| No. | Condition Text |
|---|
| 1. | Details of the access, appearance, landscaping, layout, and scale, (hereinafter called "the reserved matters") shall be submitted to and approved in writing by the local planning authority before any development begins and the development shall be carried out as approved.
Reason:-
This is outline permission only and these matters have been reserved for the subsequent approval of the Local Planning Authority. |
| 2. | Application/s for approval of the reserved matters shall be submitted to the Local Planning Authority within three years from the date of this permission.
Reason:-
To comply with Section 92 of the Town and Country Planning Act 1990 (as amended by Section 51 of the Planning and Compulsory Purchase Act 2004). |
| 3. | The development to which this permission relates must be begun not later than the expiration of two years from the final approval of the reserved matters or, in the case of approval on different dates, the final approval of the last reserved matter to be approved.
Reason:-
To comply with Section 92 of the Town and Country Planning Act 1990 (as amended by Section 51 of the Planning and Compulsory Purchase Act 2004). |
| 4. | No works shall take place in relation to any of the development hereby approved until a site investigation is undertaken to assess the level and extent of any landfill gas present, together with an assessment of associated risks. The investigation shall be in accordance with a scheme submitted to and approved in writing by the Local Planning Authority prior to any development commencing.
If during development works any contamination should be encountered which was not previously identified in the Site Investigation then works should halt immediately and the Local Planning Authority consulted to agree appropriate further action.
Reason:-
The development is situated on or within 250 metres of a current or historic landfill site or gravel pit. Insufficient information has been supplied with the application to judge the risk arising from landfill gas. Submission of an assessment prior to commencement will protect those redeveloping this site and any future occupants from potential landfill gas and will ensure that the development accords with the Development Control Policies Development Plan Document Policies DC54 and DC61. |
| 5. | No works shall take place in relation to any of the development hereby approved (except works required to secure compliance with this condition) until the following Contaminated Land reports (as applicable) are submitted to and approved in writing by the Local Planning Authority:
a) A Phase I (Desktop Study) Report documenting the history of this site, its surrounding area and the likelihood of contaminant/s, their type and extent incorporating a Site Conceptual Model.
b) A Phase II (Site Investigation) Report if the Phase I Report confirms the possibility of a significant risk to any sensitive receptors. This is an intrusive site investigation including factors such as chemical testing, quantitative risk assessment and a description of the site ground conditions. An updated Site Conceptual Model should be included showing all the potential pollutant linkages and an assessment of risk to identified receptors.
c) A Phase III (Risk Management Strategy) Report if the Phase II Report confirms the presence of a significant pollutant linkage requiring remediation. The report will comprise two parts:
Part A - Remediation Scheme which will be fully implemented before it is first occupied. Any variation to the scheme shall be agreed in writing to the Local Planning Authority in advance of works being undertaken. The Remediation Scheme is to include consideration and proposals to deal with situations where, during works on site, contamination is encountered which has not previously been identified. Any further contamination shall be fully assessed and an appropriate remediation scheme submitted to the Local Planning Authority for written approval.
Part B - Following completion of the remediation works a 'Validation Report' must be submitted demonstrating that the works have been carried out satisfactorily and remediation targets have been achieved.
d) If during development works any contamination should be encountered which was not previously identified and is derived from a different source and/or of a different type to those included in the contamination proposals, then revised contamination proposals shall be submitted to the LPA; and
e) If during development work, site contaminants are found in areas previously expected to be clean, then their remediation shall be carried out in line with the agreed contamination proposals.
For further guidance see the leaflet titled, 'Land Contamination and the Planning Process'.
Reason:-
Insufficient information has been supplied with the application to judge the risk arising from contamination. Submission of an assessment prior to commencement will ensure the safety of the occupants of the development hereby permitted and the public generally. It will also ensure that the development accords with Development Control Policies Development Plan Document Policies DC54 and DC61. |
| 6. | All building operations in connection with the construction of external walls, roof, and foundations; site excavation or other external site works; works involving the use of plant or machinery; the erection of scaffolding; the delivery of materials; the removal of materials and spoil from the site, and the playing of amplified music shall only take place between the hours of 8.00am and 6.00pm Monday to Friday, and between 8.00am and 1.00pm on Saturdays and not at all on Sundays and Bank Holidays/Public Holidays.
Reason:-
To protect residential amenity, and in order that the development accords with the Development Control Policies Development Plan Document Policy DC61. |
| 7. | No works shall take place in relation to any of the development hereby approved until a Construction Method Statement to control the adverse impact of the development on the amenity of the public and nearby occupiers is submitted to and approved in writing by the Local Planning Authority. The Construction Method statement shall include details of:
a) parking of vehicles of site personnel and visitors;
b) storage of plant and materials;
c) dust management controls;
d) measures for minimising the impact of noise and ,if appropriate, vibration arising from construction activities;
e) predicted noise and, if appropriate, vibration levels for construction using methodologies and at points agreed with the Local Planning Authority;
f) scheme for monitoring noise and if appropriate, vibration levels using methodologies and at points agreed with the Local Planning Authorities;
g) siting and design of temporary buildings;
h) scheme for security fencing/hoardings, depicting a readily visible 24-hour contact number for queries or emergencies;
i) details of disposal of waste arising from the construction programme, including final disposal points. The burning of waste on the site at any time is specifically precluded.
And the development shall be carried out in accordance with the approved scheme and statement.
Reason:-
Insufficient information has been supplied with the application in relation to the proposed construction methodology. Submission of details prior to commencement will ensure that the method of construction protects residential amenity. It will also ensure that the development accords the Development Control Policies Development Plan Document Policy DC61. |
| 8. | A) No development shall take place until the applicant has secured the implementation of a programme of archaeological works in accordance with a Written Scheme of Investigation which has been submitted by the applicant and approved by the local planning authority.
B) No development or demolition shall take place other that in accordance with the Written Scheme of Investigation approved under Part (A).
C) The development shall not be occupied until the site investigation and post investigation assessment has been completed in accordance with the programme set out in the Written Scheme of Investigation approved under Part (A), and the provision made for analysis, publication and dissemination of the results and archive deposition has been secured.
Reason: Heritage assets of archaeological interest survive on the site. Insufficient information has been supplied with the application in relation to these matters. The planning authority wishes to secure the provision of archaeological investigation and the subsequent recording of the remains prior to development (including historic buildings recording), in accordance with Policy DC70 of the Development Control Policies Development Plan Document and the NPPF. |
| 9. | Statement Required by Article 35 (2) of the Town and Country Planning (Development Management Procedure) (England) Order 2015: No significant problems were identified during the consideration of the application, and therefore it has been determined in accordance with paragraphs 186-187 of the National Planning Policy Framework 2012. |