| No. | Condition Text |
|---|
| 1. | No works shall take place in relation to any of the development hereby approved until there has been submitted to and approved by the Local Planning Authority a scheme of hard and soft landscaping, which shall include indications of all existing trees and shrubs on the site, and details of any to be retained, together with measures for the protection in the course of development. All planting, seeding or turfing comprised within the scheme shall be carried out in the first planting season following completion of the development and any trees or plants which within a period of 5 years from completion of the development die, are removed or become seriously damaged or diseased shall be replaced in the next planting season with others of a similar size and species, unless otherwise agreed in writing by the local Planning Authority.
Reason:-
Insufficient information has been supplied with the application to judge the appropriateness of the hard and soft landscaping proposed. Submission of a scheme prior to commencement will ensure that the development accords with the Development Control Policies Development Plan Document Policy DC61. It will also ensure accordance with Section 197 of the Town and Country Planning Act 1990. |
| 2. | No work shall be carried out on the site between the hours of (ENTER HOUR) and (ENTER HOURS) Mondays to Fridays, between the hours of (ENTER HOURS) and (ENTER HOURS) on Saturdays, nor at any time on Sundays, Bank or Public Holidays.
Reason:-
To minimise the impact of the development on the surrounding area in the interests of amenity, and that the development accords with the Development Control Policies Development Plan Document Policy DC61. |
| 3. | No works (other than drainage works required by this condition) shall take place in relation to any of the development hereby approved until drainage works have been carried out in accordance with details previously submitted to and approved by the Local Planning Authority.
Reason:-
Drainage works are required on site to prevent the risk of flooding. Submission of a scheme prior to commencement will ensure that the measures to be employed are technically sound and that the development accords with the Development Control Policies Development Plan Document Policies DC49 and DC61. |
| 4. | No works shall take place in relation to any of the development hereby approved until details of surface water drainage works are submitted to and approved in writing by the Local Planning Authority. Surface water drainage shall be provided in accordance with the approved details.
Reason:-
Surface water drainage works are required on site to prevent the risk of flooding. Submission of a scheme prior to commencement will ensure that the measures to be employed are technically sound and that the development accords with the Development Control Policies Development Plan Document Policies DC49 and DC61. |
| 5. | No works shall take place in relation to any of the development hereby approved until details of surface water attenuation/storage are submitted to and approved in writing by the Local Planning Authority. Surface water attenuation/storage shall be provided in accordance with the approved details.
Reason:-
Surface water attenuation/storage works are required on site to prevent the risk of flooding. Submission of a scheme prior to commencement will ensure that the measures to be employed are technically sound and that the development accords with the Development Control Policies Development Plan Document Policies DC49 and DC61. |
| 6. | Before the development hereby permitted is first commenced, vehicle cleansing facilities to prevent mud being deposited onto the public highway during construction works shall be provided on site in accordance with details to be first submitted to and approved in writing by the Local Planning Authority. The approved facilities shall be retained thereafter and used at relevant entrances to the site throughout the duration of construction works. If mud or other debris originating from the site is deposited in the public highway, all on-site operations shall cease until it has been removed.
The submission will provide;
a) A plan showing where vehicles will be parked within the site to be inspected for mud and debris and cleaned if required. The plan should show where construction traffic will access and exit the site from the public highway.
b) A description of how the parking area will be surfaced, drained and cleaned to prevent mud, debris and muddy water being tracked onto the public highway;
c) A description of how vehicles will be checked before leaving the site - this applies to the vehicle wheels, the underside of vehicles, mud flaps and wheel arches.
d) A description of how vehicles will be cleaned.
e) A description of how dirty/ muddy water be dealt with after being washing off the vehicles.
f) A description of any contingency plan to be used in the event of a break-down of the wheel washing arrangements.
Reason:-
Insufficient information has been supplied with the application in relation to wheel washing facilities. Submission of details prior to commencement will ensure that the facilities provided prevent materials from the site being deposited on the adjoining public highway, in the interests of highway safety and the amenity of the surrounding area. It will also ensure that the development accords with the Development Control Policies Development Plan Document Policies DC32 and DC61. |
| 7. | No building shall be occupied or use commenced until refuse and recycling facilities are provided in accordance with details which shall previously have been submitted to and approved in writing by the Local Planning Authority. The refuse and recycling facilities shall be permanently retained thereafter.
Reason:-
Insufficient information has been supplied with the application to judge how refuse and recycling will be managed on site. Submission of this detail prior to occupation in the case of new building works or prior to the use commencing in the case of changes of use will protect the amenity of occupiers of the development and also the locality generally and ensure that the development accords with the Development Control Policies Development Plan Document Policy DC61. |
| 8. | No building shall be occupied or use commenced until cycle storage is provided in accordance with details previously submitted to and approved in writing by the Local Planning Authority. The cycle storage shall be permanently retained thereafter.
Reason:-
Insufficient information has been supplied with the application to demonstrate what facilities will be available for cycle parking. Submission of this detail prior to occupation in the case of new building works or prior to the use commencing in the case of changes of use is in the interests of providing a wide range of facilities for non-motor car residents and sustainability. |
| 9. | All building operations in connection with the construction of external walls, roof, and foundations; site excavation or other external site works; works involving the use of plant or machinery; the erection of scaffolding; the delivery of materials; the removal of materials and spoil from the site, and the playing of amplified music shall only take place between the hours of 8.00am and 6.00pm Monday to Friday, and between 8.00am and 1.00pm on Saturdays and not at all on Sundays and Bank Holidays/Public Holidays.
Reason:-
To protect residential amenity, and in order that the development accords with the Development Control Policies Development Plan Document Policy DC61. |
| 10. | No works shall take place in relation to any of the development hereby approved until a Construction Method Statement to control the adverse impact of the development on the amenity of the public and nearby occupiers is submitted to and approved in writing by the Local Planning Authority. The Construction Method statement shall include details of:
a) parking of vehicles of site personnel and visitors;
b) storage of plant and materials;
c) dust management controls;
d) measures for minimising the impact of noise and ,if appropriate, vibration arising from construction activities;
e) predicted noise and, if appropriate, vibration levels for construction using methodologies and at points agreed with the Local Planning Authority;
f) scheme for monitoring noise and if appropriate, vibration levels using methodologies and at points agreed with the Local Planning Authorities;
g) siting and design of temporary buildings;
h) scheme for security fencing/hoardings, depicting a readily visible 24-hour contact number for queries or emergencies;
i) details of disposal of waste arising from the construction programme, including final disposal points. The burning of waste on the site at any time is specifically precluded.
And the development shall be carried out in accordance with the approved scheme and statement.
Reason:-
Insufficient information has been supplied with the application in relation to the proposed construction methodology. Submission of details prior to commencement will ensure that the method of construction protects residential amenity. It will also ensure that the development accords the Development Control Policies Development Plan Document Policy DC61. |
| 11. | No work shall be carried out on the site between the hours of (ENTER HOUR) and (ENTER HOURS) Mondays to Fridays, between the hours of (ENTER HOURS) and (ENTER HOURS) on Saturdays, nor at any time on Sundays, Bank or Public Holidays.
Reason:-
To minimise the impact of the development on the surrounding area in the interests of amenity, and that the development accords with the Development Control Policies Development Plan Document Policy DC61. |
| 12. | No works shall take place in relation to any of the development hereby approved until a site investigation is undertaken to assess the level and extent of any landfill gas present, together with an assessment of associated risks. The investigation shall be in accordance with a scheme submitted to and approved in writing by the Local Planning Authority prior to any development commencing.
If during development works any contamination should be encountered which was not previously identified in the Site Investigation then works should halt immediately and the Local Planning Authority consulted to agree appropriate further action.
Reason:-
The development is situated on or within 250 metres of a current or historic landfill site or gravel pit. Insufficient information has been supplied with the application to judge the risk arising from landfill gas. Submission of an assessment prior to commencement will protect those redeveloping this site and any future occupants from potential landfill gas and will ensure that the development accords with the Development Control Policies Development Plan Document Policies DC54 and DC61. |
| 13. | No works shall take place in relation to any of the development hereby approved (except works required to secure compliance with this condition) until the following Contaminated Land reports (as applicable) are submitted to and approved in writing by the Local Planning Authority:
a) A Phase I (Desktop Study) Report documenting the history of this site, its surrounding area and the likelihood of contaminant/s, their type and extent incorporating a Site Conceptual Model.
b) A Phase II (Site Investigation) Report if the Phase I Report confirms the possibility of a significant risk to any sensitive receptors. This is an intrusive site investigation including factors such as chemical testing, quantitative risk assessment and a description of the site ground conditions. An updated Site Conceptual Model should be included showing all the potential pollutant linkages and an assessment of risk to identified receptors.
c) A Phase III (Risk Management Strategy) Report if the Phase II Report confirms the presence of a significant pollutant linkage requiring remediation. The report will comprise two parts:
Part A - Remediation Scheme which will be fully implemented before it is first occupied. Any variation to the scheme shall be agreed in writing to the Local Planning Authority in advance of works being undertaken. The Remediation Scheme is to include consideration and proposals to deal with situations where, during works on site, contamination is encountered which has not previously been identified. Any further contamination shall be fully assessed and an appropriate remediation scheme submitted to the Local Planning Authority for written approval.
Part B - Following completion of the remediation works a 'Validation Report' must be submitted demonstrating that the works have been carried out satisfactorily and remediation targets have been achieved.
d) If during development works any contamination should be encountered which was not previously identified and is derived from a different source and/or of a different type to those included in the contamination proposals, then revised contamination proposals shall be submitted to the LPA; and
e) If during development work, site contaminants are found in areas previously expected to be clean, then their remediation shall be carried out in line with the agreed contamination proposals.
For further guidance see the leaflet titled, 'Land Contamination and the Planning Process'.
Reason:-
Insufficient information has been supplied with the application to judge the risk arising from contamination. Submission of an assessment prior to commencement will ensure the safety of the occupants of the development hereby permitted and the public generally. It will also ensure that the development accords with Development Control Policies Development Plan Document Policies DC54 and DC61. |
| 14. | Within the area defined (ENTER AREA REFERRING TO PLAN), no work shall be carried out between the hours of (ENTER HOURS) and (ENTER HOURS) on Mondays to Fridays, between the hours of (ENTER HOURS) and (ENTER HOURS) on Saturdays nor at any time on Sundays, Bank or Public Holidays.
Reason:-
To minimise the impact of the development on the surrounding area in the interests of amenity, and that the development accords with Development Control Policies Development Plan Document Policy DC61. |
| 15. | No works shall take place in relation to any of the development hereby approved until samples of all materials to be used in the external construction of the building(s) are submitted to and approved in writing by the Local Planning Authority and thereafter the development shall be constructed with the approved materials.
Reason:-
Insufficient information has been supplied with the application to judge the appropriateness of the materials to be used. Submission of samples prior to commencement will ensure that the appearance of the proposed development will harmonise with the character of the surrounding area and comply with Policy DC61 of the Development Control Policies Development Plan Document. |
| 16. | No works shall take place in relation to any of the development hereby approved until a full and detailed application for the Secured by Design award scheme is submitted to the Local Planning Authority, setting out how the principles and practices of the Secured by Design Scheme are to be incorporated. Once approved in writing by the Local Planning Authority in consultation with the Metropolitan Police Designing Out Crime Officers, the development shall be carried out in accordance with the agreed details.
Reason:-
Insufficient information has been supplied with the application to judge whether the proposals meet Secured by Design standards. Submission of a full and detailed application prior to commencement is in the interest of creating safer, sustainable communities and to reflect guidance in Policies CP17 and DC63 of the Core Strategy and Development Control Policies Development Plan Document and the NPPF. |