| No. | Condition Text |
|---|
| 1. | The development to which this permission relates must be commenced not later than three years from the date of this permission.
Reason:-
To comply with the requirements of Section 91 of the Town and Country Planning Act 1990 (as amended by Section 51 of the Planning and Compulsory Purchase Act 2004). |
| 2. | The development hereby permitted shall not be carried out otherwise than in complete accordance with the approved plans (as set out on page one of this decision notice).
Reason:-
For the avoidance of doubt and to ensure that the development is carried out as approved. |
| 3. | All materials and finishes to match the submitted specifications (feeder pillar 14 C39 Green, charging unit external colour grey , RAL 7040).
Reason:-
To safeguard the appearance of the premises and the character of the immediate area. |
| 4. | Statement Required by Article 35(2) of the Town and Country Planning (Development Management) Order 2015: No significant problems were identified during the consideration of the application, and therefore it has been determined in accordance with paragraph 38 of the National Planning Policy Framework. |
| 5. | You are informed that you need to coordinate any excavation works with infrastructure planning team at TfL at SpatialPlanning@tfl.gov.uk, to avoid any conflict with any ongoing work in wider Gallows Corner area. |