| No. | Condition Text |
|---|
| 1. | The development to which this permission relates must be commenced not later than three years from the date of this permission.
Reason:-
To comply with the requirements of Section 91 of the Town and Country Planning Act 1990 (as amended by Section 51 of the Planning and Compulsory Purchase Act 2004). |
| 2. | The development hereby permitted shall not be carried out otherwise than in complete accordance with the approved plans (as set out on page one of this decision notice).
Reason:-
The Local Planning Authority consider it essential that the whole of the development is carried out and that no departure whatsoever is made from the details approved, since the development would not necessarily be acceptable if partly carried out or carried out differently in any degree from the details submitted. Also, in order that the development accords with Development Control Policies Development Plan Document Policy DC61. |
| 3. | No works shall take place in relation to any of the development hereby approved until samples of all materials to be used in the external construction of the building(s) are submitted to and approved in writing by the Local Planning Authority and thereafter the development shall be constructed with the approved materials.
Reason:-
Insufficient information has been supplied with the application to judge the appropriateness of the materials to be used. Submission of samples prior to commencement will ensure that the appearance of the proposed development will harmonise with the character of the surrounding area and comply with Policy DC61 of the Development Control Policies Development Plan Document. |
| 4. | No works shall take place in relation to any of the development hereby approved until there has been submitted to and approved by the Local Planning Authority a scheme of hard and soft landscaping, which shall include indications of all existing trees and shrubs on the site, and details of any to be retained, together with measures for the protection in the course of development. All planting, seeding or turfing comprised within the scheme shall be carried out in the first planting season following completion of the development and any trees or plants which within a period of 5 years from completion of the development die, are removed or become seriously damaged or diseased shall be replaced in the next planting season with others of a similar size and species, unless otherwise agreed in writing by the local Planning Authority.
Reason:-
Insufficient information has been supplied with the application to judge the appropriateness of the hard and soft landscaping proposed. Submission of a scheme prior to commencement will ensure that the development accords with the Development Control Policies Development Plan Document Policy DC61. It will also ensure accordance with Section 197 of the Town and Country Planning Act 1990. |
| 5. | No works shall take place in relation to any of the development hereby approved until a scheme for the protection of trees to be retained on the site has been submitted to and agreed in writing by the Local Planning Authority. Such scheme shall contain details of the erection and maintenance of fences or walls around the trees, details of underground measures to protect roots, the control of areas around the trees and any other measures necessary for the protection of the trees. Such agreed measures shall be implemented before development commences and kept in place until the approved development is completed.
Reason:-
Insufficient information has been supplied with the application to demonstrate how the preserved trees on site will be adequately protected during construction. Submission of details prior to commencement will ensure that the measures to be employed are robust. |
| 6. | Before the development hereby permitted is first commenced, vehicle cleansing facilities to prevent mud being deposited onto the public highway during construction works shall be provided on site in accordance with details to be first submitted to and approved in writing by the Local Planning Authority. The approved facilities shall be retained thereafter and used at relevant entrances to the site throughout the duration of construction works. If mud or other debris originating from the site is deposited in the public highway, all on-site operations shall cease until it has been removed.
The submission will provide;
a) A plan showing where vehicles will be parked within the site to be inspected for mud and debris and cleaned if required. The plan should show where construction traffic will access and exit the site from the public highway.
b) A description of how the parking area will be surfaced, drained and cleaned to prevent mud, debris and muddy water being tracked onto the public highway;
c) A description of how vehicles will be checked before leaving the site - this applies to the vehicle wheels, the underside of vehicles, mud flaps and wheel arches.
d) A description of how vehicles will be cleaned.
e) A description of how dirty/ muddy water be dealt with after being washing off the vehicles.
f) A description of any contingency plan to be used in the event of a break-down of the wheel washing arrangements.
Reason:-
Insufficient information has been supplied with the application in relation to wheel washing facilities. Submission of details prior to commencement will ensure that the facilities provided prevent materials from the site being deposited on the adjoining public highway, in the interests of highway safety and the amenity of the surrounding area. It will also ensure that the development accords with the Development Control Policies Development Plan Document Policies DC32 and DC61. |
| 7. | All building operations in connection with the construction of external walls, roof, and foundations; site excavation or other external site works; works involving the use of plant or machinery; the erection of scaffolding; the delivery of materials; the removal of materials and spoil from the site, and the playing of amplified music shall only take place between the hours of 8.00am and 6.00pm Monday to Friday, and between 8.00am and 1.00pm on Saturdays and not at all on Sundays and Bank Holidays/Public Holidays.
Reason:-
To protect residential amenity, and in order that the development accords with the Development Control Policies Development Plan Document Policy DC61. |
| 8. | No works shall take place in relation to any of the development hereby approved until a Construction Method Statement to control the adverse impact of the development on the amenity of the public and nearby occupiers is submitted to and approved in writing by the Local Planning Authority. The Construction Method statement shall include details of:
a) parking of vehicles of site personnel and visitors;
b) storage of plant and materials;
c) dust management controls;
d) measures for minimising the impact of noise and ,if appropriate, vibration arising from construction activities;
e) predicted noise and, if appropriate, vibration levels for construction using methodologies and at points agreed with the Local Planning Authority;
f) scheme for monitoring noise and if appropriate, vibration levels using methodologies and at points agreed with the Local Planning Authorities;
g) siting and design of temporary buildings;
h) scheme for security fencing/hoardings, depicting a readily visible 24-hour contact number for queries or emergencies;
i) details of disposal of waste arising from the construction programme, including final disposal points. The burning of waste on the site at any time is specifically precluded.
And the development shall be carried out in accordance with the approved scheme and statement.
Reason:-
Insufficient information has been supplied with the application in relation to the proposed construction methodology. Submission of details prior to commencement will ensure that the method of construction protects residential amenity. It will also ensure that the development accords the Development Control Policies Development Plan Document Policy DC61. |
| 9. | Before the building(s) hereby permitted is first occupied, the alterations and extensions to the car parking and drop off area, as shown on drawing nos. B08600BF/A/PL041 and B08600BF/A/PL042 shall be laid out and surfaced to the satisfaction of the Local Planning Authority and retained permanently thereafter for the accommodation of vehicles visiting the site and shall not be used for any other purpose.
Reason:-
To ensure that car parking accommodation is made permanently available to the standards adopted by the Local Planning Authority in the interest of highway safety, and that the development accords with the Development Control Policies Development Plan Document Policy DC33. |
| 10. | No building shall be occupied or use commenced until cycle storage is provided in accordance with details previously submitted to and approved in writing by the Local Planning Authority. The cycle storage shall be permanently retained thereafter.
Reason:-
Insufficient information has been supplied with the application to demonstrate what facilities will be available for cycle parking. Submission of this detail prior to occupation in the case of new building works or prior to the use commencing in the case of changes of use is in the interests of providing a wide range of facilities for non-motor car residents and sustainability. |
| 11. | No works shall take place in relation to any of the development hereby approved until a site investigation is undertaken to assess the level and extent of any landfill gas present, together with an assessment of associated risks. The investigation shall be in accordance with a scheme submitted to and approved in writing by the Local Planning Authority prior to any development commencing.
If during development works any contamination should be encountered which was not previously identified in the Site Investigation then works should halt immediately and the Local Planning Authority consulted to agree appropriate further action.
Reason:-
The development is situated on or within 250 metres of a current or historic landfill site or gravel pit. Insufficient information has been supplied with the application to judge the risk arising from landfill gas. Submission of an assessment prior to commencement will protect those redeveloping this site and any future occupants from potential landfill gas and will ensure that the development accords with the Development Control Policies Development Plan Document Policies DC54 and DC61. |
| 12. | No works shall take place in relation to any of the development hereby approved (except works required to secure compliance with this condition) until the following Contaminated Land reports (as applicable) are submitted to and approved in writing by the Local Planning Authority:
a) A Phase III (Risk Management Strategy) Report if the Phase II Report confirms the presence of a significant pollutant linkage requiring remediation. The report will comprise two parts:
Part A - Remediation Scheme which will be fully implemented before it is first occupied. Any variation to the scheme shall be agreed in writing to the Local Planning Authority in advance of works being undertaken. The Remediation Scheme is to include consideration and proposals to deal with situations where, during works on site, contamination is encountered which has not previously been identified. Any further contamination shall be fully assessed and an appropriate remediation scheme submitted to the Local Planning Authority for written approval.
Part B - Following completion of the remediation works a 'Validation Report' must be submitted demonstrating that the works have been carried out satisfactorily and remediation targets have been achieved.
b) If during development works any contamination should be encountered which was not previously identified and is derived from a different source and/or of a different type to those included in the contamination proposals, then revised contamination proposals shall be submitted to the LPA; and
c) If during development work, site contaminants are found in areas previously expected to be clean, then their remediation shall be carried out in line with the agreed contamination proposals.
For further guidance see the leaflet titled, 'Land Contamination and the Planning Process'.
Reason:-
Insufficient information has been supplied with the application to judge the risk arising from contamination. Submission of an assessment prior to commencement will ensure the safety of the occupants of the development hereby permitted and the public generally. It will also ensure that the development accords with Development Control Policies Development Plan Document Policies DC54 and DC61. |
| 13. | Prior to the commencement of any works to demolish existing buildings on the site, a bat emergence survey shall be undertaken in accordance with the recommendations set out in paragraph 4.1 of the Preliminary Ecological Appraisal Report dated 20th September 2017 submitted with this application. If roosting bats are discovered, further survey work and mitigation measures are to be undertaken during the course of the development, in accordance with a scheme that shall first be submitted to and approved in writing by the Local Planning Authority.
Reason:
Bats are protected species and submission of this information will ensure that the necessary protection is given, to accord with the provisions of the Wildlife and Countryside Act 1981. |
| 14. | Prior to the first occupation of the development, details shall be submitted to and agreed in writing by the Local Planning Authority for the installation of Ultra-Low N0x boilers with maximum N0x Emissions less than 40 mg/kWh. Where any installations do not meet this emissions standard it should not be operated without the fitting of suitable N0x abatement equipment or technology as determined by a specialist to ensure comparable emissions. The installation of the boilers shall be carried out in strict accordance with the agreed details and shall thereafter be permanently retained. Following installation emissions certificates will need to be provided to the Local Planning Authority to verify boiler emissions.
Reason: To minimise the impact of building emissions on local air quality. |
| 15. | A)Prior to the commencement of the development, the developer or contractor must be signed up o the Non-Road Mobile Machinery (NRMM) register.
B)The development must be entered onto the register alongside all the NRMM equipment details
C) The register must be kept up to date for the duration of the development
D) It is to be ensured that all NRMM complies with the requirements of the directive
E)An inventory of the NRMM to be kept on site stating the emissions limits for all its equipment.
Reason: Being a major development in Greater London, but outside the NRMM Central Activity Zone, NRMM used on site must meet Stage IIIA of EU Directive 97/68/EC as a minimum. |
| 16. | Statement Required by Article 35 (2) of the Town and Country Planning (Development Management Procedure) (England) Order 2015: No significant problems were identified during the consideration of the application, and therefore it has been determined in accordance with paragraphs 186-187 of the National Planning Policy Framework 2012. |
| 17. | For any development where a flood risk is identified, the Council as the Lead Local Flood Authority want to see developers consider and implement flood resilience/resistance measures into the buildings themselves. This is not to stop development but to ensure the protection for future residents is maintained and enhanced.
The following measures are strongly recommended, although this list is not exhaustive:-
- Raising the level of the building by at least 300mm above local levels;
- Waterproof membrane in the ground floor;
- Waterproof plaster and waterproofing to ground floor;
- Electrics from the upstairs down and sockets high up off the ground floor;
- Non return valves on the sewerage pipes;
- Emergency escape plan for each individual property;
- Air brick covers; and
- Movable flood barriers for entrances |
| 18. | The applicant is advised that the London Fire Brigade strongly recommends that sprinklers are considered for new developments and major alterations to existing premises, particularly where the proposals relate to school and care homes. Sprinkler systems installed in buildings can significantly reduce the damaged caused by fire and the consequential cost to businesses and housing providers and reduce the risk to life. The Brigade opinion is that there are opportunities for developers and building owners to install sprinkler systems in order to save money, save property and protect the lives of occupiers. |
| 19. | The submitted ecological report indicates the potential for Jersey Cudweed to be present on the site. The applicant is advised that Jersey Cudweed is a legally protected species and the site should be monitored for the presence of the species throughout the development. If the species is detected on the site then a licence application for its removal will be required to be made to Natural England. Such licence application is likely to require the submission of a mitigation and enhancement strategy. |