The London Borough Of Havering - Home page

No.Condition Text
1.This permission shall be for a limited period only expiring on 9th September 2027 on or before which date the temporary building(s) carried out under this permission shall be removed and the site reinstated to its former condition to the satisfaction of the Local Planning Authority. Reason:- The temporary nature of the building(s) is such that permanent permission would not be appropriate in the interests of amenity. This permission is therefore granted on a temporary basis to enable the Local Planning Authority to retain control, and that the development accords with the Development Control Policies Development Plan Document Policy DC61.
2.The proposed development hereby approved shall be constructed in accordance with the materials detailed under Section 2.8 of the Planning Statement - Global House, Ferry Lane, Rainham dated June 2021 unless otherwise agreed in writing by the Local Planning Authority. Reason: To ensure that the appearance of the proposed development will harmonise with the character of the surrounding area and comply with Policy DC61 of the Development Control Policies Development Plan Document
3.The development hereby permitted shall not be carried out otherwise than in complete accordance with the approved plans (as set out on page one of this decision notice). Reason:- For the avoidance of doubt and to ensure that the development is carried out as approved.
4.Prior to the first occupation of the development, details shall be submitted to and agreed in writing by the Local Planning Authority for the installation of Ultra-Low NOx boilers with maximum NOx Emissions less than 40 mg/kWh. Where any installations do not meet this emissions standard it should not be operated without the fitting of suitable NOx abatement equipment or technology as determined by a specialist to ensure comparable emissions. The installation of the boilers shall be carried out in strict accordance with the agreed details and shall thereafter be permanently retained. Following installation emissions certificates will need to be provided to the Local Planning Authority to verify boiler emissions. Reason: To minimise the impact of building emissions on local air quality.
5.Statement Required by Article 35(2) of the Town and Country Planning (Development Management) Order 2015: No significant problems were identified during the consideration of the application, and therefore it has been determined in accordance with paragraph 38 of the National Planning Policy Framework.
6.The proposal is liable for the Mayor of London Community Infrastructure Levy (CIL). The Mayoral CIL levy rate for Havering is ????£25/m????² and is chargeable for each additional square metre of residential gross internal [floor] (GIA). Based upon the information supplied with the application, ????£12,925 would be payable due to result of the proposed building with 517m?????² of GIA, however this may be adjusted subject to indexation. This charge is levied under s.206 of the Planning Act 2008. CIL is payable within 60 days of commencement of development. A Liability Notice will be sent to the applicant (or anyone else who has assumed liability) shortly and you are required to notify the Council of the commencement of the development before works begin. Further details with regard to CIL are available from the Council's website. You are also advised to visit the planning portal website where you can download the appropriate document templates at http://www.planningportal.gov.uk/planning/applications/howtoapply/whattosubmit/cil
7.A fee is required when submitting details pursuant to the discharge of conditions. In order to comply with the Town and Country Planning (Fees for Applications, Deemed Applications, Requests and Site Visits) (England) Regulations 2012, (as amended), a fee of £116 per request or £34 where the related permission was for extending or altering a dwellinghouse, is needed.
8.The Environmental Permitting (England and Wales) Regulations 2016 require a permit to be obtained for any activities which will take place: · on or within 8 metres of a main river (16 metres if tidal) · on or within 8 metres of a flood defence structure or culvert (16 metres if tidal) · on or within 16 metres of a sea defence ?· involving quarrying or excavation within 16 metres of any main river, flood defence (including a remote defence) or culvert ?· in a floodplain more than 8 metres from the river bank, culvert or flood defence structure (16 metres if it's a tidal main river) and you do not already have planning permission. For further guidance please visit https://www.gov.uk/guidance/flood-risk-activities-environmental-permits or contact our National Customer Contact Centre on 03702 422 549. The applicant should not assume that a permit will automatically be forthcoming once planning permission has been granted, and we advise them to consult with us at the earliest opportunity.