authority. Reason: In the interests of highway safety and the amenity of occupiers of the development and in order that the development accords with Policies 24 and 35 of the Havering Local Plan.
9.Prior to the first occupation of the dwellings hereby permitted, a parking management plan for the site shall be submitted to and approved in writing by the Local Planning Authority and thereafter the parking management plan shall be implemented and shall thereafter remain in perpetuity. Reason: To ensure access to facilitate the servicing arrangements of the site, in the interests of highway safety and the amenity of occupiers of the development and in order that the development accords with Policies 24 and 35 of the Havering Local Plan.
10.Prior to the first occupation of the dwellings hereby permitted, details of a maintenance regime to maintain the communal areas within the site, including the children's play equipment and landscaped areas shall be submitted to and approved in writing by the Local Planning Authority and thereafter the maintenance regime shall be implemented and shall thereafter be remain in perpetuity. Reason: To ensure that the communal areas within the site, including the children's play space, are maintained to protect residential amenity and the development achieves a satisfactory level of landscape quality.
11.Prior to the first occupation of individual dwellings their associated on-site parking/turning shall be laid out in accordance with the approved plan and thereafter retained for that specific use. Reason: To ensure the permanent availability of the parking / manoeuvring area, in the interests of highway safety.
12.The proposed first floor bathroom windows on the rear elevation of Units A-D as shown on Drawing No.'s 1244.28-PA-100 Revision A and 1244.28-PA-200 shall be permanently glazed with obscure glass not less than level 4 on the standard scale of obscurity and shall thereafter be maintained. Reason:- In the interests of privacy.
13.All hard surfaces hereby approved as part of the development (including any sub-base) shall be made of porous materials or provision shall be made to direct run-off water from the hard surface to a permeable or porous area or surface within the curtilage of the application site. Reason:- In order to ensure no water run-off from the hard surface which would contribute to risk of flooding.
14.1) Prior to the commencement of any works pursuant to this permission the developer shall submit for the written approval of the Local Planning Authority; a) A Phase I (Desktop Study) Report documenting the history of the site, its surrounding area and the likelihood of contaminants, their type and extent incorporating a Site Conceptual Model. b) A Phase II (Site Investigation) Report if the Phase I Report confirms the possibility of a significant risk to any sensitive receptors. This is an intrusive site investigation including factors such as chemical testing, quantitative risk assessment and a description of the sites ground conditions. An updated Site Conceptual Model should be included showing all the potential pollutant linkages and an assessment of risk to identified receptors. c) A Phase III (Remediation Strategy) Report if the Phase II Report confirms the presence of a significant pollutant linkage requiring remediation. A detailed remediation scheme to bring the site to a condition suitable for the intended use by removing unacceptable risks to all receptors must be prepared, and is subject to the approval in writing of the Local Planning Authority. The scheme must include all works to be undertaken, proposed remediation objectives and remediation criteria, timetable of works, site management procedures and procedure for dealing with previously unidentified any contamination. The scheme must ensure that the site will not qualify as contaminated land under Part 2A of the Environmental Protection Act 1990 in relation to the intended use of the land after remediation. d) Following completion of measures identified in the approved remediation scheme mentioned in 1(c) above, a "Verification Report" that demonstrates the effectiveness of the remediation carried out, any requirement for longer-term monitoring of contaminant linkages, maintenance and arrangements for contingency action, must be produced, and is subject to the approval in writing of the Local Planning Authority. Reason: To protect those engaged in construction and occupation of the development from potential contamination and in order that the development accords with Policy 34 of the Havering Local Plan.
15.(a) If, during development, contamination not previously identified is found to be present at the site then no further development (unless otherwise agreed in writing with the local planning authority) shall be carried out until a remediation strategy detailing how this unsuspected contamination shall be dealt with has been submitted to and approved in writing by the local planning authority. The remediation strategy shall be implemented as approved. (b) Following completion of the remediation works as mentioned in (a) above, a 'Verification Report' must be submitted demonstrating that the works have been carried out satisfactorily and remediation targets have been achieved. Reason: To ensure that any previously unidentified contamination found at the site is investigated and satisfactorily addressed in order to protect those engaged in construction and occupation of the development from potential contamination.
16.a) Prior to the commencement of any groundworks or development of the site, details shall be submitted to and agreed in writing by the Local Planning Authority setting out suitable gas protection measures to be employed on site including, but not necessarily limited to, the installation of a suitable gas resistant membrane, in compliance with BS 8485:2015. The gas protection measures shall be carried out in strict accordance with the agreed details. b) Upon completion of installation, a 'Verification Report' must be submitted demonstrating that the works have been carried out. Reason: Insufficient information has been supplied with the application to judge the risk arising from landfill gases (methane and carbon dioxide). Submission of an assessment prior to commencement will protect people on or close to the site from the risks associated with migrating landfill gas, and will ensure that the development accords with Policy 34 of the Havering Local Plan.
17.No demolition or development shall take place until a written scheme of investigation (WSI) has been submitted to and approved by the local planning authority in writing. For land that is included within the WSI, no demolition or development shall take place other than in accordance with the agreed WSI, which shall include the statement of significance and research objectives, and A. The programme and methodology of site investigation and recording and the nomination of a competent person(s) or organisation to undertake the agreed works B. Where appropriate, details of a programme for delivering related positive public benefits C. The programme for post-investigation assessment and subsequent analysis, publication & dissemination and deposition of resulting material. This part of the condition shall not be discharged until these elements have been fulfilled in accordance with the programme set out in the WSI. Reason: To conserve the archaeological interest on the site and in order that the development accords with Policy 28 of the Havering Local Plan, Policy HC1 of the London Plan and the National Planning Policy Framework.
18.No works shall take place in relation to any of the development hereby approved until a Construction Method Statement to control the adverse impact of the development on the amenity of the public and nearby occupiers is submitted to and approved in writing by the Local Planning Authority. The Construction Method statement shall include details of: a) parking of vehicles of site personnel and visitors; b) storage of plant and materials; c) dust management controls; d) measures for minimising the impact of noise and ,if appropriate, vibration arising from construction activities; e) predicted noise and, if appropriate, vibration levels for construction using methodologies and at points agreed with the Local Planning Authority; f) scheme for monitoring noise and if appropriate, vibration levels using methodologies and at points agreed with the Local Planning Authorities; g) siting and design of temporary buildings; h) scheme for security fencing/hoardings, depicting a readily visible 24-hour contact number for queries or emergencies; i) details of disposal of waste arising from the construction programme, including final disposal points. The burning of waste on the site at any time is specifically precluded. And the development shall be carried out in accordance with the approved scheme and statement. Reason:- Insufficient information has been supplied with the application in relation to the proposed construction methodology. Submission of details prior to commencement will ensure that the method of construction protects residential amenity.
19.Before the development hereby permitted is first commenced, vehicle cleansing facilities to prevent mud being deposited onto the public highway during construction works shall be provided on site in accordance with details to be first submitted to and approved in writing by the Local Planning Authority. The approved facilities shall be retained thereafter and used at relevant entrances to the site throughout the duration of construction works. If mud or other debris originating from the site is deposited in the public highway, all on-site operations shall cease until it has been removed. The submission will provide; a) A plan showing where vehicles will be parked within the site to be inspected for mud and debris and cleaned if required. The plan should show where construction traffic will access and exit the site from the public highway. b) A description of how the parking area will be surfaced, drained and cleaned to prevent mud, debris and muddy water being tracked onto the public highway; c) A description of how vehicles will be checked before leaving the site - this applies to the vehicle wheels, the underside of vehicles, mud flaps and wheel arches. d) A description of how vehicles will be cleaned. e) A description of how dirty/ muddy water be dealt with after being washing off the vehicles. f) A description of any contingency plan to be used in the event of a break-down of the wheel washing arrangements. Reason:- Insufficient information has been supplied with the application in relation to wheel washing facilities. Submission of details prior to commencement will ensure that the facilities provided prevent materials from the site being deposited on the adjoining public highway, in the interests of highway safety and the amenity of the surrounding area.
20.The development hereby approved shall be provided with air source heat pumps, which shall be designed to comply with "MCS Planning Standards for Permitted Development Installations of Wind Turbines and Air Source Heat Pumps on Domestic Premises". The air source heat pumps shall be provided on site prior to first occupation of the dwellings. Reason: In the interests of sustainability and amenity.
21.Prior to the first occupation of the dwellings hereby permitted, the cycle storage shown on drawing No.'s 1244.28-PA-052D and 1244.28-600 shall be provided to the satisfaction of the Local Planning Authority and retained permanently thereafter to the satisfaction of the Local Planning Authority. Reason:- In the interests of providing a wide range of facilities for non-motor car residents and sustainability.
22.Notwithstanding the provisions of the Town and Country Planning (General Permitted Development) (England) Order 2015, no window or other opening (other than those shown on the submitted and approved plan) shall be formed in the flank wall(s) of the building(s) and the outbuildings hereby permitted, unless specific permission under the provisions of the Town and Country Planning Act 1990 has first been sought and obtained in writing from the Local Planning Authority. Reason:- In order to ensure a satisfactory development that will not result in any loss of privacy or damage to the environment of neighbouring properties which exist or may be proposed in the future.
23.Notwithstanding the provisions of the Town and Country Planning (General Permitted Development) (England) Order 2015 (Order) or any other order replacing or amending the said Order other than porches erected in accordance with the Order, no extension or enlargement (including additions to roofs) shall be made to the dwellinghouse(s) hereby permitted and no outbuildings shall be erected in the rear garden area of the dwellings, with the exception of ancillary structures up to 10 cubic metres in volume, without the express permission in writing of the Local Planning Authority. Reason:- In the interests of amenity and to enable the Local Planning Authority to retain control over future development.
24.All building operations in connection with the construction of external walls, roof, and foundations; site excavation or other external site works; works involving the use of plant or machinery; the erection of scaffolding; the delivery of materials; the removal of materials and spoil from the site, and the playing of amplified music shall only take place between the hours of 8.00am and 6.00pm Monday to Friday, and between 8.00am and 1.00pm on Saturdays and not at all on Sundays and Bank Holidays/Public Holidays. Reason:- To protect residential amenity.
25.All dwellings hereby approved shall be constructed to comply with Part M4(2) of the Building Regulations - Accessible and Adaptable Dwellings. Reason: In order to comply with Policy 7 of the Havering Local Plan and Policy D7 of the London Plan.
26.All dwellings hereby approved shall comply with Regulation 36 (2)(b) and Part G2 of the Building Regulations - Water Efficiency. Reason: In order to comply with Policy SI 5 of the London Plan.
27.All residential parking spaces within the development hereby approved shall include provision of infrastructure for electric or Ultra-Low Emission vehicles, of which a minimum of two spaces shall have active charging facilities, with passive provision for all remaining spaces. Such provision is to be made prior to the first occupation of the dwellings hereby permitted. Reason: Provision prior to first occupation of the proposed dwellings hereby permitted will ensure that the development adequately incorporates measures to allow the use of electric vehicles by future occupiers in accordance with Policy T6.1 of the London Plan.
28.Statement Required by Article 35 (2) of the Town and Country Planning (Development Management Procedure) (England) Order 2015: In accordance with paragraph 38 of the National Planning Policy Framework, improvements required to make the proposal acceptable were negotiated with Union4 Planning via email during the course of this application. The revisions involved altering the servicing arrangements and landscaping scheme. The amendments were subsequently submitted on 15th July, 25th November, 11th and 12th December 2024.
29.The proposal is liable for the Mayor of London Community Infrastructure Levy (CIL). The Mayoral CIL levy rate for Havering is £25/m² and is chargeable for each additional square metre of residential gross internal [floor] (GIA). Based upon the information supplied with the application, £10,100 would be payable due to result in a four new residential properties with 404m² of GIA, however this may be adjusted subject to indexation. The proposal is also liable for Havering Council's CIL. Havering's CIL charging rate for residential is £125m² (Zone A) for each additional square metre of GIA. Based upon the information supplied with the application, £50,500 would be payable, subject to indexation. These charges are levied under s.206 of the Planning Act 2008. CIL is payable within 60 days of commencement of development. A Liability Notice will be sent to the applicant (or anyone else who has assumed liability) shortly and you are required to notify the Council of the commencement of the development before works begin. Further details with regard to CIL are available from the Council's website. You are also advised to visit the planning portal website where you can download the appropriate document templates at http://www.planningportal.gov.uk/planning/applications/howtoapply/whattosubmit/cil
30.Before occupation of the residential/ commercial unit(s) hereby approved, it is a requirement to have the property/properties officially Street Named and Numbered by our Street Naming and Numbering Team. Official Street Naming and Numbering will ensure that that Council has record of the property/properties so that future occupants can access our services. Registration will also ensure that emergency services, Land Registry and the Royal Mail have accurate address details. Proof of having officially gone through the Street Naming and Numbering process may also be required for the connection of utilities. For further details on how to apply for registration see: https://www.havering.gov.uk/Pages/Services/Street-names-and-numbering.aspx
31.The written scheme of investigation will need to be prepared and implemented by a suitably professionally accredited archaeological practice in accordance with Historic England's Guidelines for Archaeological Projects in Greater London. This condition is exempt from deemed discharge under schedule 6 of The Town and Country Planning (Development Management Procedure) (England) Order 2015.