The London Borough Of Havering - Home page

No.Condition Text
1.The development to which this permission relates must be commenced not later than three years from the date of this permission. Reason:- To comply with the requirements of Section 91 of the Town and Country Planning Act 1990 (as amended by Section 51 of the Planning and Compulsory Purchase Act 2004).
2.Before the building(s) hereby permitted is first occupied, provision shall be made within the site for 2 no. car parking spaces each dimensioned 4.8m long by 2.4m wide and thereafter this provision shall be made permanently available for use, unless otherwise agreed in writing by the Local Planning Authority. Reason:- To ensure that adequate car parking provision is made off street in the interests of highway safety.
3.The development hereby permitted shall not be carried out otherwise than in complete accordance with the approved plans (as set out on page one of this decision notice). Reason:- For the avoidance of doubt and to ensure that the development is carried out as approved.
4.Notwithstanding the provisions of the Town and Country Planning (General Permitted Development) (England) Order 2015, no window or other opening (other than those shown on the submitted and approved plan,) shall be formed in the flank wall(s) of the building(s) hereby permitted, unless specific permission under the provisions of the Town and Country Planning Act 1990 has first been sought and obtained in writing from the Local Planning Authority. Reason:- In order to ensure a satisfactory development that will not result in any loss of privacy or damage to the environment of neighbouring properties which exist or may be proposed in the future, and in order that the development accords with Development Control Policies Development Plan Document Policy DC61.
5.a) If, during development, contamination not previously identified is found to be present at the site then no further development (unless otherwise agreed in writing with the local planning authority) shall be carried out until a remediation strategy detailing how this unsuspected contamination shall be dealt with has been submitted to and approved in writing by the local planning authority. The remediation strategy shall be implemented as approved. b) Following completion of the remediation works as mentioned in (a) above, a 'Verification Report' must be submitted demonstrating that the works have been carried out satisfactorily and remediation targets have been achieved. Reason: To ensure that any previously unidentified contamination found at the site is investigated and satisfactorily addressed in order to protect those engaged in construction and occupation of the development from potential contamination.
6.Statement Required by Article 35 (2) of the Town and Country Planning (Development Management Procedure) (England) Order 2015: In accordance with paragraph 38 of the National Planning Policy Framework 2018, improvements required to make the proposal acceptable were negotiated with Mr Rouse (Agent) by phone. The revisions involved reducing the depth of the ground floor rear extension on the boundary to comply with guidance. The amendments were subsequently submitted on 15/05/20.