| 1. | The development to which this permission relates must be commenced not later than three years from the date of this permission.
Reason: To comply with the requirements of Section 91 of the Town and Country Planning Act 1990 (as amended by Section 51 of the Planning and Compulsory Purchase Act 2004). |
| 2. | The development hereby permitted shall not be carried out otherwise than in complete accordance with the approved plans (as set out on page one of this decision notice).
Reason: The Local Planning Authority consider it essential that the whole of the development is carried out and that no departure whatsoever is made from the details approved, since the development would not necessarily be acceptable if partly carried out or carried out differently in any degree from the details submitted. Also, in order that the development accords with Development Control Policies Development Plan Document Policy DC61. |
| 3. | Before the buildings hereby permitted are first occupied, the areas set aside for car parking shall be laid out and surfaced to the satisfaction of the Local Planning Authority. The parking areas shall be retained permanently thereafter for the accommodation of vehicles visiting the site and shall not be used for any other purpose.
Reason: To ensure that car parking accommodation is made permanently available to the standards adopted by the Local Planning Authority in the interest of highway safety and in order that the development accords with the LDF Development Control Policies Development Plan Document Policy DC33. |
| 4. | No works shall take place in relation to any of the development hereby approved until samples of all materials to be used in the external construction of the building(s) are submitted to and approved in writing by the Local Planning Authority and thereafter the development shall be constructed with the approved materials.
Reason: Insufficient information has been supplied with the application to judge the appropriateness of the materials to be used. Submission of samples prior to commencement will ensure that the appearance of the proposed development will harmonise with the character of the surrounding area and comply with Policy DC61 of the Development Control Policies Development Plan Document. |
| 5. | No works shall take place in relation to any of the development hereby approved until there has been submitted to and approved by the Local Planning Authority a scheme of hard and soft landscaping, which shall include indications of all existing trees and shrubs on the site, and details of any to be retained, together with measures for the protection in the course of development. All planting, seeding or turfing comprised within the scheme shall be carried out in the first planting season following completion of the development and any trees or plants which within a period of 5 years from completion of the development die, are removed or become seriously damaged or diseased shall be replaced in the next planting season with others of a similar size and species, unless otherwise agreed in writing by the local Planning Authority.
Reason: Insufficient information has been supplied with the application to judge the appropriateness of the hard and soft landscaping proposed. Submission of a scheme prior to commencement will ensure that the development accords with the Development Control Policies Development Plan Document Policy DC61. It will also ensure accordance with Section 197 of the Town and Country Planning Act 1990. |
| 6. | Before the development hereby approved is first occupied, refuse storage facilities shall be provided on site in accordance with the details shown on drawing no. 1542_N_PL_100 Revision G and retained permanently thereafter in accordance with the approved details.
Reason: In the interests of amenity of occupiers of the development and also the visual amenity of the development and the locality generally, and in order that the development accords with the LDF Development Control Policies Development Plan Document Policy DC61. |
| 7. | No building shall be occupied or use commenced until cycle storage is provided in accordance with details previously submitted to and approved in writing by the Local Planning Authority. The cycle storage shall be permanently retained thereafter.
Reason: Insufficient information has been supplied with the application to demonstrate what facilities will be available for cycle parking. Submission of this detail prior to occupation in the case of new building works or prior to the use commencing in the case of changes of use is in the interests of providing a wide range of facilities for non-motor car residents and sustainability. |
| 8. | Prior to the commencement of the development hereby approved, details of all proposed walls, fences and boundary treatment shall be submitted to, and approved in writing by, the Local Planning Authority. The boundary development shall then be carried out in accordance with the approved details and retained permanently thereafter to the satisfaction of the Local Planning Authority.
Reason:
Insufficient information has been supplied with the application to judge the appropriateness of any boundary treatment. Submission of this detail prior to commencement will protect the visual amenities of the development, prevent undue overlooking of adjoining property and ensure that the development accords with the Development Control Policies Development Plan Document Policy DC61. |
| 9. | No building shall be occupied or use commenced until external lighting is provided in accordance with details previously submitted to and approved in writing by the Local Planning Authority. The lighting shall be provided and operated in strict accordance with the approved scheme.
Reason:-
Insufficient information has been supplied with the application to judge the impact arising from any external lighting required in connection with the building or use. Submission of this detail prior to occupation in the case of new building works or prior to the use commencing in the case of changes of use will protect residential amenity and ensure that the development accords with the Development Control Policies Development Plan Document Policy DC61. |
| 10. | All building operations in connection with the construction of external walls, roof, and foundations; site excavation or other external site works; works involving the use of plant or machinery; the erection of scaffolding; the delivery of materials; the removal of materials and spoil from the site, and the playing of amplified music shall only take place between the hours of 8.00am and 6.00pm Monday to Friday, and between 8.00am and 1.00pm on Saturdays and not at all on Sundays and Bank Holidays/Public Holidays.
Reason:-
To protect residential amenity, and in order that the development accords with the Development Control Policies Development Plan Document Policy DC61. |
| 11. | Before the development hereby permitted is first commenced, vehicle cleansing facilities to prevent mud being deposited onto the public highway during construction works shall be provided on site in accordance with details which have previously been submitted to and approved in writing by the Local Planning Authority under application reference Q0105.18. The approved facilities shall be retained thereafter and used at relevant entrances to the site throughout the duration of construction works. If mud or other debris originating from the site is deposited in the public highway, all on-site operations shall cease until it has been removed.
The submission will provide;
a) A plan showing where vehicles will be parked within the site to be inspected for mud and debris and cleaned if required. The plan should show where construction traffic will access and exit the site from the public highway.
b) A description of how the parking area will be surfaced, drained and cleaned to prevent mud, debris and muddy water being tracked onto the public highway;
c) A description of how vehicles will be checked before leaving the site - this applies to the vehicle wheels, the underside of vehicles, mud flaps and wheel arches.
d) A description of how vehicles will be cleaned.
e) A description of how dirty/ muddy water be dealt with after being washing off the vehicles.
f) A description of any contingency plan to be used in the event of a break-down of the wheel washing arrangements.
Reason:-
To ensure that the facilities provided prevent materials from the site being deposited on the adjoining public highway, in the interests of highway safety and the amenity of the surrounding area. It will also ensure that the development accords with the Development Control Policies Development Plan Document Policies DC32 and DC61. |
| 12. | The development hereby approved shall be carried out in accordance with the Construction Method Statement which has been previously submitted to and approved in writing by the Local Planning Authority under application reference Q0105.18.
Reason:-
To ensure that the method of construction protects residential amenity. It will also ensure that the development accords the Development Control Policies Development Plan Document Policy DC61. |
| 13. | Prior to the commencement of any works pursuant to this permission the developer shall submit for the written approval of the Local Planning Authority;
a) A Phase I (Desktop Study) Report documenting the history of the site, its surrounding area and the likelihood of contaminant/s, their type and extent incorporating a Site Conceptual Model.
b) A Phase II (Site Investigation) Report if the Phase I Report confirms the possibility of a significant risk to any sensitive receptors. This is an intrusive site investigation including factors such as chemical testing, quantitative risk assessment and a description of the sites ground conditions. An updated Site Conceptual Model should be included showing all the potential pollutant linkages and an assessment of risk to identified receptors.
c) A Phase III (Remediation Strategy) Report if the Phase II Report confirms the presence of a significant pollutant linkage requiring remediation. A detailed remediation scheme to bring the site to a condition suitable for the intended use by removing unacceptable risks to all receptors must be prepared, and is subject to the approval in writing of the Local Planning Authority. The scheme must include all works to be undertaken, proposed remediation objectives and remediation criteria, timetable of works, site management procedures and procedure for dealing with previously unidentified any contamination. The scheme must ensure that the site will not qualify as contaminated land under Part 2A of the Environmental Protection Act 1990 in relation to the intended use of the land after remediation.
d) Following completion of measures identified in the approved remediation scheme mentioned in 1(c) above, a "Verification Report" that demonstrates the effectiveness of the remediation carried out, any requirement for longer-term monitoring of contaminant linkages, maintenance and arrangements for contingency action, must be produced, and is subject to the approval in writing of the Local Planning Authority.
Reason: Insufficient information regarding land contamination has been submitted with the application. Submission of this information prior to commencement will protect those engaged in construction and occupation of the development from potential contamination and in order that the development accords with Development Control Policies Development Plan Document Policy DC53. |
| 14. | a) If, during development, contamination not previously identified is found to be present at the site then no further development (unless otherwise agreed in writing with the local planning authority) shall be carried out until a remediation strategy detailing how this unsuspected contamination shall be dealt with has been submitted to and approved in writing by the local planning authority. The remediation strategy shall be implemented as approved.
b) Following completion of the remediation works as mentioned in (a) above, a 'Verification Report' must be submitted demonstrating that the works have been carried out satisfactorily and remediation targets have been achieved.
Reason: To ensure that any previously unidentified contamination found at the site is investigated and satisfactorily addressed in order to protect those engaged in construction and occupation of the development from potential contamination. |
| 15. | The development hereby approved shall be carried out in accordance with the Air Quality Assessment Report that has been previously submitted to and agreed by the Local Planning Authority under application reference Q0083.18.
.
Reason: To protect the amenity of future occupants and/or neighbours and in the interests of the declared Air Quality Management Area and to accord with Policy DC52 of the Development Control Policies Development Plan Document. |
| 16. | The development shall be carried out in accordance with the scheme of works for the proposed alterations to the public highway, approved by Highways and agreed under application reference Q0092.18. No occupation of the development hereby approved shall take place until the approved scheme of works has been implemented by or on behalf of the applicant in full in accordance with the Local Planning Authority's written approval and has been certified as complete on behalf of the Local Planning Authority.
Reason: Insufficient information has been submitted with regard to the proposed alterations to the public highway. Submission of this detail prior to commencement will be in the wider interests of the travelling public and are maintained and comply with policies CP10, CP17 and DC61 of the Core Strategy and Development Control Policies Development Plan Document. |
| 17. | The proposals should provide a 2.1 by 2.1 metre pedestrian visibility splay on either side of the proposed access, set back to the boundary of the public footway. There should be no obstruction or object higher than 0.6 metres within the visibility splay.
Reason:-
In the interests of highway safety, and in order that the development accords with the Development Control Policies Development Plan Document Policy DC32. |
| 18. | The development hereby approved shall not be occupied until a children's play area has been provided on the site, in accordance with details that shall have been previously submitted to and approved in writing by the Local Planning Authority. The play area shall be retained thereafter in accordance with the approved details.
Reason: In order to ensure the provision of adequate play facilities for children occupying the development and to accord with the provisions of Policy 3.6 of the London Plan. |
| 19. | The development hereby approved shall be carried out in accordance with the recommendations set out in Section 6 of the Ecological Assessment by Middlemarch Environmental dated May 2016. Particular regard shall be paid to recommendation R3 with regard to mitigating the impact of the development on nesting birds.
Reason: To ensure that the development has an acceptable ecological impact and to accord with Policy DC58 of the Development Control Policies Development Plan Document. |
| 20. | All dwellings hereby approved shall comply with Regulation 36 (2)(b) and Part G2 of the Building Regulations - Water Efficiency.
Reason: In order to comply with Policy 5.15 of the London Plan. |
| 21. | At least 4 of the dwellings hereby approved shall be constructed to comply with Part M4(3)(2)(a) of the Building Regulations - Wheelchair Adaptable Dwellings. The remainder of the dwellings hereby approved shall be constructed to comply with Part M4(2) of the Building Regulations - Accessible and Adaptable Dwellings.
Reason: In order to comply with Policy DC7 of the Local Development Framework and Policy 3.8 of the London Plan. |
| 22. | The development hereby approved shall be carried out in accordance with the measures to protect the retained trees during the course of development which have been previously submitted to and approved in writing by the Local Planning Authority under application reference Q0097.18.
Reason: To enable protection of the trees, in the interests of visual amenity and to accord with Policy DC60 of the Development Control Policies Development Plan Document. |
| 23. | No piling shall take place until a piling method statement (detailing the depth and type of piling to be undertaken and the methodology by which such piling will be carried out, including measures to prevent and minimise the potential for damage to subsurface sewerage infrastructure and the programme for the works) has been submitted to and approved in writing by the local planning authority in consultation with Thames Water. Any piling must be undertaken in accordance with the terms of the approved piling method statement.
Reason: The proposed works will be in close proximity to underground sewerage utility infrastructure. Piling has the potential to impact on local underground sewerage utility infrastructure. The applicant is advised to contact Thames Water Developer Services on 0800 009 3921 to discuss the details of the piling method statement. |
| 24. | Prior to occupation, 'as-built' BRUKL outputs prepared under the Standard Assessment Procedure (SAP) should be submitted to the Local Planning Authority and approved in writing to demonstrate that the development has been carried out in accordance with the approved details set out in the submitted Sustainable Design Construction Statement & Energy Strategy Report. If the development is unable to meet the required reduction in CO2 emissions through the approved energy strategy, then the development shall not be occupied until any shortfall has been provided off-site or through a cash in lieu contribution to the Council as set out in the London Plan, in accordance with details to be submitted to and agreed in writing by the Local Planning Authority.
Reason: In order that the development complies with Policies 5.2 and 5.3 of the London Plan. |
| 25. | The development hereby approved shall not be occupied until the proposed drainage strategy has been implemented in accordance with the SuDs and Flood Risk Assessment Report from XC02 Energy submitted as part of the application.
Reason: Surface water drainage works are required on site to prevent the risk of flooding. The measures detailed in the drainage strategy are considered to be technically sound and need to be implemented as part of the development to ensure that it accords with Development Control Policies Development Plan Document Policies DC49 and DC61. |
| 26. | Statement Required by Article 35 (2) of the Town and Country Planning (Development Management Procedure) (England) Order 2015: No significant problems were identified during the consideration of the application, and therefore it has been determined in accordance with paragraphs 186-187 of the National Planning Policy Framework 2012. |
| 27. | The proposal is liable for the Mayor of London Community Infrastructure Levy (CIL). Based upon the information supplied with the application, the CIL payable would be £77,056.00 (this figure may go up or down, subject to indexation). CIL is payable within 60 days of commencement of development. A Liability Notice will be sent to the applicant (or anyone else who has assumed liability) shortly and you are required to notify the Council of the commencement of the development before works begin. Further details with regard to CIL are available from the Council's website. |
| 28. | In aiming to satisfy conditions 7, 8 and 9 the applicant should seek the advice of the Metropolitan Police Designing Out Crime Officers (DOCOS). The servies of the Police DOCO's are available free of charge and can be contacted via docomailbox.ne@met.police.uk or 0208 217 3813. It is the policy of the local planning authority to consult with the DOCOs in the discharging of community safety conditions. |
| 29. | With regards to surface water drainage it is the responsibility of the developer to make proper provision for drainage to ground, water courses or a suitable sewer. In respect of surface water it is recommended that the applicant should ensure that storm flows are attenuated or regulated into the receiving public network through on or off site storage. When it is proposed to connect to a combined public sewer, the site drainage should be separate and combined at the final manhole nearest the boundary. Connections are not permitted for the removal of Ground Water. Where the developer proposes to discharge to a public sewer, prior approval from Thames Water Developer Services will be required. They can be contacted on 0845 850 2777. |
| 30. | There are public sewers crossing or close to your development. In order to protect public sewers and to ensure that Thames Water can gain access to those sewers for future repair and maintenance, approval should be sought from Thames Water where the erection of a building or an extension to a building or underpinning work would be over the line of, or would come within 3 metres of a public sewer. Thames Water will usually refuse such approval in respect of the construction of new buildings but approval may be granted in some cases for extensions to existing buildings. The applicant is advised to visit thameswater.co.uk/buildover. |
| 31. | A Groundwater Risk Management Permit from Thames Water will be required for discharging groundwater into a public sewer. Any discharge made without a permit is deemed illegal and may result in prosecution under the provisions of the Water Industry Act 1991. We would expect the developer to demonstrate what measures he will take to minimise groundwater discharges into the public sewer. Permit enquiries should be directed to Thames Water's Risk Management Team by telephoning 020 35779483 or by emailing wwqriskmanagement@thameswater.co.uk. Application forms should be completed online via www.thameswater.co.uk/wastewaterquality. |
| 32. | The Applicant is advised that planning approval does not constitute approval for changes to the public highway. Highway Authority approval will only be given after suitable details have been submitted, considered and agreed. If new or amended access is required (whether temporary or permanent) there may be a requirement for the diversion or protection of third party utility plant and it is recommended that early involvement with the relevant statutory undertaker takes place. The applicant must contact Engineering Services on 01708 433751 to discuss the scheme and commence the relevant highway approvals process. Please note that unauthorised work on the highway is an offence.
The developer, their representatives and contractors are advised that this does not discharge the requirements under the New Roads and Street Works Act 1991 and the Traffic Management Act 2004. Formal notifications and approval will be needed for any highway works (including temporary works) required during the construction of the development.
The developer is advised that if construction materials are proposed to be kept on the highway during construction works then they will need to apply for a license from the Council. If the developer requires scaffolding, hoarding or mobile cranes to be used on the highway a licence is required and Streetcare should be contacted on 01708 434343 to make the necessary arrangements. |
| 33. | The planning obligations recommended in this report have been subject to the statutory tests set out in Regulation 122 of the Community Infrastructure Levy Regulations 2010 and the obligations are considered to have satisfied the following criteria:-
(a) Necessary to make the development acceptable in planning terms;
(b) Directly related to the development; and
(c) Fairly and reasonably related in scale and kind to the development. |
| 34. | Before occupation of the residential/ commercial unit(s) hereby approved, it is a requirement to have the property/properties officially Street Named and Numbered by our Street Naming and Numbering Team. Official Street Naming and Numbering will ensure that that Council has record of the property/properties so that future occupants can access our services. Registration will also ensure that emergency services, Land Registry and the Royal Mail have accurate address details. Proof of having officially gone through the Street Naming and Numbering process may also be required for the connection of utilities. For further details on how to apply for registration see:
https://www.havering.gov.uk/Pages/Services/Street-names-and-numbering.aspx |