| 1. | The development to which this permission relates must be commenced not later than three years from the date of this permission.
Reason:- To comply with the requirements of Section 91 of the Town and Country Planning Act 1990 (as amended by Section 51 of the Planning and Compulsory Purchase Act 2004). |
| 2. | The development hereby permitted shall not be carried out otherwise than in complete accordance with the approved plans (as set out on page one of this decision notice).
Reason:- For the avoidance of doubt and to ensure that the development is carried out as approved. |
| 3. | No works shall take place in relation to any of the development hereby approved until samples of all materials to be used in the external construction of the building are submitted to and approved in writing by the Local Planning Authority and thereafter the development shall be constructed with the approved materials.
Reason:-
Insufficient information has been supplied with the application to judge the appropriateness of the materials to be used. Submission of samples prior to commencement will ensure that the appearance of the proposed development will harmonise with the character of the surrounding area. |
| 4. | No works shall take place in relation to the development hereby approved until there has been submitted to and approved by the Local Planning Authority a scheme of hard and soft landscaping. The soft landscaping scheme shall include the following:
a) Planting plan;
b) Written specifications (including cultivation and other operations associated with trees, plants and grass); and
c) Schedules of plants and trees, setting out the species, sizes, numbers/densities and soil depths.
The scheme shall also include a programme setting out how the plan will be put into practice including measures for protecting plants and trees both during and after development has finished.
The new planting shall be carried out in accordance with BS 8545 (2014) 'Trees: from nursery to independence in the landscape' in the first planting and/or seeding season following the first occupation of the residential buildings hereby permitted or the substantial completion of the development, whichever is the sooner and shall comply with the requirements specified in BS 3936 (1992) 'Specification of Nursery Stock Part 1 Trees and Shrubs', and in BS 4428 (1989) 'Recommendations for General Landscape Operations'.
None of the new trees, plants or shrubs planted shall be lopped or topped within a period of five years from the completion of the development. Any trees, plants or shrubs, which, within a period of five years from the completion of the development die, are removed, or become seriously damaged or diseased, shall be replaced in the next planting season, in accordance with the approved scheme. The approved landscaping scheme shall be maintained thereafter unless otherwise agreed in writing by the local Planning Authority.
Reason:- Insufficient information has been supplied with the application to judge the appropriateness of the hard and soft landscaping proposed. Submission of a scheme prior to commencement will ensure that the development achieves a satisfactory level of landscape quality. |
| 5. | Prior to the commencement of the development hereby approved, details of all proposed walls, fences and boundary treatment shall be submitted to, and approved in writing by, the Local Planning Authority. The boundary development shall then be carried out in accordance with the approved details and retained permanently thereafter to the satisfaction of the Local Planning Authority.
Reason:
Insufficient information has been supplied with the application to judge the appropriateness of any boundary treatment. Submission of this detail prior to commencement will protect the visual amenities of the development and prevent undue overlooking of adjoining property. |
| 6. | The proposed flank windows of the dwellinghouse as shown on drawing '04G' accompanying the application, shall be permanently glazed with obscure glass not less than level 3 on the standard scale of obscurity and shall thereafter be maintained and permanently fixed shut and thereafter maintained with the exception of any top hung fanlights.
Reason: In the interests of privacy. |
| 7. | Notwithstanding the provisions of the Town and Country Planning (General Permitted Development) (England) Order 2015, no window or other opening (other than those shown on the submitted and approved plans) shall be formed in the flank wall of the building hereby permitted, unless specific permission under the provisions of the Town and Country Planning Act 1990 has first been sought and obtained in writing from the Local Planning Authority.
Reason:-
In order to ensure a satisfactory development that will not result in any loss of privacy or damage to the environment of neighbouring properties which exist or may be proposed in the future. |
| 8. | Notwithstanding the provisions of the Town and Country Planning (General Permitted Development) (England) Order 2015, no extension or enlargement (including additions to roofs) shall be made to the new dwellinghouse hereby permitted, or any detached building erected, without the express permission in writing of the Local Planning Authority.
Reason:-
In the interests of amenity and to enable the Local Planning Authority to retain control over future development. |
| 9. | Before the building hereby permitted is first occupied, the area set aside for car parking shall be laid out and surfaced to the satisfaction of the Local Planning Authority and retained permanently thereafter for the accommodation of vehicles visiting the site and shall not be used for any other purpose.
Reason:-
To ensure that car parking accommodation is made permanently available to the standards adopted by the Local Planning Authority in the interest of highway safety. |
| 10. | Any new or replacement hard surfacing shall be made of porous materials or provision shall be made to direct run-off water from the hard surface to a permeable or porous area or surface within the curtilage of the dwellinghouse.
Reason:-
In order to ensure no water run-off from the hard surface which would contribute to risk of flooding |
| 11. | All off street residential car parking spaces must provide infrastructure for electric or Ultra-Low Emission vehicles. At least 1 space shall have active charging facilities, with passive provision for all remaining spaces.
Reason:- To minimise the impact of transport emissions on local air quality. |
| 12. | No demolition or construction works, or deliveries, into the site shall take place other than between the hours of 08.00 to 18.00 on Monday to Friday and 08.00 to 13.00 hours on Saturdays unless agreed in writing with the local planning authority. No demolition or construction works, or deliveries shall take place on Sundays, Bank or Public Holidays unless otherwise agreed in writing by the local planning authority.
Reason: To protect residential amenity. |
| 13. | Minor (up to 9 units):
All dwellings hereby approved shall be constructed to comply with Part M4(2) of the Building Regulations - Accessible and Adaptable Dwellings.
Reason: In order to comply with national optional technical standards as required by Policy D7 of the London Plan. |
| 14. | All dwellings hereby approved shall comply with Regulation 36 (2)(b) and Part G2 of the Building Regulations - Water Efficiency.
Reason: In order to comply with national optional technical standards as required by Policy SI5 of the London Plan. |
| 15. | Any boilers installed in the dwelling(s) hereby approved shall be Ultra-Low NOx boilers with maximum NOx Emissions less than 40 mg/kWh. Where any installations do not meet this emissions standard it should not be operated without the fitting of suitable NOx abatement equipment or technology as determined by a specialist to ensure comparable emissions. The installation of the boilers shall be carried out in strict accordance with these details and shall thereafter be permanently retained.
If the heating strategy is to be provided by an Air Source Heat Pump, or similar, they shall be designed to comply with the provisions of the Microgeneration Installation Standard: MCS 020 "MCS Planning Standards for Permitted Development Installations of Wind Turbines and Air Source Heat Pumps on Domestic Premises". The air source heat pumps shall be provided on site prior to first occupation of the dwellings. Any installation not meeting this standard will require a separate application for planning permission.
Reason: To reduce impact on building emissions on local air quality and to ensure any air source heat pumps installed maintain amenity. |
| 16. | The refuse and recycling facilities shown on the drawings '13E' submitted as part of the application shall be carried out in accordance with the approved details and retained permanently to the satisfaction of the Local Planning Authority.
Reason:-
In the interests of managing refuse and recycling at the site appropriately. |
| 17. | The cycling facilities shown on the drawing '13E' submitted as part of the application shall be carried out in accordance with the approved details and retained permanently to the satisfaction of the Local Planning Authority.
Reason:-
In the interests of providing a wide range of facilities for non-motor car residents and sustainability. |
| 18. | The proposal is liable for the Mayor of London Community Infrastructure Levy (CIL). The Mayoral CIL levy rate for Havering is 25/m² and is chargeable for each additional square metre of residential gross internal [floor] (GIA). Based upon the information supplied with the application, £1,750 would be payable due to result in a new property with a gross internal floor area of 70m² of GIA, however this may be adjusted subject to indexation.
The proposal is also liable for Havering Council's CIL. Havering's CIL charging rate for residential is £125m² (Zone A for each additional square metre of GIA. Based upon the information supplied with the application, £8,750 would be payable, subject to indexation.
These charges are levied under s.206 of the Planning Act 2008. CIL is payable within 60 days of commencement of development. A Liability Notice will be sent to the applicant (or anyone else who has assumed liability) shortly and you are required to notify the Council of the commencement of the development before works begin. Further details with regard to CIL are available from the Council's website. |
| 19. | Statement Required by Article 35 (2) of the Town and Country Planning (Development Management Procedure) (England) Order 2015: In accordance with paragraph 38 of the National Planning Policy Framework, improvements required to make the proposal acceptable were negotiated with the agents via email. The revisions involved amending the design of the proposed development. The amendments were subsequently submitted on 17/07/2025. |