| No. | Condition Text |
|---|
| 1. | The development to which this permission relates must be commenced not later than three years from the date of this permission.
Reason:-
To comply with the requirements of Section 91 of the Town and Country Planning Act 1990 (as amended by Section 51 of the Planning and Compulsory Purchase Act 2004). |
| 2. | The development hereby permitted shall not be carried out otherwise than in complete accordance with the approved plans, particulars and specifications.
Reason:-
For the avoidance of doubt and to ensure that the development is carried out as approved. Also, in order that the development accords with Development Control Policies Development Plan Document Policy DC61. |
| 3. | Prior to the first occupation of the development hereby permitted, provision shall be made for the storage of refuse awaiting collection on site and retained thereafter.
Reason:-
In the interests of amenity of occupiers of the development and also the visual amenity of the development and the locality generally, and in order that the development accords with the Development Control Policies Development Plan Document Policy DC61. |
| 4. | The premises shall not be used for the purposes hereby permitted other than between the hours of 9am - 6pm Monday, Tuesday, Thursday, Friday, 9am-8pm Wednesday, 8.30am-6pm Saturday, 9am-5pm Sunday and not at all on public/bank holidays without the prior consent in writing of the Local Planning Authority, in order that the development accords with the LDF Development Control Policies Development Plan Document.
Reason:-
To enable the Local Planning Authority to retain control in the interests of amenity, and in order that the development accords with Development Control Policies Development Plan Document Policy DC61. |
| 5. | Before the use commences suitable equipment to remove and/or disperse odours and odorous material should be fitted to the extract ventilation system in accordance with a scheme submitted to and approved in writing by the LPA in consultation with the Havering Public Protection Service.
The approved equipment shall be installed on site and certification provided by a competent engineer. Thereafter, the equipment shall be properly maintained and operated within design specifications during normal working hours.
Reason
To protect the amenity of occupiers of nearby premises and ensure that the development accords with Development Control Policies Development Plan Document Policy DC61. |
| 6. | Statement Required by Article 31 (cc) of the Town and Country Planning (Development Management) Order 2010: No significant problems were identified during the consideration of the application, and therefore it has been determined in accordance with the National Planning Policy Framework 2019. |
| 7. | Environmental health recommend for you to follow the HSE Guidance - HSE SR13 Nail Bars and HSG 258 - Controlling airborne contaminants at work: A guide to local exhaust ventilation (LEV) to meet the necessary requirements.
Please also ask the applicant to have regard to the following italicised guidance and issues as an informative to the decision notice:
Guidance is provided in: :
· Workplace, Health, Safety and; Welfare Approved Code of Practice L24 ISBN 0-7176-0413-6 available to order from book shops.
Further information is available at the following web sites:
· Occupational safety & health - www.hse.gov.uk |