The London Borough Of Havering - Home page

No.Condition Text
1.The development to which this permission relates must be commenced not later than three years from the date of this permission. Reason:- To comply with the requirements of Section 91 of the Town and Country Planning Act 1990 (as amended by Section 51 of the Planning and Compulsory Purchase Act 2004).
2.The development hereby permitted shall not be carried out otherwise than in complete accordance with the approved plans (as set out on page one of this decision notice). Reason:- For the avoidance of doubt and to ensure that the development is carried out as approved.
3.A shop window display shall be provided at all times in the window(s) fronting Avon Road. Reason:- In the interests of visual amenity and to retain an active frontage at ground floor level to support street activity and generate pedestrian movement (Local Plan policy 13).
4.The premises shall not be used for the purposes hereby permitted other than between the hours of 08:00 to 23:00 Mondays to Saturdays and 10:00 to 22:30 Sundays and Bank or Public Holidays without the prior consent in writing of the Local Planning Authority. Reason:- To enable the Local Planning Authority to retain control in the interests of amenity (Local Plan policy 7 and 34).
5.All refuse and recycling waste shall be stored within the premises until collection by the appropriate company unless otherwise first agreed in writing by the Local Planning Authority. Reason:- In the interests of visual and neighbour amenity, in accordance with Policy 35 of the Local Plan.
6.This permission does not confer or imply approval for any alterations to the exterior of the building or advertisements, which may require submission of a further application.
7.The applicant's attention is drawn in particular to condition number 3 above. Failure to comply with this condition may well result in enforcement proceedings being taken against you.
8.Changes to the public highway (including permanent or temporary access) - Planning approval does not constitute approval for changes to the public highway. Highway Authority approval will only be given after suitable details have been submitted considered and agreed. If new or amended access is required (whether temporary or permanent), there may be a requirement for the diversion or protection of third party utility plant or highway authority assets and it is recommended that early involvement with the relevant statutory undertaker takes place. The applicant must contact Engineering Services on 01708 433751 to discuss the scheme and commence the relevant highway approvals process. Please note that unauthorised work on the highway is an offence. Highway legislation - The developer (including their representatives and contractors) is advised that planning consent does not discharge the requirements of the New Roads and Street Works Act 1991 and the Traffic Management Act 2004. Formal notifications and approval will be needed for any highway works (including temporary works of any nature) required during the construction of the development. Please note that unauthorised work on the highway is an offence. Temporary use of the public highway - The developer is advised that if construction materials are proposed to be kept on the highway during construction works then they will need to apply for a licence from the Council. If the developer required scaffolding, hoarding or mobile cranes to be used on the highway, a licence is required and Street Management should be contacted to make the necessary arrangements. Please note that unauthorised use of the highway for construction works is an offence. Surface water management - The developer is advised that surface water from the development in both its temporary and permanent states should not be discharged onto the highway. Failure to prevent such is an offence.
9.Statement Required by Article 35(2) of the Town and Country Planning (Development Management) Order 2015: No significant problems were identified during the consideration of the application, and therefore it has been determined in accordance with paragraph 38 of the National Planning Policy Framework.