1.The development to which this permission relates must be commenced not later than three years from the date of this permission. Reason:- To comply with the requirements of Section 91 of the Town and Country Planning Act 1990 (as amended by Section 51 of the Planning and Compulsory Purchase Act 2004).
2.The development hereby permitted shall not be carried out otherwise than in complete accordance with the approved plans (as set out on page one of this decision notice). Reason:- The Local Planning Authority consider it essential that the whole of the development is carried out and that no departure whatsoever is made from the details approved, since the development would not necessarily be acceptable if partly carried out or carried out differently in any degree from the details submitted. Also, in order that the development accords with Development Control Policies Development Plan Document Policy DC61.
3.All new external finishes shall be carried out in materials to match those of the existing building(s) to the satisfaction of the Local Planning Authority. Reason:- To safeguard the appearance of the premises and the character of the immediate area, and in order that the development accords with the Development Control Policies Development Plan Document Policy DC61.
4.Before the dwellings hereby permitted are first occupied, the area set aside for car parking as indicated on drawing no. SP1737-2A shall be laid out and surfaced to the satisfaction of the Local Planning Authority and retained permanently thereafter for the accommodation of vehicles visiting the site and shall not be used for any other purpose. Reason:- To ensure that car parking accommodation is made permanently available to the standards adopted by the Local Planning Authority in the interest of highway safety, and that the development accords with the Development Control Policies Development Plan Document Policy DC33.
5.The necessary agreement, notice or licence to enable the proposed alterations to the Public Highway shall be entered into prior to the commencement of development. Reason:- In the interests of ensuring good design and ensuring public safety and to comply with policies CP10, CP17 and DC61 of the Core Strategy and Development Control Policies DPD.
6.No dwelling shall be occupied until refuse and recycling facilities are provided in accordance with details which shall previously have been submitted to and approved in writing by the Local Planning Authority. The refuse and recycling facilities shall be permanently retained thereafter. Reason:- Insufficient information has been supplied with the application to judge how refuse and recycling will be managed on site. Submission of this detail prior to occupation in the case of new building works or prior to the use commencing in the case of changes of use will protect the amenity of occupiers of the development and also the locality generally and ensure that the development accords with the Development Control Policies Development Plan Document Policy DC61.
7.No dwelling shall be occupied or use commenced until cycle storage is provided in accordance with details previously submitted to and approved in writing by the Local Planning Authority. The cycle storage shall be permanently retained thereafter. Reason:- Insufficient information has been supplied with the application to demonstrate what facilities will be available for cycle parking. Submission of this detail prior to occupation in the case of new building works or prior to the use commencing in the case of changes of use is in the interests of providing a wide range of facilities for non-motor car residents and sustainability.
8.A scheme shall be submitted in writing to and be approved by the local authority to show how the building(s) shall be so constructed as to provide sound insulation of 45 DnT,w + Ctr dB (minimum values) against airborne noise and 62 L'nT,w dB (maximum values) against impact noise to the satisfaction of the Local Planning Authority. The Approved scheme shall be implemented prior to first occupation of the premises. Reason:- To prevent noise nuisance to adjoining properties.
9.Statement Required by Article 35 (2) of the Town and Country Planning (Development Management Procedure) (England) Order 2015: No significant problems were identified during the consideration of the application, and therefore it has been determined in accordance with paragraphs 186-187 of the National Planning Policy Framework 2012.
10.The proposal is liable for the Mayor of London Community Infrastructure Levy (CIL). Based upon the information supplied with the application, the CIL payable would be £360 (this figure may go up or down, subject to indexation). CIL is payable within 60 days of commencement of development. A Liability Notice will be sent to the applicant (or anyone else who has assumed liability) shortly and you are required to notify the Council of the commencement of the development before works begin. Further details with regard to CIL are available from the Council's website.
11.The Applicant is advised that planning approval does not constitute approval for changes to the public highway. Highway Authority approval will only be given after suitable details have been submitted, considered and agreed. Any proposals which involve building over the public highway as managed by the London Borough of Havering, will require a licence and the applicant must contact StreetCare, Traffic & Engineering on 01708 433750 to commence the Submission/ Licence Approval process. Should this application be granted planning permission, the developer, their representatives and contractors are advised that this does not discharge the requirements under the New Roads and Street Works Act 1991 and the Traffic Management Act 2004. Formal notifications and approval will be needed for any highway works (including temporary works) required during the construction of the development. The developer is advised that if construction materials are proposed to be kept on the highway during construction works then they will need to apply for a license from the Council.
12.Before occupation of the residential/ commercial unit(s) hereby approved, it is a requirement to have the property/properties officially Street Named and Numbered by our Street Naming and Numbering Team. Official Street Naming and Numbering will ensure that that Council has record of the property/properties so that future occupants can access our services. Registration will also ensure that emergency services, Land Registry and the Royal Mail have accurate address details. Proof of having officially gone through the Street Naming and Numbering process may also be required for the connection of utilities. For further details on how to apply for registration see: https://www.havering.gov.uk/Pages/Services/Street-names-and-numbering.aspx