| No. | Condition Text |
|---|
| 1. | The development to which this permission relates must be commenced not later than three years from the date of this permission.
Reason:-
To comply with the requirements of Section 91 of the Town and Country Planning Act 1990 (as amended by Section 51 of the Planning and Compulsory Purchase Act 2004). |
| 2. | The development hereby permitted shall not be carried out otherwise than in complete accordance with the approved plans (as set out on page one of this decision notice).
Reason:-
For the avoidance of doubt and to ensure that the development is carried out as approved. |
| 3. | All new external finishes shall be carried out in materials to match those of the existing building(s) to the satisfaction of the Local Planning Authority.
Reason:-
To safeguard the appearance of the premises and the character of the immediate area. |
| 4. | The extension hereby permitted shall be used only for living accommodation as an integral part of the existing dwelling known as No.142 Cross Road, Romford and shall not be used as a separate unit of residential accommodation at any time.
Reason:-
The site is within an area where the Local Planning Authority consider that the sub-division of existing properties should not be permitted in the interests of amenity. |
| 5. | The three proposed flank windows in the proposed side/rear extension serving the game and lounge areas as shown on drawing GLA-06L Rev:A & GLA-08L Rev:A adjacent to No.152 Cross Road, Romford shall be permanently glazed with obscure glass not less than level 4 on the standard scale of obscurity and shall thereafter be maintained and permanently fixed shut and thereafter maintained, with the exception of any top hung fanlight(s).
Reason:-
In the interests of privacy. |
| 6. | Notwithstanding the provisions of the Town and Country Planning (General Permitted Development) (England) Order 2015, no window or other opening (other than those shown on the submitted and approved plan,) shall be formed in the flank wall(s) of the building(s) hereby permitted, unless specific permission under the provisions of the Town and Country Planning Act 1990 has first been sought and obtained in writing from the Local Planning Authority.
Reason:-
In order to ensure a satisfactory development that will not result in any loss of privacy or damage to the environment of neighbouring properties which exist or may be proposed in the future. |
| 7. | The roof area of the extension hereby permitted shall not be used as a balcony, roof garden or similar amenity area without the grant of further specific permission from the Local Planning Authority.
Reason:-
In the interests of the amenity of the occupiers of neighbouring dwelling. |
| 8. | Power Network Informative
The proposed development is in close proximity to our substation and have the following observations to make: If the proposed works are located within 6m of the substation, then they are notifiable under the Party Wall etc. Act 1996.
The Applicant should provide details of the proposed works and liaise with the Company to ensure that appropriate protective measures and mitigation solutions are agreed in accordance with the Act. The Applicant would need to be responsible for any costs associated with any appropriate measures required. Any Party Wall Notice should be served on UK Power Networks at its registered office: UK Power Networks, Newington House, 237 Southwark Bridge Road, London SE1 6NP.
Our engineering guidelines state that the distance between a dwelling of two or more stories with living or bedroom windows overlooking a distribution substation should be a minimum of ten metres if the transformer is outdoor, seven metres if the transformer has a GRP surround or onemetre if the transformer is enclosed in a brick building. It is a recognised fact that transformers emit a low level hum which can cause annoyance to nearby properties. This noise is mainly airborne in origin and is more noticeable during the summer months when people tend to spend more time in their gardens and sleep with open windows. A problem can also occur when footings of buildings are too close to substation structures. Vibration from the transformer can be transmitted through the ground and into the walls of adjacent buildings.
In practice there is little that can be done to alleviate these problems after the event. We therefore offer advice as follows:
1. The distance between buildings and substations should be greater than seven metres or as far as is practically possible.
2. Care should be taken to ensure that footings of new buildings are kept separated from substation structures.
3. Buildings should be designed so that rooms of high occupancy, i.e. bedrooms and living rooms, do not overlook or have windows opening out over the substation. Minimum distance for this should be at least 10m.
4. If noise attenuation methods are found to be necessary, we would expect to recover our costs from the developer. Other points to note:
5. UK Power Networks require 24 hour vehicular access to their substations. Consideration for this should be taken during the design stage of the development.
6. The development may have a detrimental impact on our rights of access to and from the substation. If in doubt please seek advice from our Property and Consents team at Barton Road, Bury St Edmunds, Suffolk, IP32 7BG.
7. No building materials should be left in a position where they might compromise the security of the substation or could be used as climbing aids to get over the substation surround.
8. There are underground cables on the site associated with the substation and these run in close proximity to the proposed development. Prior to commencement of work accurate records should be obtained from our Plan Provision Department at UK Power Networks, Fore Hamlet, Ipswich, IP3 8AA.
9. All works should be undertaken with due regard to Health & Safety Guidance notes HS(G)47 Avoiding Danger from Underground services. This document is available from local HSE offices. Should any diversion works be necessary as a result of the development then enquiries should be made to our Customer Connections department. The address is UK Power Networks, Metropolitan house, Darkes Lane, Potters Bar, Herts, EN6 1AG. |
| 9. | For any development where a flood risk is identified, the Council as the Lead Local Flood Authority want to see developers consider and implement flood resilience/resistance measures into the buildings themselves. This is not to stop development but to ensure the protection for future residents is maintained and enhanced.
The following measures are strongly recommended, although this list is not exhaustive:-
- Raising the level of the building by at least 300mm above local levels;
- Waterproof membrane in the ground floor;
- Waterproof plaster and waterproofing to ground floor;
- Electrics from the upstairs down and sockets high up off the ground floor;
- Non return valves on the sewerage pipes;
- Emergency escape plan for each individual property;
- Air brick covers; and
- Movable flood barriers for entrances |
| 10. | Party Wall Informative
This planning permission does not remove the need to obtain any separate consent of the owner of the adjoining property prior to commencing building works on, under, above or immediately adjacent to their property (e.g. foundations or guttering). The Party Wall Etc. Act 1996 contains requirements to serve notice on adjoining owners of property under certain circumstances, and a procedure exists for resolving disputes. This is a matter of civil law between the two parties, and the Local Planning Authority are not involved in such matters.
A free guide called "The Party Wall Etc Act 1996: Explanatory Booklet" is available on the website of the Department for Communities and Local Government.
https://www.gov.uk/government/publications/the-party-wall-etc-act-1996-revised-explanatory-booklet |
| 11. | Statement Required by Article 35 (2) of the Town and Country Planning (Development Management Procedure) (England) Order 2015: In accordance with paragraph 38 of the National Planning Policy Framework, improvements required to make the proposal acceptable were negotiated with Mr Ramessur (Agent) by phone and e-mail. The revisions involved including the single storey side & rear extensions approved as part of P0458.22 as they had not been substantially complete. A revised description was agreed with the agent and neighbours were re-consulted for a further 21 days. The amendments were subsequently submitted on 21/07/25. |