1.The development hereby permitted shall begin no later than three years from the date of this decision. Reason:- To comply with the requirements of Section 91 of the Town and Country Planning Act 1990.
2.The development hereby permitted shall not be carried out otherwise than in complete accordance with the approved plans (as set out on page one of this decision notice). Reason:- For the avoidance of doubt and to ensure that the development is carried out as approved.
3.Before the development hereby approved is occupied, the materials used on the external surfaces of the development must match those used on the external surfaces of the existing property. This applies unless differences are shown on the drawings hereby approved or are required by other conditions on this permission. Reason: To ensure the development is carried out in accordance with the consent sought, has an acceptable design and complies with Policy 26 of the Havering Local Plan (2021).
4.Notwithstanding the provisions of the Town and Country Planning (General Permitted Development) (England) Order 2015, nor any Statutory Instrument which amends, removes or replaces that Order, no window or other opening (other than those shown on the submitted and approved plans) shall be formed in the flank walls of the development hereby permitted without the receipt of a specific planning permission for it from the Local Planning Authority. Reason: To protect against the amenities of neighbouring occupiers and ensure the development complies with Policy 7 of the Havering Local Plan (2021).
5.The hard surface hereby approved (including any sub-base) shall be made of porous materials or provision shall be made to direct run-off water from the hard surface to a permeable or porous area or surface within the curtilage of the dwellinghouse. Reason:- In order to ensure no water run-off from the hard surface which would contribute to risk of flooding
6.The Local Planning Authority has acted positively and proactively in determining this application by assessing the proposal against all material planning considerations, including planning policies and any representations which were received. It subsequently determined to grant planning permission in accordance with the National Planning Policy requirement that applications for sustainable development are approved where possible. A detailed analysis of the scheme is set out in the report on the application prepared by officers.