No. | Condition Text |
---|
1. | The development to which this permission relates must be commenced not later than three years from the date of this permission.
Reason:-
To comply with the requirements of Section 91 of the Town and Country Planning Act 1990 (as amended by Section 51 of the Planning and Compulsory Purchase Act 2004). |
2. | Statement Required by Article 35(2) of the Town and Country Planning (Development Management) Order 2015: No significant problems were identified during the consideration of the application, and therefore it has been determined in accordance with paragraph 38 of the National Planning Policy Framework. |
3. | The development hereby permitted shall not be carried out otherwise than in complete accordance with the approved plans (as set out on page one of this decision notice).
Reason:-
For the avoidance of doubt and to ensure that the development is carried out as approved. |
4. | No plant of machinery shall be installed unless it meets, or mitigation is employed, to meet the following standard:
The Rating Level (Lar, Tr) of the hereby permitted plant or machinery shall be at least 10dB below the prevailing background noise level (LA90, T). The measurement position, assessment and definitions shall be made according to BS4142:2014 + A1:2019 "Methods for rating and assessing industrial and commercial sound".
The equipment shall be maintained thereafter to the satisfaction of the Local Planning Authority, and the use hereby permitted must cease during any period that this condition is not complied with.
Reason: To protect the amenity of noise sensitive premises from noise from mechanical plant. |