The London Borough Of Havering - Home page

No.Condition Text
1.The development to which this permission relates must be commenced not later than three years from the date of this permission. Reason:- To comply with the requirements of Section 91 of the Town and Country Planning Act 1990 (as amended by Section 51 of the Planning and Compulsory Purchase Act 2004).
2.All new external finishes shall be carried out in materials as per the details on the plans and the application form to the satisfaction of the Local Planning Authority. Reason:- To safeguard the appearance of the premises and the character of the immediate area.
3.The development hereby permitted shall not be carried out otherwise than in complete accordance with the approved plans (as set out on page one of this decision notice). Reason:- For the avoidance of doubt and to ensure that the development is carried out as approved.
4.Notwithstanding the provisions of the Town and Country Planning (General Permitted Development) (England) Order 2015, no window or other opening (other than those shown on the submitted and approved plan,) shall be formed in the flank wall(s) of the building(s) hereby permitted, unless specific permission under the provisions of the Town and Country Planning Act 1990 has first been sought and obtained in writing from the Local Planning Authority. Reason:- In order to ensure a satisfactory development that will not result in any loss of privacy or damage to the environment of neighbouring properties which exist or may be proposed in the future.
5.The roof area of the extension hereby permitted shall not be used as a balcony, roof garden or similar amenity area without the grant of further specific permission from the Local Planning Authority. Reason:- In the interests of the amenity of the occupiers of neighbouring dwelling.
6.Statement Required by Article 35(2) of the Town and Country Planning (Development Management) Order 2015: No significant problems were identified during the consideration of the application, and therefore it has been determined in accordance with paragraph 38 of the National Planning Policy Framework.
7.The Local Planning Authority strongly recommend the use of flood resistance and resilience measures. Physical barriers raised electrical fittings and special construction materials are just some of the ways you can help reduce flood damage. To find out which measures will be effective for this development, please contact your Building Control Department. If you'd like to find out more about reducing flood damage, visit the Flood Risk and Coastal Change pages of the planning practice guidance. Further guidance on flood resistance and resilience measures can also be found in: Government guidance on flood resilient construction https://www.gov.uk/government/publications/flood-resilient-construction-of-new-buildings CIRIA Code of Practice for property flood resilience https://www.ciria.org/Research/Projects_underway2/Code_of_Practice_and_guidance_for_property_flood_resilience_.aspx British Standard 85500 - Flood resistant and resilient construction https://shop.bsigroup.com/ProductDetail/?pid=000000000030299686