1.The development to which this permission relates must be commenced not later than three years from the date of this permission. Reason:- To comply with the requirements of Section 91 of the Town and Country Planning Act 1990 (as amended by Section 51 of the Planning and Compulsory Purchase Act 2004).
2.The development hereby permitted shall not be carried out otherwise than in complete accordance with the approved plans (as set out on page one of this decision notice). Reason:- The Local Planning Authority consider it essential that the whole of the development is carried out and that no departure whatsoever is made from the details approved, since the development would not necessarily be acceptable if partly carried out or carried out differently in any degree from the details submitted. Also, in order that the development accords with Development Control Policies Development Plan Document Policy DC61.
3.The proposed development hereby approved shall be constructed in accordance with the materials detailed under Section 9 of the application form unless otherwise agreed in writing by the Local Planning Authority. Reason:- To ensure that the appearance of the proposed development will harmonise with the character of the surrounding area and comply with Policy DC61 of the Development Control Policies Development Plan Document
4.Before the use hereby permitted is commenced, the area set aside for car parking shall be laid out and surfaced to the satisfaction of the Local Planning Authority and retained permanently thereafter for the accommodation of vehicles visiting the site and shall not be used for any other purpose. Reason:- To ensure that car parking accommodation is made permanently available to the standards adopted by the Local Planning Authority in the interest of highway safety, and that the development accords with the Development Control Policies Development Plan Document Policy DC33.
5.If during development any contamination should be encountered then no further development (unless otherwise agreed in writing with the Local Planning Authority) shall be undertaken until a 'Remediation Strategy' detailing how the contamination shall be dealt with has been submitted to and approved in writing by the Local Planning Authority. The remediation strategy shall be implemented as approved. Following completion of the remediation works, mentioned above, a 'Verification Report' must be submitted demonstrating that the works have been carried out satisfactorily and remediation targets have been achieved. Reason:- To ensure that any contamination found at the site is investigated and satisfactorily addressed in order to protect those engaged in construction and occupation and to comply with Development Control Policies Development Plan Document Policy DC53.
6.Statement Required by Article 35 (2) of the Town and Country Planning (Development Management Procedure) (England) Order 2015: No significant problems were identified during the consideration of the application, and therefore it has been determined in accordance with paragraphs 186-187 of the National Planning Policy Framework 2012.