| No. | Condition Text |
|---|
| 1. | The development to which this permission relates must be commenced not later than three years from the date of this permission.
Reason: To comply with the requirements of section 91 of the Town and Country Act 1990 (as amended by Section 51 of the Planning and Compulsory Purchase Act 2004). |
| 2. | The development hereby permitted shall not be carried out otherwise than in complete accordance with the plans detailed on page 1 of the decision notice approved by the Local Planning Authority.
Reason: The Local Planning Authority consider it essential that the whole of the development is carried out and that no departure whatsoever is made from the details approved, since the development would not necessarily be acceptable if partly carried out or carried out differently in any degree from the details submitted. |
| 3. | Before the dwelling hereby permitted is first occupied, the car parking provision to the front of the proposed garage, as indicated on drawing no. 02, shall be laid out to the full satisfaction of the Local Planning Authority and be made available for use and thereafter this car parking provision shall remain permanently available for use, unless otherwise agreed in writing by the Local Planning Authority.
Reason: To ensure that car parking accommodation is made permanently available to the standards adopted by the Local Planning Authority in the interest of highway safety, and that the development accords with the Development Control Policies Development Plan Document Policy DC33. |
| 4. | The external construction of the development shall be constructed in the materials approved under condition 4 of P0305.16; under discharge of condition reference Q0217.16.
Reason: To ensure that the appearance of the proposed development will harmonise with the character of the surrounding area and comply with Policy DC61 of the Development Control Policies Development Plan Document. |
| 5. | The hard and soft landscaping shall be carried out in accordance with the details approved under condition 5 of P0305.16; under discharge of condition reference Q0217.16, and as detailed on approved drawing no. 'A9/HR/02 Revision B' as submitted with this application. The 3no. Acer negundo trees must have a minimum height of 3 metres on planting. All planting, seeding or turfing comprised within the scheme shall be carried out in the first planting season following completion of the development and any trees or plants which within a period of 5 years from completion of the development die, are removed or become seriously damaged or diseased shall be replaced in the next planting season with others of a similar size and species, unless otherwise agreed in writing by the local Planning Authority.
Reason: In accordance with Section 197 of the Town and Country Planning Act 1990 and to enhance the visual amenities of the development, and that the development accords with the Development Control Policies Development Plan Document Policy DC61. |
| 6. | The building hereby permitted shall not be occupied until the refuse and recycling facilities are provided in accordance with details approved under condition 6 of P0305.16, under discharge of condition reference Q0217.16 and as indicated drawing no. '887 10 A'. The refuse and recycling facilities shall be permanently retained thereafter.
Reason: In the interests of amenity of occupiers of the development and also the visual amenity of the development and the locality generally, and in order that the development accords with the Development Control Policies Development Plan Document Policy DC61. |
| 7. | The building hereby permitted shall not be occupied until secure cycle storage is provided in accordance with details approved under condition 7 of P0305.16, under discharge of condition reference Q0217.16 and as indicated drawing no. '887 10 A'. The secure cycle storage facilities shall be permanently retained thereafter.
Reason: In the interests of providing a wide range of facilities for non-motor car residents and sustainability, the amenity of occupiers of the development and also the visual amenity of the development and the locality generally, and in order that the development accords with the Development Control Policies Development Plan Document Policy DC35. |
| 8. | The proposals should provide a 2.1 by 2.1 metre pedestrian visibility splay on either side of the proposed access, set back to the boundary of the public footway. There should be no obstruction or object higher than 0.6 metres within the visibility splay.
Reason: In the interests of highway safety, and in order that the development accords with the Development Control Policies Development Plan Document Policy DC32. |
| 9. | The necessary agreement, notice or licence to enable the proposed alterations to the Public Highway shall be in accordance with the details approved under condition 9 of P0305.16, under discharge of condition reference Q0217.16.
Reason: In the interests of ensuring good design and ensuring public safety and to comply with policies of the Core Strategy and Development Control Policies DPD, namely CP10, CP17, and DC61. |
| 10. | The boundary treatment shall be carried out in accordance with the details approved under condition 10 of P0305.16; under discharge of condition reference Q0217.16, and as shown on approved drawing no. 887 11 A.
Reason: To ensure that the appearance of the proposed development will harmonise with the character of the surrounding area and comply with Policy DC61 of the Development Control Policies Development Plan Document and in accordance with Section 197 of the Town and Country Planning Act 1990 to enhance the visual amenities of the development, and that the development accords with the Development Control Policies Development Plan Document Policy DC61 |
| 11. | Notwithstanding the provisions of the Town and Country Planning (General Permitted Development) Order 2015 (or any order revoking and re-enacting that Order with or without modification), no window or other opening (other than those shown on the approved plans), shall be formed in the flank wall(s) of the building(s) hereby permitted, unless specific permission under the provisions of the Town and Country Planning Act 1990 has first been sought and obtained in writing from the Local Planning Authority.
Reason: In order to ensure a satisfactory development that will not result in any loss of privacy or damage to the environment of neighbouring properties which exist or may be proposed in the future, and in order that the development accords with Development Control Policies Development Plan Document Policy DC61. |
| 12. | Notwithstanding the provisions of the Town and Country Planning (General Permitted Development) Order 2015 (or any order revoking and re-enacting that Order with or without modification), Article 3, Schedule 2, Part 1, Classes A, B, C or E no extensions, roof extensions or roof alterations shall take place and no outbuildings or other means of enclosures shall be erected within the rear garden areas of the dwellings shall take place unless permission under the provisions of the Town and Country Planning Act 1990 has first been sought and obtained in writing from the Local Planning Authority.
Reason: In the interests of amenity and to enable the Local Planning Authority to retain control over future development which may be harmful to the amenity of neighbouring residents and the character and appearance of the rear garden setting, and in order that the development accords with Development Control Policies Development Plan Document Policy DC61. |
| 13. | The wheel washing and vehicle cleansing shall be carried out in accordance with the details approved under condition 14 of P0305.16; under discharge of condition reference Q0217.16, as detailed in the Traffic Management Plan.
Reason: To ensure that the facilities provided prevent materials from the site being deposited on the adjoining public highway, in the interests of highway safety and the amenity of the surrounding area. It will also ensure that the development accords with the Development Control Policies Development Plan Document Policies DC32 and DC61. |
| 14. | The Construction Methodology shall be carried out in accordance with the details approved under condition 15 of P0305.16; under discharge of condition reference Q0217.16, as detailed in the Demolition and Construction Statement, dated July 2016.
Reason: To ensure that the method of construction protects residential amenity. It will also ensure that the development accords the Development Control Policies Development Plan Document Policy DC61. |
| 15. | All building operations in connection with the construction of external walls, roof, and foundations; site excavation or other external site works; works involving the use of plant or machinery; the erection of scaffolding; the delivery of materials; the removal of materials and spoil from the site, and the playing of amplified music shall only take place between the hours of 8.00am and 6.00pm Monday to Friday, and between 8.00am and 1.00pm on Saturdays and not at all on Sundays and Bank Holidays/Public Holidays.
Reason: To protect residential amenity, and in order that the development accords with the Development Control Policies Development Plan Document Policy DC61. |
| 16. | The tree protection measures shall be carried out in accordance with the details approved under Condition 4 under discharge of condition reference; Q0264.13 as detailed in the Arboricultural Method Statement (Ref: BAN18896ams) received on 10 December 2013.
Reason: To protect the trees on the site and in order that the development accords with the Development Control Policies Development Plan Document Policy DC60. |
| 17. | Notwithstanding the provisions of the Town and Country Planning (General Permitted Development) Order 2015 (or any order revoking and re-enacting that Order with or without modification), the garage(s)/carport(s) hereby permitted shall be made permanently available for the parking of private motor vehicles and not for any other purpose including living accommodation or any trade or business.
Reason: To provide satisfactory off-street parking at the site, and that the development accords with the Development Control Policies Development Plan Document Policy DC61. |
| 18. | The proposed windows in the western elevation, namely the ground floor sitting room window and first floor ensuite bathroom window only, shall be permanently glazed with obscure glass and thereafter be maintained and permanently fixed shut to the satisfaction of the Local Planning Authority.
Reason: In the interests of privacy, and in order that the development accords with the Development Control Policies Development Plan Document Policy DC61. |
| 19. | Statement Required by Article 35 (2) of the Town and Country Planning (Development Management Procedure) (England) Order 2015: No significant problems were identified during the consideration of the application, and therefore it has been determined in accordance with paragraphs 186-187 of the National Planning Policy Framework 2012. |
| 20. | The proposal is liable for the Mayor of London Community Infrastructure Levy (CIL). Based upon the information supplied with the application, the CIL payable would be £5,449.80 (this figure may go up or down, subject to indexation). CIL is payable within 60 days of commencement of development. A Liability Notice will be sent to the applicant (or anyone else who has assumed liability) shortly and you are required to notify the Council of the commencement of the development before works begin. Further details with regard to CIL are available from the Council's website. |
| 21. | The applicant is advised that a pump appliance should be able to approach to within 45 metres of all points within the dwelling measured along a line suitable for laying a hose. If this cannot be met, a fire main should be provided and a pump appliance should be able to approach to within 18 metres of the inlet to the main, which should be visible from the appliance. The fire main should comply with BS9990:2015. There should also be a fire hydrant within 90 metres of the inlet to the fire main. Further information in this respect should be obtained from the London Fire and Emergency Planning Authority on 020 8555 1200. |
| 22. | A fee is required when submitting details pursuant to the discharge of conditions. In order to comply with the Town and Country Planning (Fees for Applications, Deemed Applications, Requests and Site Visits) (England) Regulations 2012, which came into force from 22.11.2012, a fee of £97 per request or £28 where the related permission was for extending or altering a dwellinghouse, is needed. |
| 23. | Changes to the public highway (including permanent or temporary access)
Planning approval does not constitute approval for changes to the public highway. Highway Authority approval will only be given after suitable details have been submitted considered and agreed. If new or amended access as required (whether temporary or permanent), there may be a requirement for the diversion or protection of third party utility plant and it is recommended that early involvement with the relevant statutory undertaker takes place. The applicant must contact Engineering Services on 01708 433751 to discuss the scheme and commence the relevant highway approvals process. Please note that unauthorised work on the highway is an offence.
Please note that a lamp column is affected by the new access. This will need to be relocated and potentially the lighting locally redesigned to accommodate the access. This will be at the applicant's cost.
Highway legislation
The developer (including their representatives and contractors) is advised that planning consent does not discharge the requirements of the New Roads and Street Works Act 1991 and the Traffic Management Act 2004. Formal notifications and approval will be needed for any highway works (including temporary works of any nature) required during the construction of the development. Please note that unauthorised work on the highway is an offence.
Temporary use of the public highway
The developer is advised that if construction materials are proposed to be kept on the highway during construction works then they will need to apply for a license from the Council. If the developer requires scaffolding, hoarding or mobile cranes to be used on the highway, a licence is required and Streetcare should be contacted on 01708 434343 to make the necessary arrangements. Please note that unauthorised use of the highway for construction works is an offence. |
| 24. | With regards to surface water drainage it is the responsibility of the developer to make proper provision for drainage to ground, water courses or a suitable sewer. In respect of surface water it is recommended that the applicant should ensure that storm flows are attenuated or regulated into the receiving public network through on or off site storage. When it is proposed to connect to a combined public sewer, the site drainage should be separate and combined at the final manhole nearest the boundary. Connections are not permitted for the removal of Ground Water. Where the developer proposes to discharge to a public sewer, prior approval from Thames Water Developer Services will be required. They can be contacted on 0845 850 2777. |
| 25. | The planning obligations recommended in this report have been subject to the statutory tests set out in Regulation 122 of the Community Infrastructure Levy Regulations 2010 and the obligations are considered to have satisfied the following criteria:-
(a) Necessary to make the development acceptable in planning terms;
(b) Directly related to the development; and
(c) Fairly and reasonably related in scale and kind to the development. |
| 26. | Before occupation of the residential/ commercial unit(s) hereby approved, it is a requirement to have the property/properties officially Street Named and Numbered by our Street Naming and Numbering Team. Official Street Naming and Numbering will ensure that that Council has record of the property/properties so that future occupants can access our services. Registration will also ensure that emergency services, Land Registry and the Royal Mail have accurate address details. Proof of having officially gone through the Street Naming and Numbering process may also be required for the connection of utilities. For further details on how to apply for registration see:
https://www.havering.gov.uk/Pages/Services/Street-names-and-numbering.aspx |