The London Borough Of Havering - Home page

No.Condition Text
1.The development to which this permission relates must be commenced not later than three years from the date of this permission. Reason:- To comply with the requirements of Section 91 of the Town and Country Planning Act 1990 (as amended by Section 51 of the Planning and Compulsory Purchase Act 2004).
2.All new external finishes shall be carried out in materials to match those of the existing building(s) to the satisfaction of the Local Planning Authority. Reason:- To safeguard the appearance of the premises and the character of the immediate area.
3.The development hereby permitted shall not be carried out otherwise than in complete accordance with the approved plans (as set out on page one of this decision notice). Reason:- The Local Planning Authority consider it essential that the whole of the development is carried out and that no departure whatsoever is made from the details approved, since the development would not necessarily be acceptable if partly carried out or carried out differently in any degree from the details submitted.
4.Before the building(s) hereby permitted is first occupied, the area set aside for car parking shall be laid out and surfaced to the satisfaction of the Local Planning Authority and retained permanently thereafter for the accommodation of vehicles visiting the site and shall not be used for any other purpose. Reason:- To ensure that car parking accommodation is made permanently available to the standards adopted by the Local Planning Authority in the interest of highway safety.
5.Before the building(s) hereby permitted is first occupied, details of all proposed walls, fences and boundary treatment shall be submitted to, and approved in writing by, the Local Planning Authority. The boundary development shall then be carried out in accordance with the approved details and retained permanently thereafter to the satisfaction of the Local Planning Authority. Reason: Insufficient information has been supplied with the application to judge the appropriateness of any boundary treatment. Submission of this detail prior to commencement will protect the visual amenities of the development and prevent undue overlooking of adjoining property.
6.Notwithstanding the provisions of the Town and Country Planning (General Permitted Development) (England) Order 2015, no extension or enlargement (including additions to roofs) shall be made to the dwellinghouse(s) hereby permitted, or any detached building erected, without the express permission in writing of the Local Planning Authority. Reason:- In the interests of amenity and to enable the Local Planning Authority to retain control over future development.
7.Notwithstanding the provisions of the Town and Country Planning (General Permitted Development) (England) Order 2015, no window or other opening (other than those shown on the submitted and approved plan) shall be formed in the flank wall(s) of the building(s) hereby permitted, unless specific permission under the provisions of the Town and Country Planning Act 1990 has first been sought and obtained in writing from the Local Planning Authority. Reason:- In order to ensure a satisfactory development that will not result in any loss of privacy or damage to the environment of neighbouring properties which exist or may be proposed in the future.
8.Prior to the first occupation of the development, details shall be submitted to and agreed in writing by the Local Planning Authority for the installation of Ultra-Low NOx boilers with maximum NOx Emissions less than 40 mg/kWh. Where any installations do not meet this emissions standard it should not be operated without the fitting of suitable NOx abatement equipment or technology as determined by a specialist to ensure comparable emissions. The installation of the boilers shall be carried out in strict accordance with the agreed details and shall thereafter be permanently retained. Reason: To minimise the impact of building emissions on local air quality.
9.All off street residential car parking spaces must provide infrastructure for electric or Ultra-Low Emission vehicles by way of active charging facilities. Reason: To minimise the impact of transport emissions on local air quality.
10.No work shall be carried out on the site between the hours of 08.00 hours and 18.00 hours Mondays to Fridays, between the hours of 08.00 hours and 13.00 hours on Saturdays, nor at any time on Sundays, Bank or Public Holidays. Reason: To minimise the impact of the development on the surrounding area in the interests of amenity.
11.The building(s) shall be so constructed as to provide sound insulation of 43 DnT,w + Ctr dB (minimum values) against airborne noise and 64 LnTw dB (maximum values) against impact noise to the satisfaction of the Local Planning Authority. Reason: To protect the amenity of residential premises.
12.All hard surfaces hereby approved as part of the development (including any sub-base) shall be made of porous materials or provision shall be made to direct run-off water from the hard surface to a permeable or porous area or surface within the curtilage of the application site. Reason:- In order to ensure no water run-off from the hard surface which would contribute to risk of flooding.
13.No building shall be occupied until cycle storage is provided to the satisfaction of the Council. The cycle storage shall be permanently retained thereafter. Reason:- In the interests of providing a wide range of facilities for non-motor car residents and sustainability.
14.Before occupation of the residential/ commercial unit(s) hereby approved, it is a requirement to have the property/properties officially Street Named and Numbered by our Street Naming and Numbering Team. Official Street Naming and Numbering will ensure that that Council has record of the property/properties so that future occupants can access our services. Registration will also ensure that emergency services, Land Registry and the Royal Mail have accurate address details. Proof of having officially gone through the Street Naming and Numbering process may also be required for the connection of utilities. For further details on how to apply for registration see: https://www.havering.gov.uk/Pages/Services/Street-names-and-numbering.aspx
15.Statement Required by Article 35(2) of the Town and Country Planning (Development Management) Order 2015: No significant problems were identified during the consideration of the application, and therefore it has been determined in accordance with paragraph 38 of the National Planning Policy Framework.