1.The development to which this permission relates must be commenced not later than three years from the date of this permission. Reason:- To comply with the requirements of Section 91 of the Town and Country Planning Act 1990 (as amended by Section 51 of the Planning and Compulsory Purchase Act 2004).
2.No above ground works shall take place in relation to any of the development hereby approved until a written specification of external walls and roof materials to be used in the construction of the building(s) shall be submitted to and approved in writing by the Local Planning Authority and thereafter the development shall be constructed with the approved materials. Reason:- Insufficient information has been supplied with the application to judge the appropriateness of the materials to be used. Submission of a written specification prior to any above ground works will ensure that the appearance of the proposed development will harmonise with the character of the surrounding area and comply with Policy DC61 of the Development Control Policies Development Plan Document.
3.The development hereby permitted shall not be carried out otherwise than in complete accordance with the approved plans (as set out on page one of this decision notice). Reason:- The Local Planning Authority consider it essential that the whole of the development is carried out and that no departure whatsoever is made from the details approved, since the development would not necessarily be acceptable if partly carried out or carried out differently in any degree from the details submitted. Also, in order that the development accords with Development Control Policies Development Plan Document Policy DC61.
4.Before the building(s) hereby permitted is first occupied, the area set aside for car parking shall be laid out and surfaced to the satisfaction of the Local Planning Authority and retained permanently thereafter for the accommodation of vehicles visiting the site and shall not be used for any other purpose. Reason:- To ensure that car parking accommodation is made permanently available to the standards adopted by the Local Planning Authority in the interest of highway safety, and that the development accords with the Development Control Policies Development Plan Document Policy DC33.
5.No above ground works shall take place in relation to any of the development hereby approved until there has been submitted to and approved by the Local Planning Authority a scheme of hard and soft landscaping, which shall include indications of all existing trees and shrubs on the site, and details of any to be retained, together with measures for the protection in the course of development. All planting, seeding or turfing comprised within the scheme shall be carried out in the first planting season following completion of the development and any trees or plants which within a period of 5 years from completion of the development die, are removed or become seriously damaged or diseased shall be replaced in the next planting season with others of a similar size and species, unless otherwise agreed in writing by the local Planning Authority. Reason:- Insufficient information has been supplied with the application to judge the appropriateness of the hard and soft landscaping proposed. Submission of a scheme prior to above ground works will ensure that the development accords with the Development Control Policies Development Plan Document Policy DC61. It will also ensure accordance with Section 197 of the Town and Country Planning Act 1990.
6.Before the building(s) hereby permitted is first occupied, details of all proposed walls, fences and boundary treatment shall be submitted to, and approved in writing by, the Local Planning Authority. The boundary development shall then be carried out in accordance with the approved details and retained permanently thereafter to the satisfaction of the Local Planning Authority. Reason: Insufficient information has been supplied with the application to judge the appropriateness of any boundary treatment. Submission of this detail prior to the first occupation of the dwelling hereby permitted will protect the visual amenities of the development, prevent undue overlooking of adjoining property and ensure that the development accords with the Development Control Policies Development Plan Document Policy DC61.
7.Notwithstanding the provisions of the Town and Country Planning (General Permitted Development) (England) Order 2015 (as amended), no development shall take place under Class A, B, C, D and E, unless permission under the provisions of the Town and Country Planning Act 1990 has first been sought and obtained in writing from the Local Planning Authority. Reason:- In the interests of amenity and to enable the Local Planning Authority to retain control over future development, and in order that the development accords with Development Control Policies Development Plan Document Policy DC61.
8.No building shall be occupied or use commenced until refuse and recycling facilities are provided in accordance with details which shall previously have been submitted to and approved in writing by the Local Planning Authority. The refuse and recycling facilities shall be permanently retained thereafter. Reason:- Insufficient information has been supplied with the application to judge how refuse and recycling will be managed on site. Submission of this detail prior to occupation in the case of new building works or prior to the use commencing in the case of changes of use will protect the amenity of occupiers of the development and also the locality generally and ensure that the development accords with the Development Control Policies Development Plan Document Policy DC61.
9.No building shall be occupied or use commenced until cycle storage is provided in accordance with details previously submitted to and approved in writing by the Local Planning Authority. The cycle storage shall be permanently retained thereafter. Reason:- Insufficient information has been supplied with the application to demonstrate what facilities will be available for cycle parking. Submission of this detail prior to occupation in the case of new building works or prior to the use commencing in the case of changes of use is in the interests of providing a wide range of facilities for non-motor car residents and sustainability.
10.Notwithstanding the provisions of the Town and Country Planning (General Permitted Development) (England) Order 2015, no window or other opening (other than those shown on the submitted and approved plan,) shall be formed in the flank wall(s) of the building(s) hereby permitted, unless specific permission under the provisions of the Town and Country Planning Act 1990 has first been sought and obtained in writing from the Local Planning Authority. Reason:- In order to ensure a satisfactory development that will not result in any loss of privacy or damage to the environment of neighbouring properties which exist or may be proposed in the future, and in order that the development accords with Development Control Policies Development Plan Document Policy DC61.
11.No works shall take place in relation to any of the development hereby approved until a Construction Method Statement to control the adverse impact of the development on the amenity of the public and nearby occupiers is submitted to and approved in writing by the Local Planning Authority. The Construction Method statement shall include details of: a) parking of vehicles of site personnel and visitors; b) storage of plant and materials; c) dust management controls; d) measures for minimising the impact of noise and ,if appropriate, vibration arising from construction activities; e) predicted noise and, if appropriate, vibration levels for construction using methodologies and at points agreed with the Local Planning Authority; f) scheme for monitoring noise and if appropriate, vibration levels using methodologies and at points agreed with the Local Planning Authorities; g) siting and design of temporary buildings; h) scheme for security fencing/hoardings, depicting a readily visible 24-hour contact number for queries or emergencies; i) details of disposal of waste arising from the construction programme, including final disposal points. The burning of waste on the site at any time is specifically precluded. And the development shall be carried out in accordance with the approved scheme and statement. Reason:- Insufficient information has been supplied with the application in relation to the proposed construction methodology. Submission of details prior to commencement will ensure that the method of construction protects residential amenity. It will also ensure that the development accords the Development Control Policies Development Plan Document Policy DC61.
12.All building operations in connection with the construction of external walls, roof, and foundations; site excavation or other external site works; works involving the use of plant or machinery; the erection of scaffolding; the delivery of materials; the removal of materials and spoil from the site, and the playing of amplified music shall only take place between the hours of 8.00am and 6.00pm Monday to Friday, and between 8.00am and 1.00pm on Saturdays and not at all on Sundays and Bank Holidays/Public Holidays. Reason:- To protect residential amenity, and in order that the development accords with the Development Control Policies Development Plan Document Policy DC61.
13.Prior to the first occupation of the development, details shall be submitted to and agreed in writing by the Local Planning Authority for the installation of Ultra-Low NOx boilers with maximum NOx Emissions less than 40 mg/kWh. Where any installations do not meet this emissions standard it should not be operated without the fitting of suitable NOx abatement equipment or technology as determined by a specialist to ensure comparable emissions. The installation of the boilers shall be carried out in strict accordance with the agreed details and shall thereafter be permanently retained. Following installation emissions certificates will need to be provided to the Local Planning Authority to verify boiler emissions. Reason: To minimise the impact of building emissions on local air quality.
14.The two ground floor windows on the eastern flank wall of No. 79 Essex Road serving a bathroom and an en-suite as shown on Drawing No. P002.111 shall be permanently glazed with obscure glass no less than level 4 on the standard scale of obscurity and shall thereafter be maintained. Reason:- In the interests of privacy, and in order that the development accords with the Development Control Policies Development Plan Document Policy DC61.
15.The proposed side dormer window on the eastern flank of No. 79 Essex Road as shown on Drawing No. P002.111 shall be permanently glazed with obscure glass not less than level 4 on the standard scale of obscurity and shall thereafter be maintained and permanently fixed shut. Reason:- In the interests of privacy, and in order that the development accords with the Development Control Policies Development Plan Document Policy DC61
16.The proposed first floor windows on the eastern and western flank walls of the proposed dwellings in Plots 1-5 serving stairwells and en-suites as shown on Drawing No. P002.1 shall be permanently glazed with obscure glass not less than level 4 on the standard scale of obscurity and shall thereafter be maintained and permanently fixed shut and thereafter maintained, with the exception of any top hung fanlight(s). Reason:- In the interests of privacy, and in order that the development accords with the Development Control Policies Development Plan Document Policy DC61.
17.All dwellings hereby approved shall comply with Regulation 36 (2)(b) and Part G2 of the Building Regulations - Water Efficiency. Reason: In order to comply with Policy 5.15 of the London Plan.
18.All dwellings hereby approved shall be constructed to comply with Part M4(2) of the Building Regulations - Accessible and Adaptable Dwellings. Reason: In order to comply with Policy DC7 of the Local Development Framework and Policy 3.8 of the London Plan.
19.No building shall be occupied or use commenced until external lighting is provided in accordance with details previously submitted to and approved in writing by the Local Planning Authority. The lighting shall be provided and operated in strict accordance with the approved scheme. Reason:- Insufficient information has been supplied with the application to judge the impact arising from any external lighting required in connection with the building or use. Submission of this detail prior to occupation in the case of new building works or prior to the use commencing in the case of changes of use will protect residential amenity and ensure that the development accords with the Development Control Policies Development Plan Document Policy DC61.
20.Statement Required by Article 35(2) of the Town and Country Planning (Development Management) Order 2015: No significant problems were identified during the consideration of the application, and therefore it has been determined in accordance with paragraph 38 of the National Planning Policy Framework 2018.
21.The proposal is liable for the Mayor of London Community Infrastructure Levy (CIL). Based upon the information supplied with the application, the CIL payable would be £10,575 (this figure may go up or down, subject to indexation). CIL is payable within 60 days of commencement of development. A Liability Notice will be sent to the applicant (or anyone else who has assumed liability) shortly and you are required to notify the Council of the commencement of the development before works begin. Further details with regard to CIL are available from the Council's website.
22.The planning obligations recommended in this report have been subject to the statutory tests set out in Regulation 122 of the Community Infrastructure Levy Regulations 2010 and the obligations are considered to have satisfied the following criteria:- (a) Necessary to make the development acceptable in planning terms; (b) Directly related to the development; and (c) Fairly and reasonably related in scale and kind to the development.
23.For Residential Development Only Please be advised that approval of this application from 1st September 2019 (either by London Borough of Havering, or subsequently by PINS if allowed on appeal following a refusal by London Borough of Havering) will attract a liability payment of £40,575 plus indexation in Community Infrastructure Levy (CIL). This charge has been levied under s.206 of the Planning Act 2008 and includes both the Mayor of London's CIL and Havering Council's CIL. London Borough of Havering, as CIL collecting authority, has responsibility for the collection of the Mayoral CIL, in addition to Havering's CIL, on commencement of the development. Your proposal is subject to a CIL Liability Notice indicating a levy of £10,575 plus indexation for the application, based on the Mayoral CIL levy rate for Havering of £25/sq.m plus Havering's charging rate for residential of £125/sq.m (Zone A) and the floorspace of 423 square metres. You are advised to visit the planning portal website where you can download the appropriate document templates. http://www.planningportal.gov.uk/planning/applications/howtoapply/whattosubmit/cil
24.A fee is required when submitting details pursuant to the discharge of conditions. In order to comply with the Town and Country Planning (Fees for Applications, Deemed Applications, Requests and Site Visits) (England) Regulations 2012, (as amended), a fee of £116 per request or £34 where the related permission was for extending or altering a dwellinghouse, is needed.
25.Changes to the public highway (including permanent or temporary access) - Planning approval does not constitute approval for changes to the public highway. Highway Authority approval will only be given after suitable details have been submitted considered and agreed. If new or amended access is required (whether temporary or permanent), there may be a requirement for the diversion or protection of third party utility plant or highway authority assets and it is recommended that early involvement with the relevant statutory undertaker takes place. The applicant must contact Engineering Services on 01708 433751 to discuss the scheme and commence the relevant highway approvals process. Please note that unauthorised work on the highway is an offence. Highway legislation - The developer (including their representatives and contractors) is advised that planning consent does not discharge the requirements of the New Roads and Street Works Act 1991 and the Traffic Management Act 2004. Formal notifications and approval will be needed for any highway works (including temporary works of any nature) required during the construction of the development. Please note that unauthorised work on the highway is an offence. Temporary use of the public highway - The developer is advised that if construction materials are proposed to be kept on the highway during construction works then they will need to apply for a licence from the Council. If the developer required scaffolding, hoarding or mobile cranes to be used on the highway, a licence is required and Street Management should be contacted to make the necessary arrangements. Please note that unauthorised use of the highway for construction works is an offence. Surface water management - The developer is advised that surface water from the development in both its temporary and permanent states should not be discharged onto the highway. Failure to prevent such is an offence.