| No. | Condition Text |
|---|
| 1. | The development to which this permission relates must be commenced not later than three years from the date of this permission.
Reason:-
To comply with the requirements of Section 91 of the Town and Country Planning Act 1990 (as amended by Section 51 of the Planning and Compulsory Purchase Act 2004). |
| 2. | The development hereby permitted shall not be carried out otherwise than in complete accordance with the approved plans, particulars and specifications (as set out on page one of this decision notice).
Reason:-
The Local Planning Authority consider it essential that the whole of the development is carried out and that no departure whatsoever is made from the details approved, since the development would not necessarily be acceptable if partly carried out or carried out differently in any degree from the details submitted. Also, in order that the development accords with Development Control Policies Development Plan Document Policy DC61. |
| 3. | Before the building(s) hereby permitted is first occupied, provision shall be made for 2 x No. off-street car parking spaces within the site and thereafter this provision shall be made permanently available for use, unless otherwise agreed in writing by the Local Planning Authority.
Reason:
To ensure that adequate car parking provision is made off street in the interests of highway safety. |
| 4. | Before any of the development hereby permitted is commenced, samples of all materials to be used in the external construction of the building(s) shall be submitted to and approved in writing by the Local Planning Authority and thereafter the development shall be constructed with the approved materials.
Reason:-
To ensure that the appearance of the proposed development will harmonise with the character of the surrounding area and comply with Policy DC61 of the Development Control Policies Development Plan Document. |
| 5. | No development shall take place until there has been submitted to and approved by the Local Planning Authority a scheme of hard and soft landscaping, which shall include indications of all existing trees and shrubs on the site, and details of any to be retained, together with measures for the protection in the course of development. All planting, seeding or turfing comprised within the scheme shall be carried out in the first planting season following completion of the development and any trees or plants which within a period of 5 years from completion of the development die, are removed or become seriously damaged or diseased shall be replaced in the next planting season with others of a similar size and species, unless otherwise agreed in writing by the local Planning Authority.
Reason:-
In accordance with Section 197 of the Town and Country Planning Act 1990 and to enhance the visual amenities of the development, and that the development accords with the Development Control Policies Development Plan Document Policy DC61 |
| 6. | Notwithstanding the provisions of the Town and Country Planning (General Permitted Development) Order 1995 (as amended), no window or other opening (other than those shown on the submitted and approved plan,) shall be formed in the flank wall(s) of the building(s) hereby permitted, unless specific permission under the provisions of the Town and Country Planning Act 1990 has first been sought and obtained in writing from the Local Planning Authority.
Reason:-
In order to ensure a satisfactory development that will not result in any loss of privacy or damage to the environment of neighbouring properties which exist or may be proposed in the future, and in order that the development accords with Development Control Policies Development Plan Document Policy DC61. |
| 7. | The proposed first floor flank elevation windows serving bathrooms and en-suite bathrooms shall be permanently glazed with obscure glass and with the exception of top hung fanlights shall remain
permanently fixed shut and thereafter be maintained to the satisfaction of the Local Planning Authority, in order that the development accords with Policy DC61 of the LDF.
Reason:
In the interests of privacy. |
| 8. | Prior to completion of the works hereby permitted, cycle storage of a type and in a location previously submitted to and agreed in writing by the Local Planning Authority shall be provided and permanently retained thereafter.
Reason:-
In the interests of providing a wide range of facilities for non-motor car residents, in the interests of sustainability. |
| 9. | No construction works or deliveries into the site shall take place other than between the hours of 08.00 to 18.00 on Monday to Friday and 08.00 to 13.00 hours on Saturdays unless agreed in writing with the Local Planning Authority. No construction works or deliveries shall take place on Sundays, Bank or Public Holidays unless otherwise agreed in writing by the Local Planning Authority.
Reason:-
To protect residential amenity, and in order that the development accords with the Development Control Policies Development Plan Document Policy DC61. |
| 10. | Before development is commenced, a scheme shall be submitted to and approved in writing by the Local Planning Authority making provision for a Construction Method Statement to control the adverse impact of the development on the amenity of the public and nearby occupiers. The Construction Method statement shall include details of:
a) parking of vehicles of site personnel and visitors;
b) storage of plant and materials;
c) dust management controls;
d) measures for minimising the impact of noise and ,if appropriate, vibration arising from construction activities;
e) predicted noise and, if appropriate, vibration levels for construction using methodologies and at points agreed with the Local Planning Authority;
f) scheme for monitoring noise and if appropriate, vibration levels using methodologies and at points agreed with the Local Planning Authorities;
g) siting and design of temporary buildings;
h) scheme for security fencing/hoardings, depicting a readily visible 24-hour contact number for queries or emergencies;
i) details of disposal of waste arising from the construction programme, including final disposal points. The burning of waste on the site at any time is specifically precluded.
And the development shall be carried out in accordance with the approved scheme and statement.
Reason:-
To protect residential amenity, and in order that the development accords the Development Control Policies Development Plan Document Policy DC61. |
| 11. | The necessary agreement, notice or licence to enable the proposed alterations to the Public Highway shall be entered into prior to the commencement of the development.
Reason:
To ensure the interests of the travelling public and are maintained and comply with policies of the Core Strategy and Development Control Policies, namely CP10, CP17 and DC61. |
| 12. | Prior to the commencement of the development hereby permitted, details of the measures to be incorporated into the development demonstrating how 'Secured by Design' accreditation might be achieved shall be submitted to and approved in writing by the Local Planning Authority. The development shall be carried out in accordance with the approved details, and shall not be occupied or used until written confirmation of compliance with the agreed details has been submitted to and approved in writing by the LPA
Reason:
Reason: In the interest of creating safer, sustainable communities, reflecting guidance set out in the National Planning Policy Framework, Policy 7.3 of the London Plan, and Policies CP17 Design and DC63 Delivering Safer Places of the LBH LDF. |
| 13. | Prior to the first occupation of the development hereby permitted, provision shall be made for the storage of refuse and recycling awaiting collection according to details which shall previously have been agreed in writing by the Local Planning Authority.
Reason:
In the interests of amenity of occupiers of the development and also the visual amenity of the development and the locality generally, and in order that the development accords with the LDF Development Control Policies Development Plan Document Policy DC61 |
| 14. | Prior to the commencement of any works pursuant to this permission the developer shall submit for the written approval of the Local Planning Authority;
a) A Phase II (Site Investigation) Report as the Phase I Report which had already been submitted confirms the possibility of a significant risk to any sensitive receptors. This is an intrusive site investigation including factors such as chemical testing, quantitative risk assessment and a description of the sites ground conditions. An updated Site Conceptual Model should be included showing all the potential pollutant linkages and an assessment of risk to identified receptors.
b) A Phase III (Risk Management Strategy) Report if the Phase II Report confirms the presence of a significant pollutant linkage requiring remediation. The report will comprise of two parts:
Part A Remediation Statement which will be fully implemented before it is first occupied. Any variation to the scheme shall be agreed in writing to the Local Planning Authority in advance of works being undertaken. The Remediation Scheme is to include consideration and proposals to deal with situations where, during works on site, contamination is encountered which has not previously been identified. Any further contamination shall be fully assessed and an appropriate remediation scheme submitted to the Local Planning Authority for written approval.
Part B Following completion of the remediation works a Validation Report must be submitted demonstrating that the works have been carried out satisfactorily and remediation targets have been achieved.
c) If during development works any contamination should be encountered which was not previously identified and is derived from a different source and/or of a different type to those included in the contamination proposals then revised contamination proposals shall be submitted to the LPA ; and
d) If during development work, site contaminants are found in areas previously expected to be clean, then their remediation shall be carried out in line with the agreed contamination proposals.
For further guidance see the leaflet titled, Land Contamination and the Planning Process .
Reason:
To protect those engaged in construction and occupation of the development from potential contamination. |
| 15. | Notwithstanding the provisions of the Town and Country Planning (General Permitted Development) (Amendment) (No. 2) (England) Order 2008 Article 3, Schedule 2, Part 1, Classes A, B, C, D and E
which amends the Town and Country Planning (General Permitted Development) Order 1995 ("the 1995 Order"), no extensions, roof extensions, roof alterations or outbuildings shall take place unless permission under the provisions of the Town and Country Planning Act 1990 has first been sought and obtained in writing from the Local Planning Authority.
Reason:
In the interests of amenity and to enable the Local Planning Authority to retain control over future development, and in order that the development accords with Development Control Policies Development Plan Document Policy DC61. |
| 16. | Prior to the commencement of the development, all details of boundary screening shall be submitted to and approved in writing by the Local Planning Authority the approved details shall be implemented immediately on approval and shall be permanently retained and maintained thereafter to the satisfaction of the Local Planning Authority.
Reason:
To protect the visual amenities of the development and to prevent undue overlooking of adjoining properties. |
| 17. | The buildings shall be so constructed as to provide sound insulation of 45 DnT, w + Ctr dB (minimum value) against airborne noise to the satisfaction of the Local Planning Authority.
Reason:
To prevent noise nuisance to adjoining properties. |
| 18. | The proposed development is considered to be in accordance with the aims, objectives and provisions of policies CP1, CP17, DC3, DC33, DC35, DC55, DC61, DC63 and DC72 of the LDF Core Strategy and Development Control Policies Development Plan Document, Policies 3.3, 3.4, 3.5, 3.8, 6.9, 6.10, 6.13, 7.1, 7.2, 7.3, 7.4, 7.5 and 7.6 of the London Plan and Section 6 and 7 of the National Planning Policy Framework (NPPF).
Note: Following a change in government legislation a fee is now required when submitting details pursuant to the discharge of conditions, in order to comply with the Town and Country Planning (Fees for Applications and Deemed Applications) (Amendment) (England) Regulations, which came
into force from 06.04.2008. A fee of £85 per request (or £25 where the related permission was for extending or altering a dwellinghouse) is needed. |
| 19. | Statement Required by Article 31 (cc) of the Town and Country Planning (Development Management) Order 2010: No significant problems were identified during the consideration of the application, and therefore it has been determined in accordance with paragraphs 186-187 of the National Planning Policy Framework 2012. |
| 20. | The planning obligations recommended in this report have been subject to the statutory tests set out in Regulation 122 of the Community Infrastructure Levy Regulations 2010 and the obligations are considered to have satisfied the following criteria:-
(a) Necessary to make the development acceptable in planning terms;
(b) Directly related to the development; and
(c) Fairly and reasonably related in scale and kind to the development. |
| 21. | The Applicant is advised that planning approval does not constitute approval for changes to the public highway. Highway Authority approval will only be given after suitable details have been submitted, considered and agreed. Any proposals which involve building over the public highway as managed by the London Borough of Havering, will require a licence and the applicant must contact StreetCare, Traffic & Engineering on 01708 433750 to commence the Submission/ Licence Approval process.
The developer, their representatives and contractors are advised that planning permission does not discharge the requirements under the New Roads and Street Works Act 1991 and the Traffic Management Act 2004. Formal notifications and approval will be needed for any highway works (including temporary works) required during the construction of the development.
The developer is advised that if construction materials are proposed to be kept on the highway during construction works then they will need to apply for a license from the Council. |
| 22. | With regards to surface water drainage it is the responsibility of the developer to make proper provision for drainage to ground, water courses or a suitable sewer. In respect of surface water it is recommended that the applicant should ensure that storm flows are attenuated or regulated into the receiving public network through on or off site storage. When it is proposed to connect to a combined public sewer, the site drainage should be separate and combined at the final manhole nearest the boundary. Connections are not permitted for the removal of Ground Water. Where the developer proposes to discharge to a public sewer, prior approval from Thames Water Developer Services will be required. They can be contacted on 0845 850 2777. |
| 23. | In aiming to satisfy condition 12 the applicant should seek the advice of the Police Crime Prevention Design Advisor. The services of the local Police CPDA are available free of charge through Havering Development and Building Control. It is the policy of the local planning authority to consult with the Borough CPDA in the discharging of community safety condition(s). |