No.Condition Text
1.Details of the Landscaping (hereinafter called "the reserved matters") shall be submitted to and approved in writing by the local planning authority before any development begins and the development shall be carried out as approved. Reason:- This is outline permission only and these matters have been reserved for the subsequent approval of the Local Planning Authority.
2.Application/s for approval of the reserved matters shall be submitted to the Local Planning Authority within three years from the date of this permission. Reason:- To comply with Section 92 of the Town and Country Planning Act 1990 (as amended by Section 51 of the Planning and Compulsory Purchase Act 2004).
3.Before the building(s) hereby permitted is first occupied, the area set aside for car parking shall be laid out and surfaced to the satisfaction of the Local Planning Authority and retained permanently thereafter for the accommodation of vehicles visiting the site and shall not be used for any other purpose. Reason:- To ensure that car parking accommodation is made permanently available to the standards adopted by the Local Planning Authority in the interest of highway safety.
4.Before any work above damp proof course for the development hereby permitted is commenced, written specification of external walls and roof materials to be used in the construction of the building(s) shall be submitted to and approved in writing by the Local Planning Authority and thereafter the development shall be constructed with the approved materials. Reason:- Insufficient information has been supplied with the application to judge the appropriateness of the materials to be used. Submission of a written specification prior to commencement will ensure that the appearance of the proposed development will harmonise with the character of the surrounding area.
5.The boundary treatment shall be carried out in accordance to the drawing 1514-310 D hereby approved prior to the first occupation of the site and retained permanently thereafter to the satisfaction of the Local Planning Authority. Reason: To protect the visual amenities of the development and prevent undue overlooking of adjoining property.
6.The development hereby permitted shall not be carried out otherwise than in complete accordance with the approved plans (as set out on page one of this decision notice). Reason:- For the avoidance of doubt and to ensure that the development is carried out as approved.
7.Any window on the flank elevation of the dwelling hereby approved shall be shall be permanently glazed with obscure glass not less than obscurity level 4. on the standard scale of obscurity and shall thereafter be maintained and permanently fixed shut and thereafter maintained, with the exception of any top hung fanlight(s). Reason:- In the interests of privacy.
8.Notwithstanding the provisions of the Town and Country Planning (General Permitted Development) (England) Order 2015, other than porches erected in accordance with the Order, no outbuilding, no extension or enlargement (including additions to roofs) shall be made to the dwellinghouse(s) hereby permitted, or any other opening to the flank elevations be carried, without the express permission in writing of the Local Planning Authority. Reason:- In the interests of amenity and to enable the Local Planning Authority to retain control over future development.
9.No works shall take place in relation to any of the development hereby approved until details of surface water drainage works are submitted to and approved in writing by the Local Planning Authority. Surface water drainage shall be provided in accordance with the approved details. Reason:- Surface water drainage works are required on site to prevent the risk of flooding. Submission of a scheme prior to commencement will ensure that the measures to be employed are technically sound.
10.No building shall be occupied or use commenced until refuse and recycling facilities are provided in accordance the drawing numbered 1514-310 D hereby approved. The refuse and recycling facilities shall be permanently retained thereafter. Reason:- To protect the amenity of occupiers of the development and also the locality generally.
11.No building shall be occupied or use commenced until cycle storage is provided in accordance to the drawing numbered 1514-310 D hereby approved. The cycle storage shall be permanently retained thereafter. Reason:- In the interests of providing a wide range of facilities for non-motor car residents and sustainability.
12.All building operations in connection with the construction of external walls, roof, and foundations; site excavation or other external site works; works involving the use of plant or machinery; the erection of scaffolding; the delivery of materials; the removal of materials and spoil from the site, and the playing of amplified music shall only take place between the hours of 8.00am and 6.00pm Monday to Friday, and between 8.00am and 1.00pm on Saturdays and not at all on Sundays and Bank Holidays/Public Holidays. Reason:- To protect residential amenity.
13.No works shall take place in relation to any of the development hereby approved until a Construction Method Statement to control the adverse impact of the development on the amenity of the public and nearby occupiers is submitted to and approved in writing by the Local Planning Authority. The Construction Method statement shall include details of: a) parking of vehicles of site personnel and visitors; b) storage of plant and materials; c) dust management controls; d) measures for minimising the impact of noise and ,if appropriate, vibration arising from construction activities; e) predicted noise and, if appropriate, vibration levels for construction using methodologies and at points agreed with the Local Planning Authority; f) scheme for monitoring noise and if appropriate, vibration levels using methodologies and at points agreed with the Local Planning Authorities; g) siting and design of temporary buildings; h) scheme for security fencing/hoardings, depicting a readily visible 24-hour contact number for queries or emergencies; i) details of disposal of waste arising from the construction programme, including final disposal points. The burning of waste on the site at any time is specifically precluded. And the development shall be carried out in accordance with the approved scheme and statement. Reason:- Insufficient information has been supplied with the application in relation to the proposed construction methodology. Submission of details prior to commencement will ensure that the method of construction protects residential amenity.
14.Before the development hereby approved is first occupied, the site shall be equipped with both passive and active provision of electric vehicle charging points, in accordance with details which shall have been previously submitted to and approved in writing by the Local Planning Authority. This shall provide a minimum of 20 per cent of all spaces for active charging point for electric vehicles, with the passive charging provision for all remaining spaces for the electric vehicles in the future. The development shall be implemented in accordance to approved details prior to first occupation and thereafter be maintained as such. Reason: In order to encourage the uptake of the use of electric vehicles and to comply with Policy T6.13 of London Plan
15.No building shall be occupied or use commenced until external lighting with respect to the terrace of the building to the rear including the access and driveway is carried out in accordance to the drawing numbered 1514-310 D hereby approved. The lighting shall be provided and operated in strict accordance with the approved scheme. Reason:- To protect residential amenity of the existing and future occupiers of the site.
16.All dwellings hereby approved shall comply with Regulation 36 (2)(b) and Part G2 of the Building Regulations - Water Efficiency. Reason: In order to comply with national optional technical standards as required by Policy SI5 of the London Plan.
17.Contamination a) If, during development, contamination not previously identified is found to be present at the site then no further development (unless otherwise agreed in writing with the local planning authority) shall be carried out until a remediation strategy detaining how this unsuspected contamination shall be dealt with has been submitted to and approved in writing by the local planning authority. The remediation strategy shall be implemented as approved. b) Following completion of the remediation works as mentioned in (a) above a 'verification report' must be submitted to demonstrating that the works have been carried out satisfactorily and remediation targets have been achieved. Reason; To ensure that any previously unidentified contamination found at the site is investigated and satisfactorily addressed in order to protect those engaged in construction and occupation of the development from potential contamination.
18.At least 10 percent of the dwellings hereby approved shall be constructed to comply with Part M4(3) of the Building Regulations - Wheelchair Adaptable Dwellings. The remainder of the dwellings hereby approved shall be constructed to comply with Part M4(2) of the Building Regulations - Accessible and Adaptable Dwellings. Reason: In order to comply with Policy 7 of the Local Plan.
19.No development shall commence on site, until a swept path diagram and analysis has been provided for all types of vehicles visiting the site in particular fire engines to ensure the vehicles would be able to enter and manoeuvre within the site. The proposals should also provide a 2.1 by 2.1 metre pedestrian visibility splay on either side of the proposed access, set back to the boundary of the public footway. There should be no obstruction or object higher than 0.6 metres within the visibility splay. Reason:- In the interests of highway safety.
20.Prior to the first occupation of the development, details shall be submitted to and agreed in writing by the Local Planning Authority for the installation of Ultra-Low NOx boilers with maximum NOx Emissions less than 40 mg/kWh. Where any installations do not meet this emissions standard it should not be operated without the fitting of suitable NOx abatement equipment or technology as determined by a specialist to ensure comparable emissions. The installation of the boilers shall be carried out in strict accordance with the agreed details and shall thereafter be permanently retained. Following installation emissions certificates will need to be provided to the Local Planning Authority to verify boiler emissions. Reason: To minimise the impact of building emissions on local air quality.
21.INFORMATIVE In promoting the delivery of safer, stronger, sustainable places the Local Planning Authority fully supports the adoption of the principles and practices of the Secured by Design Award Scheme and Designing against Crime. Your attention is drawn to the free professional service provided by the Metropolitan Police Designing Out Crime Officers for North East London, whose can be contacted via DOCOMailbox.NE@met.police.uk or 0208 217 3813 . They are able to provide qualified advice on incorporating crime prevention measures into new developments.
22.Changes to the public highway (including permanent or temporary access) - Planning approval does not constitute approval for changes to the public highway. Highway Authority approval will only be given after suitable details have been submitted considered and agreed. If new or amended access is required (whether temporary or permanent), there may be a requirement for the diversion or protection of third party utility plant or highway authority assets and it is recommended that early involvement with the relevant statutory undertaker takes place. The applicant must contact Engineering Services on 01708 433751 to discuss the scheme and commence the relevant highway approvals process. Please note that unauthorised work on the highway is an offence. Highway legislation - The developer (including their representatives and contractors) is advised that planning consent does not discharge the requirements of the New Roads and Street Works Act 1991 and the Traffic Management Act 2004. Formal notifications and approval will be needed for any highway works (including temporary works of any nature) required during the construction of the development. Please note that unauthorised work on the highway is an offence. Temporary use of the public highway - The developer is advised that if construction materials are proposed to be kept on the highway during construction works then they will need to apply for a licence from the Council. If the developer required scaffolding, hoarding or mobile cranes to be used on the highway, a licence is required and Street Management should be contacted to make the necessary arrangements. Please note that unauthorised use of the highway for construction works is an offence. Surface water management - The developer is advised that surface water from the development in both its temporary and permanent states should not be discharged onto the highway. Failure to prevent such is an offence.
23.Statement Required by Article 35 (2) of the Town and Country Planning (Development Management Procedure) (England) Order 2015: In accordance with paragraph 38 of the National Planning Policy Framework, improvements required to make the proposal acceptable were negotiated with the applicants agent with respect to layout, massing and design. The latest revised scheme received on 11th November 2022.
24.The proposed development will create 452sqm of new net gross internal floorspace. The proposal is liable for LB Havering CIL and will incur a charge of £56,500.00 (subject to indexation) based on the calculation of £125.00 per square metre. The proposal is also liable for Mayoral CIL and will incur a charge of £P11,300.00 (subject to indexation) based on the calculation of £25.00 per square metre. These charges are levied under s.206 of the Planning Act 2008. CIL is payable within 60 days of commencement of development. A Liability Notice will be sent to the applicant (or anyone else who has assumed liability) shortly and you are required to notify the Council of the commencement of the development before works begin. Further details with regard to CIL are available from the Council's website. You are also advised to visit the planning portal website where you can download the appropriate document templates at http://www.planningportal.gov.uk/planning/applications/howtoapply/whattosubmit/cil