1.The development to which this permission relates must be commenced not later than three years from the date of this permission. Reason:- To comply with the requirements of Section 91 of the Town and Country Planning Act 1990 (as amended by Section 51 of the Planning and Compulsory Purchase Act 2004).
2.All new external finishes shall be carried out in materials to match those of the existing building(s) to the satisfaction of the Local Planning Authority. Reason:- To safeguard the appearance of the premises and the character of the immediate area.
3.The development hereby permitted shall not be carried out otherwise than in complete accordance with the approved plans (as set out on page one of this decision notice). Reason:- For the avoidance of doubt and to ensure that the development is carried out as approved.
4.The windows to be inserted on the northern elevation shall be obscure-glazed, and non-opening unless the parts of the window which can be opened are more than 1.7m above the floor of the room in which the window is installed. Reason - In the interest of privacy and to protect the amenity of the adjacent neighbours
5.Notwithstanding the provisions of the Town and Country Planning (General Permitted Development) (England) Order 2015, no window or other opening (other than those shown on the submitted and approved plan,) shall be formed in the flank wall(s) of the building(s) hereby permitted, unless specific permission under the provisions of the Town and Country Planning Act 1990 has first been sought and obtained in writing from the Local Planning Authority. Reason:- In order to ensure a satisfactory development that will not result in any loss of privacy or damage to the environment of neighbouring properties which exist or may be proposed in the future.
6.The hard surface hereby approved (including any sub-base) shall be made of porous materials or provision shall be made to direct run-off water from the hard surface to a permeable or porous area or surface within the curtilage of the dwellinghouse. Reason:- In order to ensure no water run-off from the hard surface which would contribute to risk of flooding
7.Statement Required by Article 35 (2) of the Town and Country Planning (Development Management Procedure) (England) Order 2015: In accordance with paragraph 38 of the National Planning Policy Framework, improvements required to make the proposal acceptable were negotiated with the agent via email. The revisions involved revising the left side elevation drawing to show the proposed windows and to increase the number of provided off-street parks. The amendments were subsequently submitted on 22/08/2023.
8.For any development where a flood risk is identified, the Council as the Lead Local Flood Authority want to see developers consider and implement flood resilience/resistance measures into the buildings themselves. This is not to stop development but to ensure the protection for future residents is maintained and enhanced. The following measures are strongly recommended, although this list is not exhaustive:- - Raising the level of the building by at least 300mm above local levels; - Waterproof membrane in the ground floor; - Waterproof plaster and waterproofing to ground floor; - Electrics from the upstairs down and sockets high up off the ground floor; - Non return valves on the sewerage pipes; - Emergency escape plan for each individual property; - Air brick covers; and - Movable flood barriers for entrances