| No. | Condition Text |
|---|
| 1. | The development hereby permitted shall begin no later than three years from the date of this decision.
Reason: To comply with the requirements of Section 91 of the Town and Country Planning Act 1990. |
| 2. | The development hereby permitted shall not be carried out otherwise than in complete accordance with the following approved plans:
201
200A
202A
203A
Reason: For the avoidance of doubt and to ensure that the development is carried out as approved and is compliant with development plan policy. |
| 3. | Before the developments hereby approved is occupied, the materials used on the external surfaces of the development must match those used on the external surfaces of the existing property. This applies unless differences are shown on the drawings hereby approved or are required by other conditions on this permission.
Reason: To ensure the development is carried out in accordance with the consent sought, has an acceptable design and complies with policy 26 of the Havering Local Plan (2021). |
| 4. | The proposed car port hereby approved shall be constructed in accordance with the materials detailed under the materials section of the application form unless otherwise agreed in writing by the Local Planning Authority.
Reason: To ensure that the appearance of the proposed development will harmonise with the character of the surrounding area. |
| 5. | Notwithstanding the provisions of the Town and Country Planning (General Permitted Development) (England) Order 2015, nor any Statutory Instrument which amends, removes or replaces that Order, no window or other opening (other than those shown on the submitted and approved plans) shall be formed in the flank walls of the development hereby permitted without the receipt of a specific planning permission for it from the London Planning Authority.
Reason: To protect the amenities of neighbouring occupiers and ensure the development complies with policy 7 of the Havering Local Plan (2021). |
| 6. | During construction of the developments hereby permitted, any trees within or near to the application site shall be protected in accordance with the requirements of BS 5837 (2012) 'Trees in Relation to Design, Demolition and Construction'. The protection measures shall be implemented prior to any below ground works and shall be retained for the entire period of the duration of any work at the site, in connection with the development hereby permitted.
Reason:- In order to maintain the existing vegetation at the site, which makes an important contribution to the character of the area, and to accord with Policy 27 of the Council's Local Plan. |
| 7. | You are reminded that this decision notice only addresses requirements under Planning Legislation. You also need to check that whether or not the development requires consent under the Building Regulations, as this is an entirely separate process. Further information on the requirements of the Building Regulations can be found at: https://www.havering.gov.uk/building control. |
| 8. | You are reminded that this decision notice only addresses requirements under Planning Legislation. It does not give consent for an permanent or temporary changes to the public highway, the use of the public highway for the storage of materials or placing of apparatus associated with the construction or other processes, nor does it permit the discharge of surface water onto the public highway. You are encouraged to check whether or not works or activities necessitate separate consents under the requirements of other, non-planning legislation at the earliest opportunity by emailing environmentbusinesssupport@havering.gov.uk for further information. Unauthorised work on or use of the public highway and a failure to prevent the discharge of surface water on to the public highway area all an offence. |
| 9. | You are reminded that this decision notice only addresses requirements under Planning Legislation. You also need to check whether or not the development necessitates an agreement under the requirements of the Party Wall etc. Act 1996, as this is an entirely separate process. Further guidance on the Party Wall etc. Act 1996 can be found at: https;//www,gov.uk/housing-local-and-community/party-walls. |
| 10. | For any development where a flood risk is identified, the Council as the Lead Local Flood Authority want to see developers consider and implement flood resilience/resistance measures into the buildings themselves. This is not to stop development but to ensure the protection for future residents is maintained and enhanced.
The following measures are strongly recommended, although this list is not exhaustive:-
- Raising the level of the building by at least 300mm above local levels;
- Waterproof membrane in the ground floor;
- Waterproof plaster and waterproofing to ground floor;
- Electrics from the upstairs down and sockets high up off the ground floor;
- Non return valves on the sewerage pipes;
- Emergency escape plan for each individual property;
- Air brick covers; and
- Movable flood barriers for entrances |
| 11. | The Local Planning Authority has acted positively and proactively in determining this application by assessing the proposal against all material planning considerations, including planning policies and any representations which were received. It subsequently determined to grant planning permission in accordance with the National Planning Policy requirement that applications for sustainable development are approved where possible. A detailed analysis of the scheme is set out in the report on the application prepared by officers. |