1.The development to which this permission relates must be commenced not later than three years from the date of this permission. Reason:- To comply with the requirements of Section 91 of the Town and Country Planning Act 1990 (as amended by Section 51 of the Planning and Compulsory Purchase Act 2004).
2.The development hereby permitted shall not be carried out otherwise than in complete accordance with the approved plans (as set out on page one of this decision notice). Reason:- The Local Planning Authority consider it essential that the whole of the development is carried out and that no departure whatsoever is made from the details approved, since the development would not necessarily be acceptable if partly carried out or carried out differently in any degree from the details submitted. Also, in order that the development accords with Development Control Policies Development Plan Document Policy DC61.
3.No above ground works shall take place in relation to any of the development hereby approved until written specification of external walls, roof materials and samples of all materials to be used in the external construction of the building(s) are submitted to and approved in writing by the Local Planning Authority and thereafter the development shall be constructed with the approved materials. Reason:- Insufficient information has been supplied with the application to judge the appropriateness of the materials to be used. Submission of samples prior to commencement will ensure that the appearance of the proposed development will harmonise with the character of the surrounding area and comply with Policy DC61 of the Development Control Policies Development Plan Document.
4.The roof area of the extension hereby permitted shall not be used as a balcony, roof garden or similar amenity area without the grant of further specific permission from the Local Planning Authority. Reason:- In the interests of the amenity of the occupiers of neighbouring dwelling, and in order that the development accords with the Development Control Policies Development Plan Document Policy DC61.
5.The proposed window at first floor on the eastern and western elevations serving en-suite and shower shall be permanently glazed with obscure glass not less than level 4 on the standard scale of obscurity and shall thereafter be maintained and permanently fixed shut and thereafter maintained, with the exception of any top hung fanlight(s). Reason:- In the interests of privacy, and in order that the development accords with the Development Control Policies Development Plan Document Policy DC61.
6.Notwithstanding the provisions of the Town and Country Planning (General Permitted Development) (England) Order 2015, no window or other opening (other than those shown on the submitted and approved plan,) shall be formed in the flank wall(s) of the extensions hereby permitted, unless specific permission under the provisions of the Town and Country Planning Act 1990 has first been sought and obtained in writing from the Local Planning Authority. Reason:- In order to ensure a satisfactory development that will not result in any loss of privacy or damage to the environment of neighbouring properties which exist or may be proposed in the future, and in order that the development accords with Development Control Policies Development Plan Document Policy DC61.
7.The hard surface hereby approved (including any sub-base) shall be made of porous materials or provision shall be made to direct run-off water from the hard surface to a permeable or porous area or surface within the curtilage of the dwellinghouse. Reason:- In order to ensure no water run-off from the hard surface which would contribute to risk of flooding
8.All existing trees as indicated on drawing no. TP-01RevC shall be retained in accordance with the approved plans. Reason:- In order to preserve the landscape character of Emerson Park Area.
9.Changes to the public highway (including permanent or temporary access) - Planning approval does not constitute approval for changes to the public highway. Highway Authority approval will only be given after suitable details have been submitted considered and agreed. If new or amended access is required (whether temporary or permanent), there may be a requirement for the diversion or protection of third party utility plant or highway authority assets and it is recommended that early involvement with the relevant statutory undertaker takes place. The applicant must contact Engineering Services on 01708 433751 to discuss the scheme and commence the relevant highway approvals process. Please note that unauthorised work on the highway is an offence. Highway legislation - The developer (including their representatives and contractors) is advised that planning consent does not discharge the requirements of the New Roads and Street Works Act 1991 and the Traffic Management Act 2004. Formal notifications and approval will be needed for any highway works (including temporary works of any nature) required during the construction of the development. Please note that unauthorised work on the highway is an offence. Temporary use of the public highway - The developer is advised that if construction materials are proposed to be kept on the highway during construction works then they will need to apply for a licence from the Council. If the developer required scaffolding, hoarding or mobile cranes to be used on the highway, a licence is required and Street Management should be contacted to make the necessary arrangements. Please note that unauthorised use of the highway for construction works is an offence. Surface water management - The developer is advised that surface water from the development in both its temporary and permanent states should not be discharged onto the highway. Failure to prevent such is an offence.
10.The proposal involves works which affect the highway and/or its verge. Before commencing such works you must obtain separate consent of the Highway Authority. Please contact the Streetcare on 01708 432563.
11.i) The new gates at front side of the property if hinged to the brick piers must open inwards as opposed to opening on to the highway. If the gates are sliding, must be installed within the property boundary line. ii) The paving at front garden of the property must allow permeability of water iii) At the front gates, install Echo drains to prevent water spilling onto the footway which must be connected to the surface water system
12.For Residential Development Only Please be advised that approval of this application from 1st September 2019 (either by London Borough of Havering, or subsequently by PINS if allowed on appeal following a refusal by London Borough of Havering) will attract a liability payment of £65,000 plus indexation in Community Infrastructure Levy (CIL). This charge has been levied under s.206 of the Planning Act 2008 and includes both the Mayor of London's CIL and Havering Council's CIL. London Borough of Havering, as CIL collecting authority, has responsibility for the collection of the Mayoral CIL, in addition to Havering's CIL, on commencement of the development. Your proposal is subject to a CIL Liability Notice indicating a levy of £65,000 plus indexation for the application, based on the Mayoral CIL levy rate for Havering of £25/sq.m plus Havering's charging rate for residential of £125/sq.m (Zone A) and the floorspace of 520 square metres. You are advised to visit the planning portal website where you can download the appropriate document templates. http://www.planningportal.gov.uk/planning/applications/howtoapply/whattosubmit/cil
13.Statement Required by Article 35(2) of the Town and Country Planning (Development Management) Order 2015: No significant problems were identified during the consideration of the application, and therefore it has been determined in accordance with paragraph 38 of the National Planning Policy Framework 2021.