| No. | Condition Text |
|---|
| 1. | The development hereby permitted shall begin no later than three years from the date of this decision.
Reason:
To comply with the requirements of Section 91 of the Town and Country Planning Act 1990. |
| 2. | The development hereby permitted shall not be carried out otherwise than in complete accordance with the following approved plans:
ZAAVIA/133LA/102 B
ZAAVIA/133LA/104 A
ZAAVIA/133LA/105 A
ZAAVIA/133LA/107 A
Reason:
For the avoidance of doubt and to ensure that the development is carried out as approved and is compliant with development plan policy. |
| 3. | Before the development hereby approved is occupied, the materials used on the external surfaces of the development must match those used on the external surfaces of the existing property. This applies unless differences are shown on the drawings hereby approved or are required by other conditions on this permission.
Reason
To ensure the development is carried out in accordance with the consent sought, has an acceptable design and complies with policy 26 of the Havering Local Plan (2021) |
| 4. | Notwithstanding the provisions of the Town and Country Planning (General Permitted Development) (England) Order 2015, nor any Statutory Instrument which amends, removes or replaces that Order, no window or other opening (other than those shown on the submitted and approved plans) shall be formed in the flank walls of the development hereby permitted without the receipt of a specific planning permission for it from the London Planning Authority.
Reason:To protect the amenities of neighbouring occupiers and ensure the development complies with policy 7 of the Havering Local Plan (2021) |
| 5. | a) Prior to the commencement of any groundworks or development of the site, details shall be submitted to and agreed in writing by the Local Planning Authority setting out suitable gas protection measures to be employed on site including, but not necessarily limited to, the installation of a suitable gas resistant membrane, in compliance with BS 8485:2015 and A1:2019. The gas protection measures shall be carried out in strict accordance with the agreed details.
b) Upon completion of installation, a 'Verification Report' must be submitted demonstrating that the works have been carried out.
Reason:-
Insufficient information has been supplied with the application to judge the risk arising from landfill gases (methane and carbon dioxide). Submission of an assessment prior to commencement will protect people on or close to the site from the risks associated with migrating landfill gas. |
| 6. | [U]Positive and Proactive Statement[]
The Local Planning Authority has acted positively and proactively in determining this application by assessing the proposal against all material planning considerations, including planning policies and any representations which were received. It subsequently determined to grant planning permission in accordance with the National Planning Policy requirement that applications for sustainable development are approved where possible. A detailed analysis of the scheme is set out in the report on the application prepared by officers. |
| 7. | ]Building Regulations
You are reminded that this decision notice only addresses requirements under Planning Legislation. You also need to check that whether or not the development requires consent under the Building Regulations, as this is an entirely separate process. Further information on the requirements of the Building Regulations can be found at: https://www.havering.gov.uk/building control. |
| 8. | ]Party Wall Act[
You are reminded that this decision notice only addresses requirements under Planning Legislation. You also need to check whether or not the development necessitates an agreement under the requirements of the Party Wall etc. Act 1996, as this is an entirely separate process. Further guidance on the Party Wall etc. Act 1996 can be found at: https;//www.gov.uk/housing-local-and-community/party-walls. |