1.The development to which this permission relates must be commenced not later than three years from the date of this permission. Reason:- To comply with the requirements of Section 91 of the Town and Country Planning Act 1990 (as amended by Section 51 of the Planning and Compulsory Purchase Act 2004).
2.The development hereby permitted shall not be carried out otherwise than in complete accordance with the approved plans (as set out on page one of this decision notice). Reason:- The Local Planning Authority consider it essential that the whole of the development is carried out and that no departure whatsoever is made from the details approved, since the development would not necessarily be acceptable if partly carried out or carried out differently in any degree from the details submitted. Also, in order that the development accords with Development Control Policies Development Plan Document Policy DC61.
3.No works shall take place in relation to any of the development hereby approved until samples of all materials to be used in the external construction of the building(s) are submitted to and approved in writing by the Local Planning Authority and thereafter the development shall be constructed with the approved materials. Reason:- Insufficient information has been supplied with the application to judge the appropriateness of the materials to be used. Submission of samples prior to commencement will ensure that the appearance of the proposed development will harmonise with the character of the surrounding area and comply with Policy DC61 of the Development Control Policies Development Plan Document.
4.Before the building hereby permitted is first occupied or the ground floor use commenced, the area set aside for car parking, as indicated on drawing no.KS1509511/03, shall be laid out and surfaced to the satisfaction of the Local Planning Authority and retained permanently thereafter for the accommodation of vehicles visiting the site and shall not be used for any other purpose. Reason:- To ensure that car parking accommodation is made permanently available to the standards adopted by the Local Planning Authority in the interest of highway safety, and that the development accords with the Development Control Policies Development Plan Document Policy DC33.
5.No works shall take place in relation to any of the development hereby approved until there has been submitted to and approved by the Local Planning Authority a scheme of hard and soft landscaping, which shall include hedging to screen the new front parking area and create a buffer with the adjoining residential occupier, as well as provide an indication of all existing trees and shrubs on the site, and details of any to be retained, together with measures for the protection in the course of development. All planting, seeding or turfing comprised within the scheme shall be carried out in the first planting season following completion of the development and any trees or plants which within a period of 5 years from completion of the development die, are removed or become seriously damaged or diseased shall be replaced in the next planting season with others of a similar size and species, unless otherwise agreed in writing by the local Planning Authority. Reason:- Insufficient information has been supplied with the application to judge the appropriateness of the hard and soft landscaping proposed. Submission of a scheme prior to commencement will ensure that the development accords with the Development Control Policies Development Plan Document Policy DC61. It will also ensure accordance with Section 197 of the Town and Country Planning Act 1990.
6.The proposals should provide a 2.1 by 2.1 metre pedestrian visibility splay on either side of the proposed access, set back to the boundary of the public footway. There should be no obstruction or object higher than 0.6 metres within the visibility splay. Reason:- In the interests of highway safety, and in order that the development accords with the Development Control Policies Development Plan Document Policy DC32.
7.Prior to the commencement of the development hereby approved, details of all proposed walls, fences and boundary treatment shall be submitted to, and approved in writing by, the Local Planning Authority. The boundary development shall then be carried out in accordance with the approved details and retained permanently thereafter to the satisfaction of the Local Planning Authority. Reason: Insufficient information has been supplied with the application to judge the appropriateness of any boundary treatment. Submission of this detail prior to commencement will protect the visual amenities of the development, prevent undue overlooking of adjoining property and ensure that the development accords with the Development Control Policies Development Plan Document Policy DC61.
8.No works shall take place in relation to any of the development hereby approved until a scheme for protecting the proposed dwelling from noise from external sources is submitted to and approved by the Local Planning Authority. Any works which form part of the scheme shall be completed before any of the permitted dwelling is occupied. Reason:- Insufficient information has been supplied with the application to judge the appropriateness of the noise insulation measures to be employed. Submission of the information prior to commencement will prevent noise nuisance to the development from external sources in accordance with Development Control Policies Development Plan Document Policies DC55 and DC61.
9.No building shall be occupied or use commenced until a scheme for the new plant or machinery is submitted to and approved in writing by the Local Planning Authority to achieve the following standard - Noise levels expressed as the equivalent continuous sound level LAeq (1 hour) when calculated at the boundary with the nearest noise sensitive property shall not exceed LA90 -10dB. Plant and machinery shall be maintained thereafter in accordance with the approved scheme. Reason:- Insufficient information has been supplied with the application to assess the noise levels of the plant or machinery to be used on site. Submission of this detail prior to occupation in the case of new building works or prior to the use commencing in the case of changes of use, will prevent noise nuisance to adjoining properties in accordance with the Development Control Policies Development Plan Document Policies DC55 and DC61.
10.The building shall be so constructed as to provide sound insulation of 43 DnT,w + Ctr dB (minimum values) against airborne noise and 64 L'nT,w dB (maximum values) against impact noise to the satisfaction of the Local Planning Authority. Reasons:- To prevent noise nuisance to adjoining properties in accordance with the Development Control Policies Development Plan Document Policies DC55 and DC61.
11.No works shall take place in relation to any of the development hereby approved until a Construction Method Statement to control the adverse impact of the development on the amenity of the public and nearby occupiers is submitted to and approved in writing by the Local Planning Authority. The Construction Method statement shall include details of: a) parking of vehicles of site personnel and visitors; b) storage of plant and materials; c) dust management controls; d) measures for minimising the impact of noise and ,if appropriate, vibration arising from construction activities; e) predicted noise and, if appropriate, vibration levels for construction using methodologies and at points agreed with the Local Planning Authority; f) scheme for monitoring noise and if appropriate, vibration levels using methodologies and at points agreed with the Local Planning Authorities; g) siting and design of temporary buildings; h) scheme for security fencing/hoardings, depicting a readily visible 24-hour contact number for queries or emergencies; i) details of disposal of waste arising from the construction programme, including final disposal points. The burning of waste on the site at any time is specifically precluded. And the development shall be carried out in accordance with the approved scheme and statement. Reason:- Insufficient information has been supplied with the application in relation to the proposed construction methodology. Submission of details prior to commencement will ensure that the method of construction protects residential amenity. It will also ensure that the development accords the Development Control Policies Development Plan Document Policy DC61.
12.All building operations in connection with the construction of external walls, roof, and foundations; site excavation or other external site works; works involving the use of plant or machinery; the erection of scaffolding; the delivery of materials; the removal of materials and spoil from the site, and the playing of amplified music shall only take place between the hours of 8.00am and 6.00pm Monday to Friday, and between 8.00am and 1.00pm on Saturdays and not at all on Sundays and Bank Holidays/Public Holidays. Reason:- To protect residential amenity, and in order that the development accords with the Development Control Policies Development Plan Document Policy DC61.
13.Notwithstanding the provisions of the Town and Country Planning (Use Classes) Order 1987 (as amended) the use hereby permitted shall be as a physiotherapy practice only and shall be used for no other purpose(s) whatsoever including any other use in Class D1 of the Order, unless otherwise agreed in writing by the Local Planning Authority. Reason:- To restrict the use of the premises to one compatible with the surrounding area and to enable the Local Planning Authority to exercise control over any future use not forming part of this application, and that the development accords with the Development Control Policies Development Plan Document Policy DC61
14.The ground floor premises shall not be used for the purposes hereby permitted other than between the hours of 08:30 to 20:00 on Monday to Friday, 08:30 to 17:00 on Saturday and not at all on Sundays and Bank or Public holidays without the prior consent in writing of the Local Planning Authority. Reason:- To enable the Local Planning Authority to retain control in the interests of amenity, and in order that the development accords with Development Control Policies Development Plan Document Policy DC61.
15.No building shall be occupied or use commenced until refuse and recycling facilities are provided in accordance with details which shall previously have been submitted to and approved in writing by the Local Planning Authority. The refuse and recycling facilities shall be permanently retained thereafter. Reason:- Insufficient information has been supplied with the application to judge how refuse and recycling will be managed on site. Submission of this detail prior to occupation in the case of new building works or prior to the use commencing in the case of changes of use will protect the amenity of occupiers of the development and also the locality generally and ensure that the development accords with the Development Control Policies Development Plan Document Policy DC61.
16.No building shall be occupied or use commenced until cycle storage is provided in accordance with details previously submitted to and approved in writing by the Local Planning Authority. The cycle storage shall be permanently retained thereafter. Reason:- Insufficient information has been supplied with the application to demonstrate what facilities will be available for cycle parking. Submission of this detail prior to occupation in the case of new building works or prior to the use commencing in the case of changes of use is in the interests of providing a wide range of facilities for non-motor car residents and sustainability.
17.The proposed windows, as annotated and shown on drawing no. KS1509511/05 Revision A shall be permanently glazed with obscure glass not less than level 3 of obscurity on the standard scale of obscurity and shall thereafter be maintained. Reason:- In the interests of privacy, and in order that the development accords with the Development Control Policies Development Plan Document Policy DC61.
18.Statement Required by Article 35 (2) of the Town and Country Planning (Development Management Procedure) (England) Order 2015: During consideration by the committee, members placed different weight on the planning merits and decided to approve planning permission.
19.The proposal is liable for the Mayor of London Community Infrastructure Levy (CIL). Based upon the information supplied with the application, the CIL payable would be £5,200.00 (this figure may go up or down, subject to indexation). CIL is payable within 60 days of commencement of development. A Liability Notice will be sent to the applicant (or anyone else who has assumed liability) shortly and you are required to notify the Council of the commencement of the development before works begin. Further details with regard to CIL are available from the Council's website.
20.The Applicant is advised that planning approval does not constitute approval for changes to the public highway. Highway Authority approval will only be given after suitable details have been submitted, considered and agreed. Any proposals which involve building over the public highway as managed by the London Borough of Havering, will require a licence and the applicant must contact StreetCare, Traffic & Engineering on 01708 433750 to commence the Submission/ Licence Approval process. Should this application be granted planning permission, the developer, their representatives and contractors are advised that this does not discharge the requirements under the New Roads and Street Works Act 1991 and the Traffic Management Act 2004. Formal notifications and approval will be needed for any highway works (including temporary works) required during the construction of the development. The developer is advised that if construction materials are proposed to be kept on the highway during construction works then they will need to apply for a license from the Council.
21.The planning obligations recommended in this report have been subject to the statutory tests set out in Regulation 122 of the Community Infrastructure Levy Regulations 2010 and the obligations are considered to have satisfied the following criteria:- (a) Necessary to make the development acceptable in planning terms; (b) Directly related to the development; and (c) Fairly and reasonably related in scale and kind to the development.