The London Borough Of Havering - Home page

No.Condition Text
1.The development to which this permission relates must be commenced not later than three years from the date of this permission. Reason:- To comply with the requirements of Section 91 of the Town and Country Planning Act 1990 (as amended by Section 51 of the Planning and Compulsory Purchase Act 2004).
2.The development hereby permitted shall not be carried out otherwise than in complete accordance with the approved plans (as set out on page one of this decision notice). Reason:- For the avoidance of doubt and to ensure that the development is carried out as approved.
3.No works shall take place in relation to any of the development hereby approved until samples of all materials to be used in the external construction of the building(s) are submitted to and approved in writing by the Local Planning Authority and thereafter the development shall be constructed with the approved materials. Reason:- Insufficient information has been supplied with the application to judge the appropriateness of the materials to be used. Submission of samples prior to commencement will ensure that the appearance of the proposed development will harmonise with the character of the surrounding area..
4.All building operations in connection with the construction of external walls, roof, and foundations; site excavation or other external site works; works involving the use of plant or machinery; the erection of scaffolding; the delivery of materials; the removal of materials and spoil from the site, and the playing of amplified music shall only take place between the hours of 8.00am and 6.00pm Monday to Friday, and between 8.00am and 1.00pm on Saturdays and not at all on Sundays and Bank Holidays/Public Holidays. Reason:- To protect residential amenity.
5.The hard surface hereby approved (including any sub-base) shall be made of porous materials or provision shall be made to direct run-off water from the hard surface to a permeable or porous area or surface within the curtilage of the dwellinghouse. Reason:- In order to ensure no water run-off from the hard surface which would contribute to risk of flooding
6.The proposed windows located on the first floor side elevation of both dwellings shall be permanently glazed with obscure glass not less than LEVEL 3 on the standard scale of obscurity and shall thereafter be maintained. Reason:- In the interests of privacy.
7.Minor (up to 9 units): All dwellings hereby approved shall be constructed to comply with Part M4(2) of the Building Regulations - Accessible and Adaptable Dwellings. Reason: In order to comply with national optional technical standards as required by Policy D7 of the London Plan.
8.All dwellings hereby approved shall comply with Regulation 36 (2)(b) and Part G2 of the Building Regulations - Water Efficiency. Reason: In order to comply with national optional technical standards as required by Policy SI5 of the London Plan.
9.Prior to the first occupation of the development, details shall be submitted to and agreed in writing by the Local Planning Authority for the installation of Ultra-Low NOx boilers with maximum NOx Emissions less than 40 mg/kWh. Where any installations do not meet this emissions standard it should not be operated without the fitting of suitable NOx abatement equipment or technology as determined by a specialist to ensure comparable emissions. The installation of the boilers shall be carried out in strict accordance with the agreed details and shall thereafter be permanently retained. Reason: To minimise the impact of building emissions on local air quality.
10.The dwellings hereby permitted shall no be occupied until the relocated / replacement highway tree as indicated on Proposed Site Plan 21-0293 PL05 Rev E has been replanted and shall be retained permanently thereafter. Reason: In the interests of visual amenity.
11.Statement Required by Article 35 (2) of the Town and Country Planning (Development Management Procedure) (England) Order 2015: In accordance with paragraph 38 of the National Planning Policy Framework, improvements required to make the proposal acceptable were negotiated with the Agent via email on 31st Aug 2022. The revisions involved amending the space between boundaries of neighbouring dwellings. The amendments were subsequently submitted in September 2022.
12.The proposal is liable for the Mayor of London Community Infrastructure Levy (CIL). The Mayoral CIL levy rate for Havering is £25.00 per square metre and is chargeable for each additional square metre of residential gross internal [floor] (GIA). Based upon the information supplied with the application, £6640.00 would be payable due to result in a new residential property with 265.6m of GIA, however this may be adjusted subject to indexation. The proposal is also liable for Havering Council's CIL. Havering's CIL charging rate for residential is £125.00 for each additional square metre of GIA. Based upon the information supplied with the application, £33200.00 would be payable, subject to indexation. These charges are levied under s.206 of the Planning Act 2008. CIL is payable within 60 days of commencement of development. A Liability Notice will be sent to the applicant (or anyone else who has assumed liability) shortly and you are required to notify the Council of the commencement of the development before works begin. Further details with regard to CIL are available from the Council's website. You are also advised to visit the planning portal website where you can download the appropriate document templates at http://www.planningportal.gov.uk/planning/applications/howtoapply/whattosubmit/cil