| No. | Condition Text |
|---|
| 1. | The development to which this permission relates must be commenced not
later than five years from the date of this permission.
Reason:-
To comply with the requirements of Section 91 of the Town and Country
Planning Act 1990. |
| 2. | The development hereby permitted shall not be carried out otherwise than
in complete accordance with the approved plans, particulars and
specifications.
Reason:-
The Local Planning Authority consider it essential that the whole of the
development is carried out and that no departure whatsoever is made from
the details approved, since the development would not necessarily be
acceptable if partly carried out or carried out differently in any degree
from the details submitted. |
| 3. | All new external finishes shall be carried out in materials to match those
of the existing buildings to the satisfaction of the Local Planning
Authority.
Reason:-
To safeguard the appearance of the premises and the character of the
immediate area. |
| 4. | INFORMATIVE 1: This permission in no way conveys or implies
approval to the advertisement signs shown for illustrative
purposes on the plans hereby approved. Separate consent will
be required under the appropriate Advertisement Regulations and
the applicant is advised to contact the Head of Development
Control Services, London Borough of Havering to discuss such
proposals.
INFORMATIVE 2: The applicant is reminded that this permission
relates only to the elevational changes to the building. It does
not have the effect of changing, deleting or superseding other
conditions previously imposed on planning applications:
L/HAV/582/83, P0410.94 and P0667.96. |