| No. | Condition Text |
|---|
| 1. | The concrete surface to the access road hereby permitted shall be removed together with all resulting materials within 14 days of the date of failure to meet any one of the requirements set out in i) to iv) below:
i) Within 3 months of the date of this decision a scheme for surface water drainage shall have been submitted for the written approval of the local planning authority and the scheme shall include a timetable for its implementation and maintenance.
ii) If within 5 months of the date of this decision the local planning authority refuse to approve the scheme or fail to give a decision within the prescribed period, an appeal shall have been made to, and accepted as validly made by, the Secretary of State.
iii) If an appeal is made in pursuance of ii) above, that appeal shall have been finally determined and the submitted scheme shall have been approved by the Secretary of State.
iv) The approved scheme shall have been carried out and completed in accordance with the approved timetable.
Upon implementation of the approved scheme specified in this condition, that scheme shall thereafter be maintained.
In the event of a legal challenge to this decision, or to a decision made pursuant to the procedure set out in this condition, the operation of the time limits specified in this condition will be suspended until that legal challenge has been finally determined |
| 2. | Notwithstanding the provisions of Class A in Part 2 of Schedule 2 to the Town and Country Planning (General Permitted Development) (England) Order 2015 (or any order revoking and re-enacting that Order with or without modification), no fences, gates, walls or other means of enclosure shall be erected on the western side of the access road hereby permitted or fronting the A12 highway other than in accordance with details that have previously been submitted to and approved in writing by the local planning authority. |
| 3. | The bund hereby permitted and all resulting materials shall be removed within 14 days of the date of failure to meet any one of the requirements set out in i) to iv) below:
i) Within 3 months of the date of this decision a scheme of landscaping for the bund shall have been submitted for the written approval of the local planning authority. The scheme shall include details of re-profiling the bund, soft landscape works (including planting plans, written specifications and schedules of plants noting species, plant sizes and numbers/densities), a timetable for its implementation and a programme of maintenance for a minimum period of 5 years.
ii) If within 5 months of the date of this decision the local planning authority refuse to approve the scheme or fail to give a decision within the prescribed period, an appeal shall have been made to, and accepted as validly made by, the Secretary of State.
iii) If an appeal is made in pursuance of ii) above, that appeal shall have been finally determined and the submitted scheme shall have been approved by the Secretary of State.
iv) The approved scheme shall have been carried out and completed in accordance with the approved timetable.
Upon implementation of the approved scheme specified in this condition, that scheme shall thereafter be maintained.
In the event of a legal challenge to this decision, or to a decision made pursuant to the procedure set out in this condition, the operation of the time limits specified in this condition will be suspended until that legal challenge has been finally determined |
| 4. | The schedule of landscape maintenance, approved in compliance with condition 3 above, shall be carried out in accordance with the approved details. Any trees or plants which within a period of 5 years from completion of the landscaping scheme die, are removed or become seriously damaged or diseased shall be replaced in the next planting season with plants of a similar size and species |