No.Condition Text
1.The development to which this permission relates must be commenced not later than three years from the date of this permission. Reason:- To comply with the requirements of Section 91 of the Town and Country Planning Act 1990 (as amended by Section 51 of the Planning and Compulsory Purchase Act 2004).
2.The development hereby permitted shall not be carried out otherwise than in complete accordance with the approved plans, particulars and specifications. Reason:- For the avoidance of doubt and to ensure that the development is carried out as approved. Also, in order that the development accords with Development Control Policies Development Plan Document Policy DC61.
3.Prior to the first occupation of the development hereby permitted, provision shall be made for the storage of refuse awaiting collection on site and retained thereafter. Reason:- In the interests of amenity of occupiers of the development and also the visual amenity of the development and the locality generally, and in order that the development accords with the Development Control Policies Development Plan Document Policy DC61.
4.The premises shall not be used for the purposes hereby permitted other than between the hours of 9:30 - 19:00 Mondays to Wednesdays, and Friday to Saturday, from 9:30 - 20:00 on Thursday, and not at all on Sundays and public/bank holidays without the prior consent in writing of the Local Planning Authority, in order that the development accords with the LDF Development Control Policies Development Plan Document. Reason:- To enable the Local Planning Authority to retain control in the interests of amenity, and in order that the development accords with Development Control Policies Development Plan Document Policy DC61.
5.Before the development hereby permitted commences details of a scheme shall be submitted to and approved in writing by the Local Planning Authority which specifies the provisions to be made for the control of noise emanating from the site. Such scheme as may be approved shall be implemented prior to first occupation and thereafter retained in accordance with such details. Reason:- To prevent noise nuisance to adjoining properties in accordance with the recommendations of Planning Policy Guidance Note 24 "Planning & Noise" 1994, and in order that the development accords with the Development Control Policies Development Plan Document Policies DC55 and DC61.
6.Before the use commences a scheme to control the transmission of noise and vibration from any mechanical ventilation system installed shall be submitted to and approved in writing by the Local Planning Authority and implemented prior to the permitted use commencing. Thereafter, the equipment shall be properly maintained and operated during normal working hours. Reason:- Insufficient information has been supplied with the application to assess the noise levels of the plant or machinery to be used on site. Submission of this detail prior to occupation in the case of new building works or prior to the use commencing in the case of changes of use, will prevent noise nuisance to adjoining properties in accordance with the Development Control Policies Development Plan Document Policies DC55 and DC61.
7.Statement Required by Article 31 (cc) of the Town and Country Planning (Development Management) Order 2010: No significant problems were identified during the consideration of the application, and therefore it has been determined in accordance with the National Planning Policy Framework 2019.