The London Borough Of Havering - Home page

No.Condition Text
1.The development to which this permission relates must be commenced not later than three years from the date of this permission. Reason:- To comply with the requirements of Section 91 of the Town and Country Planning Act 1990 (as amended by Section 51 of the Planning and Compulsory Purchase Act 2004).
2.The development hereby permitted shall not be carried out otherwise than in complete accordance with the approved plans (as set out on page one of this decision notice). Reason:- For the avoidance of doubt and to ensure that the development is carried out as approved.
3.The proposed development hereby approved shall be constructed in accordance with the materials detailed under the Materials Section (ps. 5-6) of the application form and approved plans refs. PT757PL02-2, PT757PL02-3 and PT757PL02-4A, unless otherwise agreed in writing by the Local Planning Authority. Reason:- To ensure that the appearance of the proposed development will harmonise with the character of the surrounding area.
4.Notwithstanding the provisions of the Town and Country Planning (General Permitted Development) (England) Order 2015, no window or other opening (other than those shown on the submitted and approved plan,) shall be formed in the flank wall(s) of the building(s) hereby permitted, unless specific permission under the provisions of the Town and Country Planning Act 1990 has first been sought and obtained in writing from the Local Planning Authority. Reason:- In order to ensure a satisfactory development that will not result in any loss of privacy or damage to the environment of neighbouring properties which exist or may be proposed in the future.
5.The ground floor window inserted on the south elevation serving the bathroom shall be obscure-glazed, and non-opening unless the parts of the window which can be opened are more than 1.7m above the floor of the room in which the window is installed. Reason:- In the interest of privacy and to protect the amenity of the adjacent neighbours, and in accordance with Policy 7 of the Havering Local Plan (adopted 2021).
6.Statement Required by Article 35 (2) of the Town and Country Planning (Development Management Procedure) (England) Order 2015: In accordance with paragraph 38 of the National Planning Policy Framework, improvements required to make the proposal acceptable were negotiated with the agent.
7.This planning permission does not remove the need to obtain any separate consent of the owner of the adjoining property prior to commencing building works on, under, above or immediately adjacent to their property (e.g. foundations or guttering). The Party Wall Etc. Act 1996 contains requirements to serve notice on adjoining owners of property under certain circumstances, and a procedure exists for resolving disputes. This is a matter of civil law between the two parties, and the Local Planning Authority are not involved in such matters. A free guide called "The Party Wall Etc Act 1996: Explanatory Booklet" is available on the website of the Department for Communities and Local Government. https://www.gov.uk/government/publications/the-party-wall-etc-act-1996-revised-explanatory-booklet
8.Whilst it would appear from the application that the proposed development is to be entirely within the curtilage of the dwelling, care should be taken upon the commencement and during the course of building operations to ensure that no part of the development, including the foundations and roof overhang, encroaches on, under or over adjoining property. It should be noted that this permission relates solely to works included within the application site.
9.This permission does not convey any consent which may be required under any legislation other than the Town and Country Planning Acts. Any permission required under the Building Regulations or under any other Act, must be obtained from the relevant authority or body e.g. Fire Officer, Health and Safety Executive, Environment Agency (Water interest etc. Neither does this permission negate or override any private covenants which may affect the land.
10.For any development where a flood risk is identified, the Council as the Lead Local Flood Authority want to see developers consider and implement flood resilience/resistance measures into the buildings themselves. This is not to stop development but to ensure the protection for future residents is maintained and enhanced. The following measures are strongly recommended, although this list is not exhaustive:- - Raising the level of the building by at least 300mm above local levels; - Waterproof membrane in the ground floor; - Waterproof plaster and waterproofing to ground floor; - Electrics from the upstairs down and sockets high up off the ground floor; - Non return valves on the sewerage pipes; - Emergency escape plan for each individual property; - Air brick covers; and - Movable flood barriers for entrances