1.The development hereby permitted shall begin no later than three years from the date of this decision. Reason To comply with the requirements of Section 91 of the Town and Country Planning Act 1990.
2.The development hereby permitted shall not be carried out otherwise than in complete accordance with the following approved plans: PLN 04, PLN 05, PLN 06, PLN 07, and PLN 08. Reason For the avoidance of doubt and to ensure that the development is carried out as approved and is compliant with development plan policy.
3.Before the development hereby approved is occupied, the materials used on the external surfaces of the development must match those used on the external surfaces of the existing property. This applies unless differences are shown on the drawings hereby approved or are required by other conditions on this permission. Reason To ensure the development is carried out in accordance with the consent sought, has an acceptable design and complies with policy 26 of the Havering Local Plan (2021)
4.Any windows located in a wall or roof slope forming a side elevation of the development hereby approved shall only be glazed in obscure glass, with the glass to be obscure to at leave Level 4 on the Pilkington Levels of Privacy, and fixed shut, except for any top hung fan light, which shall be a minimum of 1.7metres above internal finished floor level prior to the first use or occupation of the development hereby permitted and the development shall be retained as such thereafter in perpetuity. In the case of multiple or double-glazed units at least one layer of glass in the relevant units shall be glazed in obscure glass to at least Level 4 on the Pilkington scale. Reason To protect the amenities of neighbouring occupiers and ensure the development complies to policy 7 of the Havering Local Plan (2021)
5.Notwithstanding the provisions of the Town and Country Planning (General Permitted Development) (England) Order 2015, nor any Statutory Instrument which amends, removes or replaces that Order, no window or other opening (other than those shown on the submitted and approved plans) shall be formed in the flank walls of the development hereby permitted without the receipt of a specific planning permission for it from the London Planning Authority. Reason To protect the amenities of neighbouring occupiers and ensure the development complies with policy 7 of the Havering Local Plan (2021)
6.For any development where a flood risk is identified, the Council as the Lead Local Flood Authority want to see developers consider and implement flood resilience/resistance measures into the buildings themselves. This is not to stop development but to ensure the protection for future residents is maintained and enhanced. The following measures are strongly recommended, although this list is not exhaustive:- - Raising the level of the building by at least 300mm above local levels; - Waterproof membrane in the ground floor; - Waterproof plaster and waterproofing to ground floor; - Electrics from the upstairs down and sockets high up off the ground floor; - Non return valves on the sewerage pipes; - Emergency escape plan for each individual property; - Air brick covers; and - Movable flood barriers for entrances
7.Flood Risk Activity Permit The Environmental Permitting (England and Wales) Regulations 2016 require a permit to be obtained for any activities which will take place: · on or within 8 metres of a main river (16 metres if tidal) · on or within 8 metres of a flood defence structure or culvert including any buried elements (16 metres if tidal) · on or within 16 metres of a sea defence · involving quarrying or excavation within 16 metres of any main river, flood defence (including a remote defence) or culvert · in a floodplain more than 8 metres from the river bank, culvert or flood defence structure (16 metres if it's a tidal main river) and you don't already have planning permission. For further guidance please visit https://www.gov.uk/guidance/flood-risk-activities-environmental-permits or contact our National Customer Contact Centre on 03702 422 549 or by emailing enquiries@environment-agency.gov.uk. The applicant should not assume that a permit will automatically be forthcoming once planning permission has been granted, and we advise them to consult with us at the earliest opportunity.
8.With regards to surface water drainage it is the responsibility of the developer to make proper provision for drainage to ground, water courses or a suitable sewer. In respect of surface water it is recommended that the applicant should ensure that storm flows are attenuated or regulated into the receiving public network through on or off site storage. When it is proposed to connect to a combined public sewer, the site drainage should be separate and combined at the final manhole nearest the boundary. Connections are not permitted for the removal of Ground Water. Where the developer proposes to discharge to a public sewer, prior approval from Thames Water Developer Services will be required. They can be contacted on 0845 850 2777.
9.[U]Positive and Proactive Statement[] The Local Planning Authority has acted positively and proactively in determining this application by assessing the proposal against all material planning considerations, including planning policies and any representations which were received. It subsequently determined to grant planning permission in accordance with the National Planning Policy requirement that applications for sustainable development are approved where possible. A detailed analysis of the scheme is set out in the report on the application prepared by officers.
10.Building Regulations You are reminded that this decision notice only addresses requirements under Planning Legislation. You also need to check that whether or not the development requires consent under the Building Regulations, as this is an entirely separate process. Further information on the requirements of the Building Regulations can be found at: https://www.havering.gov.uk/building control.
11.Highways Matters You are reminded that this decision notice only addresses requirements under Planning Legislation. It does not give consent for an permanent or temporary changes to the public highway, the use of the public highway for the storage of materials or placing of apparatus associated with the construction or other processes, nor does it permit the discharge of surface water onto the public highway. You are encouraged to check whether or not works or activities necessitate separate consents under the requirements of other, non-planning legislation at the earliest opportunity by emailing environmentbusinesssupport@havering.gov.uk for further information. Unauthorised work on or use of the public highway and a failure to prevent the discharge of surface water on to the public highway area all an offence.
12.Party Wall Act You are reminded that this decision notice only addresses requirements under Planning Legislation. You also need to check whether or not the development necessitates an agreement under the requirements of the Party Wall etc. Act 1996, as this is an entirely separate process. Further guidance on the Party Wall etc. Act 1996 can be found at: https;//www,gov.uk/housing-local-and-community/party-walls.