| No. | Condition Text |
|---|
| 1. | The development to which this permission relates must be commenced not later than three years from the date of this permission.
Reason:-
To comply with the requirements of Section 91 of the Town and Country Planning Act 1990 (as amended by Section 51 of the Planning and Compulsory Purchase Act 2004). |
| 2. | The development hereby permitted shall not be carried out otherwise than in complete accordance with the approved plans (as set out on page one of this decision notice).
Reason:-
The Local Planning Authority consider it essential that the whole of the development is carried out and that no departure whatsoever is made from the details approved, since the development would not necessarily be acceptable if partly carried out or carried out differently in any degree from the details submitted. Also, in order that the development accords with Development Control Policies Development Plan Document Policy DC61. |
| 3. | Before any new plant or machinery is installed a scheme shall be submitted to the local planning authority that demonstrates how the following noise standard is to be achieved:- the noise levels expressed as the equivalent continuous sound level LAeq (1 hour) when calculated at the boundary with the nearest noise sensitive premises shall not exceed LA90 -10dB. The plant and machinery shall be installed to meet the noise standard and maintained thereafter such as to achieve this standard throughout the lifetime of the development.
Reason:-
Insufficient information has been supplied with the application to assess the noise levels of the plant or machinery to be used on site. Submission of this detail prior to occupation in the case of new building works or prior to the use commencing in the case of changes of use, will prevent noise nuisance to adjoining properties in accordance with the Development Control Policies Development Plan Document Policies DC55 and DC61. |
| 4. | Statement Required by Article 35 (2) of the Town and Country Planning (Development Management Procedure) (England) Order 2015: No significant problems were identified during the consideration of the application, and therefore it has been determined in accordance with paragraphs 186-187 of the National Planning Policy Framework 2012. |