No.Condition Text
1.The development to which this permission relates must be commenced not later than three years from the date of this permission. Reason:- To comply with the requirements of Section 91 of the Town and Country Planning Act 1990 (as amended by Section 51 of the Planning and Compulsory Purchase Act 2004).
2.Before any of the development hereby permitted is commenced, samples of all materials to be used in the external construction of the building(s) shall be submitted to and approved in writing by the Local Planning Authority and thereafter the development shall be constructed with the approved materials. Reason:- Insufficient information has been supplied with the application to judge the appropriateness of the materials to be used. Submission of samples prior to commencement will ensure that the appearance of the proposed development will harmonise with the character of the surrounding area and comply with Policy DC61 of the Development Control Policies Development Plan Document.
3.The development hereby permitted shall not be carried out otherwise than in complete accordance with the approved plans (as set out on page one of this decision notice). Reason:- The Local Planning Authority consider it essential that the whole of the development is carried out and that no departure whatsoever is made from the details approved, since the development would not necessarily be acceptable if partly carried out or carried out differently in any degree from the details submitted. Also, in order that the development accords with Development Control Policies Development Plan Document Policy DC61.
4.Notwithstanding the provisions of the Town and Country Planning (General Permitted Development) Order 1995 (as amended), no window or other opening (other than those shown on the submitted and approved plan,) shall be formed in the flank wall(s) of the building(s) hereby permitted, unless specific permission under the provisions of the Town and Country Planning Act 1990 has first been sought and obtained in writing from the Local Planning Authority. Reason:- In order to ensure a satisfactory development that will not result in any loss of privacy or damage to the environment of neighbouring properties which exist or may be proposed in the future, and in order that the development accords with Development Control Policies Development Plan Document Policy DC61.
5.No development shall take place until there has been submitted to and approved by the Local Planning Authority a scheme of hard and soft landscaping, which shall include indications of all existing trees and shrubs on the site, and details of any to be retained, together with measures for the protection in the course of development. The scheme shall include the landscape treatment of the courtyard. All planting, seeding or turfing comprised within the scheme shall be carried out in the first planting season following completion of the development and any trees or plants which within a period of 5 years from completion of the development die, are removed or become seriously damaged or diseased shall be replaced in the next planting season with others of a similar size and species, unless otherwise agreed in writing by the local Planning Authority. Reason: Insufficient information has been supplied with the application to judge the appropriateness of the hard and soft landscaping proposed. Submission of a scheme prior to commencement will ensure that the development accords with the Development Control Policies Development Plan Document Policy DC61. It will also ensure accordance with Section 197 of the Town and Country Planning Act 1990.
6.Prior to the first occupation of the development hereby permitted, provision shall be made for the storage of refuse and recycling awaiting collection according to details which shall previously have been agreed in writing by the Local Planning Authority. Reason:- Insufficient information has been supplied with the application to judge how refuse and recycling will be managed on site. Submission of this detail prior to occupation in the case of new building works or prior to the use commencing in the case of changes of use will protect the amenity of occupiers of the development and also the locality generally and ensure that the development accords with the Development Control Policies Development Plan Document Policy DC61.
7.Prior to completion of the works hereby permitted, cycle storage of a type and in a location previously submitted to and agreed in writing by the Local Planning Authority shall be provided and permanently retained thereafter. Reason:- Insufficient information has been supplied with the application to demonstrate what facilities will be available for cycle parking. Submission of this detail prior to occupation in the case of new building works or prior to the use commencing in the case of changes of use is in the interests of providing a wide range of facilities for non-motor car residents and sustainability.
8.Before the A3 use hereby approved commences suitable equipment to remove and/or disperse odours and odorous material should be fitted to the extract ventilation system with the additional use of carbon filters in accordance with a scheme to be designed and certified by a competent engineer and after installation a certificate to be lodged with the Planning Authority. 1. Control may include fine filtration or ESP followed by carbon filtration (carbon filters rated with 0.4-0.8 second residence time) 2. Fine filtration or ESP followed by carbon filtration and by counteracting/neutralising system to achieve the same level of control as 1. 3. Fine filtration or ESP followed by UV ozone system to achieve the same level of control as 1. 4. Fine filtration or ESP followed by wet scrubbing to achieve the same level of control as 1. Maintenance must be carried out to ensure these performance levels are maintained. Thereafter, the equipment shall be properly maintained and operated within design specifications during normal working hours. Reason: Insufficient information has been supplied with the application to judge the technical specifications of the extract ventilation system. Submission of this detail prior to commencement of the use will protect the amenity of occupiers of nearby premises and ensure that the development accords with Development Control Policies Development Plan Document Policy DC61
9.Prior to the commencement of the development hereby approved a full and detailed application for the Secured by Design award scheme shall be submitted to the Local Planning Authority, setting out how the principles and practices of the Secured by Design Scheme are to be incorporated. Once approved in writing by the Local Planning Authority in consultation with the Metropolitan Police Designing Out Crime Officers (DOCOs), the development shall be carried out in accordance with the agreed details. Reason: Insufficient information has been supplied with the application to judge whether the proposals meet Secured by Design standards. Submission of a full and detailed application prior to commencement is in the interest of creating safer, sustainable communities and to reflect guidance in Policies CP17 and DC63 of the Core Strategy and Development Control Policies Development Plan Document and the NPPF.
10.All building operations in connection with the construction of external walls, roof, and foundations; site excavation or other external site works; works involving the use of plant or machinery; the erection of scaffolding; the delivery of materials; the removal of materials and spoil from the site, and the playing of amplified music shall only take place between the hours of 8.00am and 6.00pm Monday to Friday, and between 8.00am and 1.00pm on Saturdays and not at all on Sundays and Bank Holidays/Public Holidays. Reason:- To protect residential amenity, and in order that the development accords with the Development Control Policies Development Plan Document Policy DC61.
11.Before development is commenced, a scheme shall be submitted to and approved in writing by the Local Planning Authority making provision for a Construction Method Statement to control the adverse impact of the development on the amenity of the public and nearby occupiers. The Construction Method statement shall include details of: a) parking of vehicles of site personnel and visitors; b) storage of plant and materials; c) dust management controls; d) measures for minimising the impact of noise and ,if appropriate, vibration arising from construction activities; e) predicted noise and, if appropriate, vibration levels for construction using methodologies and at points agreed with the Local Planning Authority; f) scheme for monitoring noise and if appropriate, vibration levels using methodologies and at points agreed with the Local Planning Authorities; g) siting and design of temporary buildings; h) scheme for security fencing/hoardings, depicting a readily visible 24-hour contact number for queries or emergencies; i) details of disposal of waste arising from the construction programme, including final disposal points. The burning of waste on the site at any time is specifically precluded. And the development shall be carried out in accordance with the approved scheme and statement. Reason:- Insufficient information has been supplied with the application in relation to the proposed construction methodology. Submission of details prior to commencement will ensure that the method of construction protects residential amenity. It will also ensure that the development accords the Development Control Policies Development Plan Document Policy DC61.
12.(1) Prior to the commencement of any works or occupation of the site, pursuant to this permission, the developer shall submit for the written approval of the Local Planning Authority; a) A Phase I (Desktop Study) Report documenting the history of the site, its surrounding area and the likelihood of contaminant/s, their type and extent incorporating a Site Conceptual Model. b) A Phase II (Site Investigation) Report if the Phase I Report confirms the possibility of a significant risk to any sensitive receptors. This is an intrusive site investigation including factors such as chemical testing, quantitative risk assessment and a description of the sites ground conditions. An updated Site Conceptual Model should be included showing all the potential pollutant linkages and an assessment of risk to identified receptors. c) A Phase III (Remediation Scheme) Report if the Phase II Report confirms the presence of a significant pollutant linkage requiring remediation. A detailed remediation scheme to bring the site to a condition suitable for the intended use by removing unacceptable risks to all receptors must be prepared, and is subject to the approval in writing of the Local Planning Authority. The scheme must include all works to be undertaken, proposed remediation objectives and remediation criteria, timetable of works, site management procedures and procedure for dealing with previously unidentified any contamination. The scheme must ensure that the site will not qualify as contaminated land under Part 2A of the Environmental Protection Act 1990 in relation to the intended use of the land after remediation. d) Following completion of measures identified in the approved remediation scheme mentioned in 1(c) above, a "Verification Report" that demonstrates the effectiveness of the remediation carried out, any requirement for longer-term monitoring of contaminant linkages, maintenance and arrangements for contingency action, must be produced, and is subject to the approval in writing of the Local Planning Authority. Reason: Insufficient information has been supplied with the application to judge the risk arising from contamination. Submission of an assessment prior to commencement will ensure the safety of the occupants of the development hereby permitted and the public generally. It will also ensure that the development accords with Development Control Policies Development Plan Document Policies DC54 and DC61
13.(2) a) If, during development, contamination not previously identified is found to be present at the site then no further development (unless otherwise agreed in writing with the local planning authority) shall be carried out until a remediation strategy detailing how this unsuspected contamination shall be dealt with has been submitted to and approved in writing by the local planning authority. The remediation strategy shall be implemented as approved. b) Following completion of the remediation works as mentioned in (a) above, a 'Verification Report' must be submitted demonstrating that the works have been carried out satisfactorily and remediation targets have been achieved. Reason: To ensure that any previously unidentified contamination found at the site is investigated and satisfactorily addressed in order to protect those engaged in construction and occupation of the development from potential contamination.
14.No development shall take place until a scheme for external lighting has been submitted to and approved in writing by the Local Planning Authority. The scheme of lighting shall include the low level lighting of the access road. The approved details shall be implemented in full prior commencement of the hereby approved development and permanently maintained in accordance with the approved details. Reason: Insufficient information has been supplied with the application to judge the impact arising from any external lighting required in connection with the building or use. Submission of this detail prior to occupation in the case of new building works or prior to the use commencing in the case of changes of use will protect residential amenity and ensure that the development accords with the Development Control Policies Development Plan Document Policy DC61
15.No development shall take place until a scheme of vehicle cleansing has been submitted to and approved in writing by the Local Planning Authority. The development shall thereafter be undertaken in accordance with the approved details, which shall be retained for the life of the development. The submitted scheme will provide the following details: a) A plan showing where vehicles will be parked within the site, to be inspected for mud and debris and cleaned if required. The plan should show where construction traffic will access and exit the site from the public highway. b) A description of how the parking area will be surfaced, drained and cleaned to prevent mud, debris and muddy water being tracked onto the public highway. c) A description of how vehicles will be checked before leaving the site, including their wheels, the underside of vehicles, mud flaps and wheel arches. d) A description of how vehicles will be cleaned. e) A description of how dirty/muddy water be dealt with after being washed off the vehicles. f) A description of any contingency plan to be used in the event of a break-down of the wheel washing arrangements. g) A description of how any material tracked into the public highway will be removed. Should material be deposited in the public highway, then all operations at the site shall cease until such time as the material has been removed in accordance with the approved details. Reason:- Insufficient information has been supplied with the application in relation to wheel washing facilities. Submission of details prior to commencement will ensure that the facilities provided prevent materials from the site being deposited on the adjoining public highway, in the interests of highway safety and the amenity of the surrounding area. It will also ensure that the development accords with the Development Control Policies Development Plan Document Policies DC32 and DC61.
16.The necessary agreement, notice or licence to enable the proposed alterations to the Public Highway shall be entered into and completed prior to the commencement of the development. Reason: To ensure the interests of the travelling public are maintained and comply with policies of the Core Strategy and Development Control Policies, namely CP10, CP17 and DC61.
17.The A1/A2/A3 units and cafe hereby permitted shall not be used for the purposes hereby permitted other than between the hours of 08:00 and 24:00 on any day without the prior consent in writing of the Local Planning Authority. Reason: To enable the Local Planning Authority to retain control in the Interests of amenity, and in order that the development accords with the LDF Development Control Policies Development Plan Document Policy DC61.
18.No deliveries or servicing of the non-residential elements of the development shall take place other than between the hours of 06:00 and 22:00 any day without the prior consent in writing of the Local Planning Authority. Reason: To enable the Local Planning Authority to retain control in the interests of amenity, and in order that the development accords with the LDF Development Control Policies Development Plan Document Policy DC61.
19.Prior to commencement of the development hereby approved a delivery and servicing plan (DSP) shall be submitted to and agreed in writing by the Local Planning Authority. The DSP shall include details of the servicing arrangements including the exact location, times and frequency of deliveries and collections, vehicle movements, silent reversing methods and quiet loading/unloading measures. The development shall thereafter be operated strictly in accordance with the agreed details unless otherwise agreed in writing by the Local Planning Authority. Reason: Insufficient information has been provided in relation to delivery and servicing arrangements. Submission of details prior to commencement will ensured that the development does not adversely affect neighbouring amenity or the functioning of the highway and that the development can be adequately serviced, in order that the development accords with the LDF Development Control Policies Development Plan Document Policies DC32 and DC36.
20.Before the commercial use commences, the walls and ceiling of the ground floor of the building shall be insulated in accordance with a scheme which shall previously have been approved by the Local Planning Authority in order to secure a reduction in the level of noise emanating from it and it shall be effectively sealed to prevent the passage of odours through the structure of the building to other premises and dwellings. Reason: Insufficient information has been supplied with the application to judge the impact of noise emanting from the development and the subsequent impact on other premises and dwellings. Submission of an insulation details prior to commencement will protect future residents against the impacts from noise and odour nuissance in accordance with Development Control Policies Development Plan Document Policies DC55 and DC61.
21.Before any works commence, a scheme for any new plant or machinery shall be submitted to the Local Planning Authority to achieve the following standard. Noise levels expressed as the equivalent continuous sound level LAeq (1 hour) when calculated at the boundary with the nearest noise sensitive premises shall not exceed LA90 - 10dB and shall be maintained thereafter to the satisfaction of the Local Planning Authority. Reason: Insufficient information has been supplied with the application to assess the noise levels of the plant or machinery to be used on site. Submission of this detail prior to the use commencing in the case of changes of use, will prevent noise nuisance to adjoining properties in accordance with the Development Control Policies Development Plan Document Policies DC55 and DC61.
22.The building(s) shall be so constructed as to provide sound insulation of 45 DnT, w + Ctr dB (minimum values) against airborne noise and 62 L'nT, w dB (maximum values) against impact noise to the satisfaction of the Local Planning Authority. Reason: To prevent noise nuisance to adjoining properties.
23.Before any development is commenced, a scheme for protecting the proposed dwellings from noise amplified music and raised voices from existing music venues in South Street (including 72-74 South Street, 87-89 South Street and 105-111 South Street) shall be submitted to and approved by the Local Planning Authority. Any works which form part of the scheme shall be completed before any of the permitted dwellings are occupied. Reason: Insufficient information has been supplied with the application to judge the appropriateness of the noise insulation measures to be employed. Submission of the information prior to commencement will prevent noise nuisance to the development from noise amplified music and raised voices in accordance with Development Control Policies Development Plan Document Policies DC55 and DC61.
24.Before the uses commence, a scheme to control the transmission of noise and vibration from any mechanical ventilation system installed shall be submitted to and approved in writing by the Local Planning Authority and implemented prior to the permitted use commencing. Thereafter, the equipment shall be properly maintained and operated during normal working hours. Reason: Insufficient information has been supplied with the application to judge the technical specifications of the mechanical ventilation system. Submission of this detail prior to occupation in the case of new building works or prior to the use commencing in the case of changes of use protect the amenity of occupiers of nearby premises, and in order that the development accords with Development Control Policies Development Plan Document Policy DC61.
25.No piling shall take place until a piling method statement (detailing the depth and type of piling to be undertaken and the methodology by which such piling will be carried out, including measures to prevent and minimise the potential for damage to subsurface sewerage infrastructure, and the programme for the works) has been submitted to and approved in writing by the Local Planning Authority in consultation with Thames Water. Any piling must be undertaken in accordance with the terms of the approved piling method statement. Reason: Insufficient information has been provided regarding the proposed piling works.The proposed works will be in close proximity to underground sewerage utility infrastructure and submission of the information prior to commencement will mitigate the potential impact on local underground sewerage utility infrastructure. The applicant is advised to contact Thames Water Developer Services on 0845 850 2777 to discuss the details of the piling method statement.
26.Before any of the development hereby permitted is commenced; a methodology for the proposed repair and restoration works to the front of the building shall be submitted to and approved in writing by the Local Planning Authority and thereafter the development shall be constructed in accordance with the approved methodology. The repair and restoration works approved shall be carried out prior to the first occupation of the new residential units. Reason: Insufficient information has been supplied with the application to judge the appropriateness of the method of the proposed repair and restoration works. Submission of a detailed methodology prior to the commencement of the works will ensure that the development preserves the character and appearance of the locally listed buildingmethod and its setting and complies with Policies DC61 and DC67 of the Development Control Policies Development Plan Document and the Heritage Supplementary Planning Document.
27.Statement Required by Article 31 (cc) of the Town and Country Planning (Development Management) Order 2010: Improvements required to make the proposal acceptable were negotiated and submitted, in accordance with para 186-187 of the National Planning Policy Framework 2012.
28.The proposal is liable for the Mayor of London Community Infrastructure Levy (CIL). Based upon the information supplied with the application, the CIL payable would be £22,620 (subject to indexation). CIL is payable within 60 days of commencement of development. A Liability Notice will be sent to the applicant (or anyone else who has assumed liability) shortly and you are required to notify the Council of the commencement of the development before works begin. Further details with regard to CIL are available from the Council's website.
29.A fee is required when submitting details pursuant to the discharge of conditions. In order to comply with the Town and Country Planning (Fees for Applications, Deemed Applications, Requests and Site Visits) (England) Regulations 2012, which came into force from 22.11.2012, a fee of £97 per request or £28 where the related permission was for extending or altering a dwellinghouse, is needed.
30.In promoting the delivery of safer, stronger, sustainable places the Local Planning Authority fully supports the adoption of the principles and practices of the Secured by Design Award Scheme and Designing against Crime. Your attention is drawn to the free professional service provided by the Metropolitan Police Designing Out Crime Officers for North East London, whose can be contacted via DOCOMailbox.NE@met.police.uk or 0208 217 3813 . They are able to provide qualified advice on incorporating crime prevention measures into new developments.
31.The Applicant is advised that planning approval does not constitute approval for changes to the public highway. Highway Authority approval will only be given after suitable details have been submitted, considered and agreed. Any proposals which involve building over the public highway as managed by the London Borough of Havering, will require a licence and the applicant must contact StreetCare, Traffic & Engineering on 01708 433750 to commence the Submission/ Licence Approval process. Should this application be granted planning permission, the developer, their representatives and contractors are advised that this does not discharge the requirements under the New Roads and Street Works Act 1991 and the Traffic Management Act 2004. Formal notifications and approval will be needed for any highway works (including temporary works) required during the construction of the development. The developer is advised that if construction materials are proposed to be kept on the highway during construction works then they will need to apply for a license from the Council.
32.With regards to surface water drainage it is the responsibility of the developer to make proper provision for drainage to ground, water courses or a suitable sewer. In respect of surface water it is recommended that the applicant should ensure that storm flows are attenuated or regulated into the receiving public network through on or off site storage. When it is proposed to connect to a combined public sewer, the site drainage should be separate and combined at the final manhole nearest the boundary. Connections are not permitted for the removal of Ground Water. Where the developer proposes to discharge to a public sewer, prior approval from Thames Water Developer Services will be required. They can be contacted on 0845 850 2777.
33.The applicant is advised to have regard to the following guidance provided in: · The Food Industry Guides to Good Hygiene Practice: · Workplace, Health, Safety and; Welfare Approved Code of Practice L24 ISBN 0-7176-0413-6 available to order from book shops. · Further information is available at the following web sites: · Food safety - www.food.gov.uk/foodindustry/ · Occupational safety & health - www.hse.gov.uk Applicants have found it beneficial to consider the items below before final detailed plans are produced 1. provision of suitable outside bin storage 2. provision of a grease trap on the foul drainage 3. proper storage and disposal of waste oil 4. vehicle and pedestrian routes when loading and unloading 5. vehicle and pedestrian routes for customers Finally, food premises must be registered with the Environmental Health Department at least 28 days before opening. It is an offence for premises to trade without registration. A registration form is available from our office or at our website: online.havering.gov.uk/officeforms/licence_food_business.ofml.
34.The planning obligations recommended in this report have been subject to the statutory tests set out in Regulation 122 of the Community Infrastructure Levy Regulations 2010 and the obligations are considered to have satisfied the following criteria:- (a) Necessary to make the development acceptable in planning terms; (b) Directly related to the development; and (c) Fairly and reasonably related in scale and kind to the development.