| No. | Condition Text |
|---|
| 1. | The development to which this permission relates must be commenced not later than three years from the date of this permission.
Reason:-
To comply with the requirements of Section 91 of the Town and Country Planning Act 1990 (as amended by Section 51 of the Planning and Compulsory Purchase Act 2004). |
| 2. | The development hereby permitted shall not be carried out otherwise than in complete accordance with the approved plans (as set out on page one of this decision notice).
Reason:-
The Local Planning Authority consider it essential that the whole of the development is carried out and that no departure whatsoever is made from the details approved, since the development would not necessarily be acceptable if partly carried out or carried out differently in any degree from the details submitted. Also, in order that the development accords with Development Control Policies Development Plan Document Policy DC61. |
| 3. | The premises shall not be used for the purposes hereby permitted other than between the hours of 10:00am and 22:30pm Monday through Saturday and 10:00 to 22:00 Sundays and Bank/Public holidays without the prior consent in writing of the Local Planning Authority.
Reason:-
To enable the Local Planning Authority to retain control in the interests of amenity, and in order that the development accords with Development Control Policies Development Plan Document Policy DC61. |
| 4. | Before any works commence a scheme for any new plant or machinery shall be submitted to the local planning authority to achieve the following standard. Noise levels expressed as the equivalent continuous sound level LAeq (1 hour) when calculated at the boundary with the nearest noise sensitive premises shall not exceed La90 -10dB and shall be maintained thereafter to the satisfaction of the Local Planning Authority.
Reason :-
Insufficient information has been supplied with the application to gauge the impact of any new plant or machinery. Submission of this detail prior to occupation in the case of new building works or prior to the use commencing in the case of changes of use will protect the amenity of adjoining occupiers of the development and also the locality generally and ensure that the development accords with the Development Control Policies Development Plan Document Policy DC61. |
| 5. | Before the use commences a scheme to control the transmission of noise and vibration from any mechanical ventilation system installed shall be submitted to and approved in writing by the Local Planning Authority and implemented prior to the permitted use commencing. Thereafter, the equipment shall be properly maintained and operated during normal working hours.
Reason :-
Insufficient information has been supplied with the application to judge how the transmission of noise and vibration will be controlled. Submission of this detail prior to occupation in the case of new building works or prior to the use commencing in the case of changes of use will protect the amenity of any adjoining occupiers of the development and also the locality generally and ensure that the development accords with the Development Control Policies Development Plan Document Policy DC61. |
| 6. | Before the use commences suitable equipment to remove and/or disperse odours and odorous material should be fitted to the extract ventilation system in accordance with a scheme to be designed and certified by a competent engineer and after installation a certificate to be lodged with the Planning Authority. Thereafter, the equipment shall be properly maintained and operated within design specifications during normal working hours.
Reason:-
Insufficient information has been supplied with the application to judge the technical specifications of the extract ventilation system. Submission of this detail prior to commencement of the use will protect the amenity of occupiers of nearby premises and ensure that the development accords with Development Control Policies Development Plan Document Policy DC61. |
| 7. | The A3 use herby approved shall not be commenced until refuse and recycling facilities are provided in accordance with details which have been previously submitted to and approved in writing by the Local Planning Authority. The refuse and recycling facilities shall be permanently retained thereafter.
Reason:-
Insufficient information has been supplied with the application to judge how refuse and recycling will be managed on site. Submission of this detail prior to occupation in the case of new building works or prior to the use commencing in the case of changes of use will protect the amenity of occupiers of the development and also the locality generally and ensure that the development accords with the Development Control Policies Development Plan Document Policy DC61. |
| 8. | Statement Required by Article 35 (2) of the Town and Country Planning (Development Management Procedure) (England) Order 2015: During consideration by the committee, members placed different weight on the planning merits and decided to grant planning permission contrary to officer recommendation. |