1.The development to which this permission relates must be commenced not later than three years from the date of this permission. Reason:- To comply with the requirements of Section 91 of the Town and Country Planning Act 1990 (as amended by Section 51 of the Planning and Compulsory Purchase Act 2004).
2.The development hereby permitted shall not be carried out otherwise than in complete accordance with the approved plans (as set out on page one of this decision notice). Reason:- The Local Planning Authority consider it essential that the whole of the development is carried out and that no departure whatsoever is made from the details approved, since the development would not necessarily be acceptable if partly carried out or carried out differently in any degree from the details submitted. Also, in order that the development accords with Development Control Policies Development Plan Document Policy DC61.
3.Before any works commence a scheme for any new plant or machinery shall be submitted to the local planning authority to achieve the following standard. Noise levels expressed as the equivalent continuous sound level LAeq (1 hour) when calculated at the boundary with the nearest noise sensitive premises shall not exceed LA90 -10dB and shall be maintained thereafter to the satisfaction of the Local Planning Authority. Reason: To prevent noise nuisance to adjoining/adjacent properties.
4.Before the uses commences a scheme to control the transmission of noise and vibration from any mechanical ventilation system installed shall be submitted to and approved in writing by the Local Planning Authority and implemented prior to the permitted use commencing. Thereafter, the equipment shall be properly maintained and operated during normal working hours. Reason: To protect the amenity of occupiers of nearby premises
5.Statement Required by Article 31 (cc) of the Town and Country Planning (Development Management) Order 2010: No significant problems were identified during the consideration of the application, and therefore it has been determined in accordance with paragraphs 186-187 of the National Planning Policy Framework 2019.