The London Borough Of Havering - Home page

No.Condition Text
1.The development to which this permission relates must be commenced not later than three years from the date of this permission. Reason:- To comply with the requirements of Section 91 of the Town and Country Planning Act 1990 (as amended by Section 51 of the Planning and Compulsory Purchase Act 2004).
2.The development hereby permitted shall not be carried out otherwise than in complete accordance with the approved plans (as set out on page one of this decision notice). Reason:- The Local Planning Authority consider it essential that the whole of the development is carried out and that no departure whatsoever is made from the details approved, since the development would not necessarily be acceptable if partly carried out or carried out differently in any degree from the details submitted. Also, in order that the development accords with Development Control Policies Development Plan Document Policy DC61.
3.The premises shall not be used for the purposes hereby permitted other than between the hours of 08:00 and 19:00 on Mondays to Saturdays and 10:00 and 16:00 Sundays, Bank or Public holidays without the prior consent in writing of the Local Planning Authority. Reason:- To enable the Local Planning Authority to retain control in the interests of amenity, and in order that the development accords with Development Control Policies Development Plan Document Policy DC61.
4.Before the use is commenced a scheme for the new plant or machinery must be submitted to and approved in writing by the Local Planning Authority to achieve the following standard - Noise levels expressed as the equivalent continuous sound level LAeq (1 hour) when calculated at the boundary with the nearest noise sensitive property shall not exceed -10db. Plant and machinery shall be maintained thereafter in accordance with the approved scheme. Reason:- Insufficient information has been supplied with the application to assess the noise levels of the plant or machinery to be used on site. Submission of this detail prior to occupation in the case of new building works or prior to the use commencing in the case of changes of use, will prevent noise nuisance to adjoining properties in accordance with the Development Control Policies Development Plan Document Policies DC55 and DC61.
5.No operations or activities in connection with the Tyre repair shop shall take place other than within the interior of the existing building as shown on drawing number 17-0046 PL01 Reason:- In order to safeguard the amenity of nearby residents and in order that the development accord with Policy DC61 of the LDF Development Control Policies Development Plan Document.
6.Notwithstanding the provisions of the Town and Country Planning (General Permitted Development) (England) Order 2015, the premises shall only be used for the purposes specified in the application as a Tyre Repair Shop (B2) and for no other purpose (including any other purpose in Class B2 of the Schedule to the Town and Country Planning (Use Classes) Order 1987 (as amended) (or any provision equivalent to that Class in any Statutory Instrument revoking and/or re-enacting that Order). Reason:- In order that the Local Authority maintain control.
7.Statement Required by Article 35 (2) of the Town and Country Planning (Development Management Procedure) (England) Order 2015: No significant problems were identified during the consideration of the application, and therefore it has been determined in accordance with paragraphs 186-187 of the National Planning Policy Framework 2012.