The London Borough Of Havering - Home page

No.Condition Text
1.The development to which this permission relates must be commenced not later than three years from the date of this permission. Reason:- To comply with the requirements of Section 91 of the Town and Country Planning Act 1990 (as amended by Section 51 of the Planning and Compulsory Purchase Act 2004).
2.The development hereby permitted shall not be carried out otherwise than in complete accordance with the approved plans (as set out on page one of this decision notice); unless where otherwise required by another condition. Reason:- For the avoidance of doubt and to ensure that the development is carried out as approved.
3.No demolition works shall take place in relation to any of the development hereby approved until a Construction Method Statement to control the adverse impact of the development on the amenity of the public and nearby occupiers (specifically the adjacent High School) is submitted to and approved in writing by the Local Planning Authority. The Construction Method statement shall include details of: a) parking of vehicles of site personnel and visitors; b) storage of plant and materials; c) dust management controls; d) measures for minimising the impact of noise and ,if appropriate, vibration arising from construction activities; e) predicted noise and, if appropriate, vibration levels for construction using methodologies and at points agreed with the Local Planning Authority; f) scheme for monitoring noise and if appropriate, vibration levels using methodologies and at points agreed with the Local Planning Authorities; g) siting and design of temporary buildings; h) scheme for security fencing/hoardings, depicting a readily visible 24-hour contact number for queries or emergencies; i) details of disposal of waste arising from the construction programme, including final disposal points. The burning of waste on the site at any time is specifically precluded. j) details of the impact and management of access to the school at all times. And the development shall be carried out in accordance with the approved scheme and statement. Reason:- Insufficient information has been supplied with the application in relation to the proposed construction methodology. Submission of details prior to commencement will ensure that the method of construction protects residential amenity and that of access to the adjacent High School. It will also ensure that the development accords with Local Plan policies 23, 24 and 34.
4.The proposed development hereby approved shall be constructed in accordance with the materials detailed within the submitted application form unless otherwise agreed in writing by the Local Planning Authority. Reason: To ensure that the appearance of the proposed development will harmonise with the character of the surrounding area.
5.Before the building(s) hereby permitted is first occupied, the area set aside for refuse and recycling facilities shall be laid out and provided to the satisfaction of the Local Planning Authority Reason:- To protect the amenity of occupiers of the development and also the locality generally and ensure that the development accords with Local Plan policy 35.
6.Before the building(s) hereby permitted is first occupied, the area set aside for car parking shall be laid out and surfaced to the satisfaction of the Local Planning Authority and retained permanently thereafter for the accommodation of vehicles visiting the site and shall not be used for any other purpose. Reason:- To ensure that car parking accommodation is made permanently available to the standards adopted by the Local Planning Authority in the interest of highway safety, and that the development accords with Local Plan policy 24.
7.Notwithstanding the provisions of the Town and Country Planning (General Permitted Development) (England) Order 2015, - or any other development order - other than porches erected in accordance with the Order, no extension or enlargement (including additions to roofs) shall be made to the dwellinghouses hereby permitted, or any detached building erected, without the express permission in writing of the Local Planning Authority. Reason:- In the interests of amenity and to enable the Local Planning Authority to retain control over future development, and in order that the development accords with Local Plan policy 26.
8.Notwithstanding the provisions of the Town and Country Planning (General Permitted Development) (England) Order 2015 the outbuildings hereby permitted shall be used only for purposes incidental to the enjoyment of the dwelling house and not for any trade or business nor as living accommodation. Reason:- To restrict the use to one compatible with a residential area, and in order that the development accords with Local Plan policies 7 and 26.
9.The new dwelling hereby approved shall be designed to ensure that the internal water consumption does not exceed a maximum of 105 litres per day to comply with London Plan policy SI5 and Regulation 36 (2)(b) and Part G2 of the Building Regulations - Water Efficiency. Reason: In order to comply with Policy SI 5 of the London Plan (2021).
10.Prior to the first occupation of the development, details shall be submitted to and agreed in writing by the Local Planning Authority for the installation of Ultra-Low NOx boilers with maximum NOx Emissions less than 40 mg/kWh. Where any installations do not meet this emissions standard it should not be operated without the fitting of suitable NOx abatement equipment or technology as determined by a specialist to ensure comparable emissions. The installation of the boilers shall be carried out in strict accordance with the agreed details and shall thereafter be permanently retained. Following installation emissions certificates will need to be provided to the Local Planning Authority to verify boiler emissions. Reason: To minimise the impact of building emissions on local air quality (Local Plan policies 33 ad 34 and London Plan Policy SI1.
11.The flat roof area of the dwelling hereby permitted shall not be used as a balcony, roof garden or similar amenity area without the grant of further specific permission from the Local Planning Authority. Reason:- In the interests of the amenity of the occupiers of neighbouring dwelling.
12.All hard surfaces hereby approved as part of the development (including any sub-base) shall be made of porous materials or provision shall be made to direct run-off water from the hard surface to a permeable or porous area or surface within the curtilage of the application site. Reason:- In order to ensure no water run-off from the hard surface which would contribute to risk of flooding.
13.The dwelling hereby approved shall be constructed to comply with Part M4(2) of the Building Regulations - Accessible and Adaptable Dwellings. Reason: In order to comply with Policy SI 5 of the London Plan (2021).
14.No demolition works shall take place in relation to any of the development hereby approved until there has been submitted to and approved by the Local Planning Authority a scheme of hard and soft landscaping, which shall include indications of all existing trees and shrubs on the site, and details of any to be retained, together with measures for the protection in the course of development. All planting, seeding or turfing comprised within the scheme shall be carried out in the first planting season following completion of the development and any trees or plants which within a period of 5 years from completion of the development die, are removed or become seriously damaged or diseased shall be replaced in the next planting season with others of a similar size and species, unless otherwise agreed in writing by the local Planning Authority. Reason:- Insufficient information has been supplied with the application to judge the appropriateness of the hard and soft landscaping proposed. Submission of a scheme prior to commencement will ensure that the development achieves a satisfactory level of landscape quality.
15.Notwithstanding the provisions of the Town and Country Planning (General Permitted Development) (England) Order 2015, no window or other opening (other than those shown on the submitted and approved plan,) shall be formed in the flank wall(s) of the building(s) hereby permitted, unless specific permission under the provisions of the Town and Country Planning Act 1990 has first been sought and obtained in writing from the Local Planning Authority. Reason:- In order to ensure a satisfactory development that will not result in any loss of privacy or damage to the environment of neighbouring properties which exist or may be proposed in the future, and in order that the development accords with Local Plan policies 7 and 26.
16.No demolition works shall take place in relation to any of the development hereby approved until, details of all proposed walls, fences and boundary treatment have been submitted to, and approved in writing by, the Local Planning Authority. The boundary development shall then be carried out in accordance with the approved details and retained permanently thereafter to the satisfaction of the Local Planning Authority. Reason: Insufficient information has been supplied with the application to judge the appropriateness of any boundary treatment. Submission of this detail prior to commencement will protect the visual amenities of the development and prevent undue overlooking of adjoining property.
17.All building operations in connection with the construction of external walls, roof, and foundations; site excavation or other external site works; works involving the use of plant or machinery; the erection of scaffolding; the delivery of materials; the removal of materials and spoil from the site, and the playing of amplified music shall only take place between the hours of 8.00am and 6.00pm Monday to Friday, and between 8.00am and 1.00pm on Saturdays and not at all on Sundays and Bank Holidays/Public Holidays. Reason:- To protect residential amenity.
18.The proposed window firs floor flank windows shall be permanently glazed with obscure glass not less than Level 4 on the standard scale of obscurity and shall thereafter be maintained and permanently fixed shut and thereafter maintained, with the exception of any top hung fanlight(s). Reason:- In the interests of privacy.
19.Statement Required by Article 35 (2) of the Town and Country Planning (Development Management Procedure) (England) Order 2015: In accordance with paragraph 38 of the National Planning Policy Framework, improvements required to make the proposal acceptable were negotiated with the Agent on the 21/04/22 to lower the height of the front boundary treatment. The amendments were subsequently submitted on 21/04/22.
20.The proposals would incur a Mayoral CIL contribution of £10,125 at a rate of £25 per sqm (407sqm x 25). The proposal is also liable for the Havering Community Infrastructure Levy (HCIL), which has a charging rate of £125 per square metre of net additional floor space in Zone A (407sqm x 125). The Havering Community Infrastructure Levy contribution would equate to £50,875. Each contribution would be subject to indexation. These charges are levied under s.206 of the Planning Act 2008. CIL is payable within 60 days of commencement of development. A Liability Notice will be sent to the applicant (or anyone else who has assumed liability) shortly and you are required to notify the Council of the commencement of the development before works begin. Further details with regard to CIL are available from the Council's website. You are also advised to visit the planning portal website where you can download the appropriate document templates at: http://www.planningportal.gov.uk/planning/applications/howtoapply/whattosubmit/cil
21.Before occupation of the residential/ commercial unit(s) hereby approved, it is a requirement to have the property/properties officially Street Named and Numbered by our Street Naming and Numbering Team. Official Street Naming and Numbering will ensure that that Council has record of the property/properties so that future occupants can access our services. Registration will also ensure that emergency services, Land Registry and the Royal Mail have accurate address details. Proof of having officially gone through the Street Naming and Numbering process may also be required for the connection of utilities. For further details on how to apply for registration see: https://www.havering.gov.uk/Pages/Services/Street-names-and-numbering.aspx