| 1. | The development to which this permission relates must be commenced not later than three years from the date of this permission.
Reason:-
To comply with the requirements of Section 91 of the Town and Country Planning Act 1990 (as amended by Section 51 of the Planning and Compulsory Purchase Act 2004). |
| 2. | The development hereby permitted shall not be carried out otherwise than in complete accordance with the approved plans (as set out on page one of this decision notice).
Reason:-
For the avoidance of doubt and to ensure that the development is carried out as approved. |
| 3. | No above ground works shall take place in relation to any of the development hereby approved until samples of all materials to be used in the external construction of the buildings are submitted to and approved in writing by the Local Planning Authority and thereafter the development shall be constructed with the approved materials.
Reason:-
Insufficient information has been supplied with the application to judge the appropriateness of the materials to be used. Submission of samples prior to commencement will ensure that the appearance of the proposed development will harmonise with the character of the surrounding area.. |
| 4. | All building operations in connection with the construction of external walls, roof, and foundations; site excavation or other external site works; works involving the use of plant or machinery; the erection of scaffolding; the delivery of materials; the removal of materials and spoil from the site, and the playing of amplified music shall only take place between the hours of 8.00am and 6.00pm Monday to Friday, and between 8.00am and 1.00pm on Saturdays and not at all on Sundays and Bank Holidays/Public Holidays.
Reason:-
To protect residential amenity. |
| 5. | No works shall take place in relation to any of the development hereby approved until a site investigation is undertaken to assess the level and extent of any landfill gas present, together with an assessment of associated risks. The investigation shall be in accordance with a scheme submitted to and approved in writing by the Local Planning Authority prior to any development commencing.
If during development works any contamination should be encountered which was not previously identified in the Site Investigation then works should halt immediately and the Local Planning Authority consulted to agree appropriate further action.
Reason:-
The development is situated on or within 250 metres of a current or historic landfill site or gravel pit. Insufficient information has been supplied with the application to judge the risk arising from landfill gas. Submission of an assessment prior to commencement will protect those redeveloping this site and any future occupants from potential landfill gas. |
| 6. | No works shall take place in relation to any of the development hereby approved (except works required to secure compliance with this condition) until the following Contaminated Land reports (as applicable) are submitted to and approved in writing by the Local Planning Authority:
a) A Phase I (Desktop Study) Report documenting the history of this site, its surrounding area and the likelihood of contaminant/s, their type and extent incorporating a Site Conceptual Model.
b) A Phase II (Site Investigation) Report if the Phase I Report confirms the possibility of a significant risk to any sensitive receptors. This is an intrusive site investigation including factors such as chemical testing, quantitative risk assessment and a description of the site ground conditions. An updated Site Conceptual Model should be included showing all the potential pollutant linkages and an assessment of risk to identified receptors.
c) A Phase III (Risk Management Strategy) Report if the Phase II Report confirms the presence of a significant pollutant linkage requiring remediation. The report will comprise two parts:
Part A - Remediation Scheme which will be fully implemented before it is first occupied. Any variation to the scheme shall be agreed in writing to the Local Planning Authority in advance of works being undertaken. The Remediation Scheme is to include consideration and proposals to deal with situations where, during works on site, contamination is encountered which has not previously been identified. Any further contamination shall be fully assessed and an appropriate remediation scheme submitted to the Local Planning Authority for written approval.
Part B - Following completion of the remediation works a 'Validation Report' must be submitted demonstrating that the works have been carried out satisfactorily and remediation targets have been achieved.
d) If during development works any contamination should be encountered which was not previously identified and is derived from a different source and/or of a different type to those included in the contamination proposals, then revised contamination proposals shall be submitted to the LPA; and
e) If during development work, site contaminants are found in areas previously expected to be clean, then their remediation shall be carried out in line with the agreed contamination proposals.
For further guidance see the leaflet titled, 'Land Contamination and the Planning Process'.
Reason:-
Insufficient information has been supplied with the application to judge the risk arising from contamination. Submission of an assessment prior to commencement will ensure the safety of the occupants of the development hereby permitted and the public generally. |
| 7. | Prior to any above ground works details of all proposed walls, fences and boundary treatment shall be submitted to, and approved in writing by, the Local Planning Authority. The boundary development shall then be carried out in accordance with the approved details and retained permanently thereafter to the satisfaction of the Local Planning Authority.
Reason:-
Insufficient information has been supplied with the application to judge the appropriateness of any boundary treatment. Submission of this detail prior to commencement will protect the visual amenities of the development and prevent undue overlooking of adjoining property. |
| 8. | Notwithstanding the details shown on submitted drawings, no building shall be occupied or use commenced until refuse and recycling facilities are provided in accordance with the approved plans. The refuse and recycling facilities shall be permanently retained thereafter.
Reason:-
To protect the amenity of occupiers of the development and also the locality generally (Local Plan Policy 35). |
| 9. | No building shall be occupied or use commenced until cycle storage is provided in accordance with Policy T5 of the London Plan. The cycle storage shall be permanently retained thereafter.
Reason:-
In the interests of providing a wide range of facilities for non-motor car residents and sustainability (London Plan (2021) Policy T5). |
| 10. | Any boilers installed in the dwelling(s) hereby approved shall be Ultra-Low NOx boilers with maximum NOx Emissions less than 40 mg/kWh. Where any installations do not meet this emissions standard it should not be operated without the fitting of suitable NOx abatement equipment or technology as determined by a specialist to ensure comparable emissions. The installation of the boilers shall be carried out in strict accordance with these details and shall thereafter be permanently retained.
If the heating strategy is to be provided by an Air Source Heat Pump, or similar, they shall be designed to comply with the provisions of the Microgeneration Installation Standard: MCS 020 "MCS Planning Standards for Permitted Development Installations of Wind Turbines and Air Source Heat Pumps on Domestic Premises". The air source heat pumps shall be provided on site prior to first occupation of the dwellings. Any installation not meeting this standard will require a separate application for planning permission.
Reason: To reduce impact on building emissions on local air quality and to ensure any air source heat pumps installed maintain amenity. |
| 11. | No part of the development hereby approved shall be occupied until access to the highway has been completed in accordance with the approved details on plan no. 20.1437.1000 Rev D.
Reason:-
To ensure construction of a satisfactory access and in the interests of highway safety, good design, traffic movement and amenity in accordance with Policy 24 of the Havering Local Plan. |
| 12. | All hard surfaces hereby approved as part of the development (including any sub-base) shall be made of porous materials or provision shall be made to direct run-off water from the hard surface to a permeable or porous area or surface within the curtilage of the application site.
Reason:-
In order to ensure no water run-off from the hard surface which would contribute to risk of flooding. |
| 13. | All building operations in connection with the construction of external walls, roof, and foundations; site excavation or other external site works, including any works of demolition; works involving the use of plant or machinery; the erection of scaffolding; the delivery of materials; the removal of materials and spoil from the site, and the playing of amplified music shall only take place between the hours of 8.00am and 6.00pm Monday to Friday, and between 8.00am and 1.00pm on Saturdays and not at all on Sundays and Bank Holidays/Public Holidays.
Reason:-
To protect residential amenity and to accord with Policy 7 of the Council's Local Plan. |
| 14. | Prior to the first occupation of the proposed dwellings hereby approved, the area set aside for car parking shall be laid out and surfaced to the satisfaction of the Local Planning Authority and retained permanently thereafter for the accommodation of vehicles visiting the site and shall not be used for any other purpose.
Reason:-
To ensure that car parking accommodation is made permanently available to the standards adopted by the Local Planning Authority in the interest of highway safety, and that the development accords with Policy 24 of the Havering Local Plan. |
| 15. | All dwellings hereby approved shall comply with Regulation 36 (2)(b) and Part G2 of the Building Regulations - Water Efficiency.
Reason:-
In order to comply with Policy SI 5 of the London Plan. |
| 16. | All dwellings hereby approved shall be constructed to comply with Part M4(2) of the Building Regulations - Accessible and Adaptable Dwellings.
Reason: In order to comply with national optional technical standards as required by Policy D7 of the London Plan. |
| 17. | Notwithstanding the provisions of the Town and Country Planning (General Permitted Development) (England) Order 2015 no extension or enlargement (including additions to roofs and front porch) shall be made to the dwellings hereby permitted, or any detached building erected, without the express permission in writing of the Local Planning Authority.
Reason:-
In the interests of amenity and to enable the Local Planning Authority to retain control over future development. |
| 18. | Prior to the first occupation of the development hereby approved, the residential parking space(s) shall be provided with active vehicle charging facilities for electric or Ultra-Low Emission vehicles.
Reason:-
Provision prior to first occupation of the proposed dwellings hereby permitted will ensure that the development adequately incorporates measures to allow the use of electric vehicles by future occupiers in accordance with Policy T6.1 of the London Plan. |
| 19. | The proposal is liable for the Mayor of London Community Infrastructure Levy (CIL). The Mayoral CIL levy rate for Havering is 25/m² and is chargeable for each additional square metre of residential gross internal [floor] (GIA). Based upon the information supplied with the application, £2,225.00 would be payable due to result in new properties with a combined gross internal floor area of 89m² of GIA, however this may be adjusted subject to indexation.
The proposal is also liable for Havering Council's CIL. Havering's CIL charging rate for residential is £89m² (Zone A for each additional square metre of GIA. Based upon the information supplied with the application, £11,125.00 would be payable, subject to indexation.
The total chargeable amount is £13,350.00. The applicant has stated that the proposal is a self-build project and may therefore be eligible for exemption. To claim this exemption, the applicant must submit the relevant self-build exemption form and supporting evidence to the Council before commencement of development. Failure to do so will result in the full CIL charge becoming payable.
Further information on CIL and exemptions can be found on the Planning Portal or from the Council's website.