No.Condition Text
1.Details of the appearance, landscaping, layout, and scale, (hereinafter called "the reserved matters") shall be submitted to and approved in writing by the local planning authority before any development begins and the development shall be carried out as approved. Reason:- This is outline permission only and these matters have been reserved for the subsequent approval of the Local Planning Authority.
2.No works shall take place in relation to any of the development hereby approved until there has been submitted to and approved by the Local Planning Authority a scheme of hard and soft landscaping, which shall include indications of all existing trees and shrubs on the site, and details of any to be retained, together with measures for the protection in the course of development. All planting, seeding or turfing comprised within the scheme shall be carried out in the first planting season following completion of the development and any trees or plants which within a period of 5 years from completion of the development die, are removed or become seriously damaged or diseased shall be replaced in the next planting season with others of a similar size and species, unless otherwise agreed in writing by the local Planning Authority. Reason:- Insufficient information has been supplied with the application to judge the appropriateness of the hard and soft landscaping proposed. Submission of a scheme prior to commencement will ensure that the development accords with the Development Control Policies Development Plan Document Policy DC61. It will also ensure accordance with Section 197 of the Town and Country Planning Act 1990.
3.Prior to the commencement of the development hereby approved, details of all proposed walls, fences and boundary treatment shall be submitted to, and approved in writing by, the Local Planning Authority. The boundary development shall then be carried out in accordance with the approved details and retained permanently thereafter to the satisfaction of the Local Planning Authority. Reason: Insufficient information has been supplied with the application to judge the appropriateness of any boundary treatment. Submission of this detail prior to commencement will protect the visual amenities of the development, prevent undue overlooking of adjoining property and ensure that the development accords with the Development Control Policies Development Plan Document Policy DC61.
4.Notwithstanding the provisions of the Town and Country Planning (General Permitted Development) (England) Order 2015, no window or other opening (other than those shown on the submitted and approved plan,) shall be formed in the flank wall(s) of the building(s) hereby permitted, unless specific permission under the provisions of the Town and Country Planning Act 1990 has first been sought and obtained in writing from the Local Planning Authority. Reason:- In order to ensure a satisfactory development that will not result in any loss of privacy or damage to the environment of neighbouring properties which exist or may be proposed in the future, and in order that the development accords with Development Control Policies Development Plan Document Policy DC61.
5.Application/s for approval of the reserved matters shall be submitted to the Local Planning Authority within three years from the date of this permission. Reason:- To comply with Section 92 of the Town and Country Planning Act 1990 (as amended by Section 51 of the Planning and Compulsory Purchase Act 2004).
6.The development to which this permission relates must be begun not later than the expiration of two years from the final approval of the reserved matters or, in the case of approval on different dates, the final approval of the last reserved matter to be approved. Reason:- To comply with Section 92 of the Town and Country Planning Act 1990 (as amended by Section 51 of the Planning and Compulsory Purchase Act 2004).
7.No works shall take place in relation to any of the development hereby approved until samples of all materials to be used in the external construction of the building(s) are submitted to and approved in writing by the Local Planning Authority and thereafter the development shall be constructed with the approved materials. Reason:- Insufficient information has been supplied with the application to judge the appropriateness of the materials to be used. Submission of samples prior to commencement will ensure that the appearance of the proposed development will harmonise with the character of the surrounding area and comply with Policy DC61 of the Development Control Policies Development Plan Document.
8.No works shall take place in relation to any of the development hereby approved until full details of doors and windows and samples of all materials including rainwater goods to be used in the construction of the extension(s) hereby permitted are submitted to and approved in writing by the Local Planning Authority and thereafter the development shall be constructed with the approved materials. Reason:- Insufficient information has been supplied with the application to judge the appropriateness of the doors, windows, materials and rainwater goods to be used. Submission of samples prior to commencement will safeguard the appearance of the building and the character of the immediate area, and will ensure that the development accords with the Development Control Policies Development Plan Document Policy DC61
9.The development hereby permitted shall not be carried out otherwise than in complete accordance with the approved plans (as set out on page one of this decision notice). Reason:- The Local Planning Authority consider it essential that the whole of the development is carried out and that no departure whatsoever is made from the details approved, since the development would not necessarily be acceptable if partly carried out or carried out differently in any degree from the details submitted. Also, in order that the development accords with Development Control Policies Development Plan Document Policy DC61.
10.Before the development hereby permitted commences details of a scheme shall be submitted to and approved in writing by the local planning authority which specifies the provisions to be made for the control of noise effecting the site. Such scheme as may be approved shall be implemented prior to first occupation and thereafter retained in accordance with such details. Reason:- To protect the amenity of future residents.
11.Changes to the public highway (including permanent or temporary access) - Planning approval does not constitute approval for changes to the public highway. Highway Authority approval will only be given after suitable details have been submitted considered and agreed. If new or amended access is required (whether temporary or permanent), there may be a requirement for the diversion or protection of third party utility plant or highway authority assets and it is recommended that early involvement with the relevant statutory undertaker takes place. The applicant must contact Engineering Services on 01708 433751 to discuss the scheme and commence the relevant highway approvals process. Please note that unauthorised work on the highway is an offence. Highway legislation - The developer (including their representatives and contractors) is advised that planning consent does not discharge the requirements of the New Roads and Street Works Act 1991 and the Traffic Management Act 2004. Formal notifications and approval will be needed for any highway works (including temporary works of any nature) required during the construction of the development. Please note that unauthorised work on the highway is an offence. Temporary use of the public highway - The developer is advised that if construction materials are proposed to be kept on the highway during construction works then they will need to apply for a licence from the Council. If the developer required scaffolding, hoarding or mobile cranes to be used on the highway, a licence is required and Street Management should be contacted to make the necessary arrangements. Please note that unauthorised use of the highway for construction works is an offence. Surface water management - The developer is advised that surface water from the development in both its temporary and permanent states should not be discharged onto the highway. Failure to prevent such is an offence.
12.No works shall take place in relation to any of the development hereby approved until a scheme for protecting the proposed dwelling(s) from external noise from is submitted to and approved by the Local Planning Authority. Any works which form part of the scheme shall be completed before any of the permitted dwelling(s) is occupied. Reason:- Insufficient information has been supplied with the application to judge the appropriateness of the noise insulation measures to be employed. Submission of the information prior to commencement will prevent noise nuisance to the development from external noise sources in accordance with Development Control Policies Development Plan Document Policies DC55 and DC61.
13.No works shall take place in relation to any of the development hereby approved until an assessment of the impact of: a) railway noise (in accordance with Technical memorandum, "Calculation of Railway Noise", 1995) and; b) vibration from the use of the railway lines upon the site; is undertaken and a scheme detailing the measures to protect future residents from railway noise and vibration is submitted to and approved in writing by the Local Planning Authority. The approved scheme shall be implemented prior to occupancy taking place. Reason:- Insufficient information has been supplied with the application to judge the impact of transportation noise and vibration upon the proposed development. Submission of an assessment prior to commencement will protect future residents against the impact of transportation noise and vibration, in accordance with Development Control Policies Development Plan Document Policies DC55 and DC61.
14.Before the development hereby permitted is first commenced, vehicle cleansing facilities to prevent mud being deposited onto the public highway during construction works shall be provided on site in accordance with details to be first submitted to and approved in writing by the Local Planning Authority. The approved facilities shall be retained thereafter and used at relevant entrances to the site throughout the duration of construction works. If mud or other debris originating from the site is deposited in the public highway, all on-site operations shall cease until it has been removed. The submission will provide; a) A plan showing where vehicles will be parked within the site to be inspected for mud and debris and cleaned if required. The plan should show where construction traffic will access and exit the site from the public highway. b) A description of how the parking area will be surfaced, drained and cleaned to prevent mud, debris and muddy water being tracked onto the public highway; c) A description of how vehicles will be checked before leaving the site - this applies to the vehicle wheels, the underside of vehicles, mud flaps and wheel arches. d) A description of how vehicles will be cleaned. e) A description of how dirty/ muddy water be dealt with after being washing off the vehicles. f) A description of any contingency plan to be used in the event of a break-down of the wheel washing arrangements. Reason:- Insufficient information has been supplied with the application in relation to wheel washing facilities. Submission of details prior to commencement will ensure that the facilities provided prevent materials from the site being deposited on the adjoining public highway, in the interests of highway safety and the amenity of the surrounding area. It will also ensure that the development accords with the Development Control Policies Development Plan Document Policies DC32 and DC61.
15.Before the development hereby permitted commences details of a scheme shall be submitted to and approved in writing by the local planning authority which specifies the provisions to be made for refuse and recycling for the site. Such scheme as may be approved shall be implemented prior to first occupation and thereafter retained in accordance with such details. Reason:- Insufficient information has been supplied with the application to judge how refuse and recycling will be managed on site. Submission of this detail will protect the amenity of occupiers of the development and also the locality generally and ensure that the development accords with the Development Control Policies Development Plan Document Policy DC61.
16.No building shall be occupied or use commenced until cycle storage is provided in accordance with details previously submitted to and approved in writing by the Local Planning Authority. The cycle storage shall be permanently retained thereafter. Reason:- Insufficient information has been supplied with the application to demonstrate what facilities will be available for cycle parking. Submission of this detail prior to occupation in the case of new building works or prior to the use commencing in the case of changes of use is in the interests of providing a wide range of facilities for non-motor car residents and sustainability.
17.No works shall take place in relation to any of the development hereby approved (except works required to secure compliance with this condition) until the following Contaminated Land reports (as applicable) are submitted to and approved in writing by the Local Planning Authority: a) A Phase I (Desktop Study) Report documenting the history of this site, its surrounding area and the likelihood of contaminant/s, their type and extent incorporating a Site Conceptual Model. b) A Phase II (Site Investigation) Report if the Phase I Report confirms the possibility of a significant risk to any sensitive receptors. This is an intrusive site investigation including factors such as chemical testing, quantitative risk assessment and a description of the site ground conditions. An updated Site Conceptual Model should be included showing all the potential pollutant linkages and an assessment of risk to identified receptors. c) A Phase III (Remediation Strategy) Report if the Phase II Report confirms the presence of a significant pollutant linkage requiring remediation. A detailed remediation scheme to bring the site to a condition suitable for the intended use by removing unacceptable risks to all receptors must be prepared, and is subject to the approval in writing of the local planning authority. This scheme must include all works to be undertaken, proposed remediation objectives and remediation criteria, timetable of works, site management procedures and procedure for dealing with previously unidentified contamination. The scheme must ensure that the site will not qualify as contaminated land under Part 2A of the Environmental Protection Act 1990 in relation to the intended use of the land after remediation. d) Following completion of measures identified in the approved remediation scheme mentioned in (c), a 'Validation Report' that demonstrates the effectiveness of the remediation carried out, any requirement for longer-term monitoring of contaminant linkages, maintenance and arrangements for contingency action, must be produced, and is subject to the approval in writing of the Local Planning Authority. e) If during development contamination not previously identified is found to be present at the site then no further development (unless otherwise agreed in writing by the local planning authority) shall be carried out until a remediation strategy detailing how this unsuspected contamination shall be dealt with has been submitted to and approved in writing by the local planning authority. The remediation strategy shall be implemented as approved. f) Following completion of the remediation of the remediation works as mentioned in (e), a Verification Report must be submitted demonstrating that the works have been carried out satisfactorily and remediation targets have been achieved. Reason:- To protect those engaged in construction and occupation of the development from potential contamination.
18.All building operations in connection with the construction of external walls, roof, and foundations; site excavation or other external site works; works involving the use of plant or machinery; the erection of scaffolding; the delivery of materials; the removal of materials and spoil from the site, and the playing of amplified music shall only take place between the hours of 8.00am and 6.00pm Monday to Friday, and between 8.00am and 1.00pm on Saturdays and not at all on Sundays and Bank Holidays/Public Holidays. Reason:- To protect residential amenity, and in order that the development accords with the Development Control Policies Development Plan Document Policy DC61.
19.No works shall take place in relation to any of the development hereby approved until a Construction Method Statement to control the adverse impact of the development on the amenity of the public and nearby occupiers is submitted to and approved in writing by the Local Planning Authority. The Construction Method statement shall include details of: a) parking of vehicles of site personnel and visitors; b) storage of plant and materials; c) dust management controls; d) measures for minimising the impact of noise and ,if appropriate, vibration arising from construction activities; e) predicted noise and, if appropriate, vibration levels for construction using methodologies and at points agreed with the Local Planning Authority; f) scheme for monitoring noise and if appropriate, vibration levels using methodologies and at points agreed with the Local Planning Authorities; g) siting and design of temporary buildings; h) scheme for security fencing/hoardings, depicting a readily visible 24-hour contact number for queries or emergencies; i) details of disposal of waste arising from the construction programme, including final disposal points. The burning of waste on the site at any time is specifically precluded. And the development shall be carried out in accordance with the approved scheme and statement. Reason:- Insufficient information has been supplied with the application in relation to the proposed construction methodology. Submission of details prior to commencement will ensure that the method of construction protects residential amenity. It will also ensure that the development accords the Development Control Policies Development Plan Document Policy DC61.
20.No works shall take place in relation to any of the development hereby approved until a full and detailed application for the Secured by Design award scheme is submitted to the Local Planning Authority, setting out how the principles and practices of the Secured by Design Scheme are to be incorporated. Once approved in writing by the Local Planning Authority in consultation with the Metropolitan Police Designing Out Crime Officers, the development shall be carried out in accordance with the agreed details. Reason:- Insufficient information has been supplied with the application to judge whether the proposals meet Secured by Design standards. Submission of a full and detailed application prior to commencement is in the interest of creating safer, sustainable communities and to reflect guidance in Policies CP17 and DC63 of the Core Strategy and Development Control Policies Development Plan Document and the NPPF.
21.All dwellings hereby approved shall comply with Regulation 36 (2)(b) and Part G2 of the Building Regulations - Water Efficiency. Reason: In order to comply with Policy 5.15 of the London Plan.
22.In promoting the delivery of safer, stronger, sustainable places the Local Planning Authority fully supports the adoption of the principles and practices of the Secured by Design Award Scheme and Designing against Crime. Your attention is drawn to the free professional service provided by the Metropolitan Police Designing Out Crime Officers for North East London, whose can be contacted via DOCOMailbox.NE@met.police.uk or 0208 217 3813 . They are able to provide qualified advice on incorporating crime prevention measures into new developments.
23.With regards to surface water drainage it is the responsibility of the developer to make proper provision for drainage to ground, water courses or a suitable sewer. In respect of surface water it is recommended that the applicant should ensure that storm flows are attenuated or regulated into the receiving public network through on or off site storage. When it is proposed to connect to a combined public sewer, the site drainage should be separate and combined at the final manhole nearest the boundary. Connections are not permitted for the removal of Ground Water. Where the developer proposes to discharge to a public sewer, prior approval from Thames Water Developer Services will be required. They can be contacted on 0845 850 2777.
24.Changes to the public highway (including permanent or temporary access) - Planning approval does not constitute approval for changes to the public highway. Highway Authority approval will only be given after suitable details have been submitted considered and agreed. If new or amended access is required (whether temporary or permanent), there may be a requirement for the diversion or protection of third party utility plant or highway authority assets and it is recommended that early involvement with the relevant statutory undertaker takes place. The applicant must contact Engineering Services on 01708 433751 to discuss the scheme and commence the relevant highway approvals process. Please note that unauthorised work on the highway is an offence. Highway legislation - The developer (including their representatives and contractors) is advised that planning consent does not discharge the requirements of the New Roads and Street Works Act 1991 and the Traffic Management Act 2004. Formal notifications and approval will be needed for any highway works (including temporary works of any nature) required during the construction of the development. Please note that unauthorised work on the highway is an offence. Temporary use of the public highway - The developer is advised that if construction materials are proposed to be kept on the highway during construction works then they will need to apply for a licence from the Council. If the developer required scaffolding, hoarding or mobile cranes to be used on the highway, a licence is required and Street Management should be contacted to make the necessary arrangements. Please note that unauthorised use of the highway for construction works is an offence. Surface water management - The developer is advised that surface water from the development in both its temporary and permanent states should not be discharged onto the highway. Failure to prevent such is an offence.
25.Statement Required by Article 35 (2) of the Town and Country Planning (Development Management Procedure) (England) Order 2015: In accordance with para 186-187 of the National Planning Policy Framework 2012, improvements required to make the proposal acceptable were negotiated with the agent by email in November 2017. The revisions involved redrawing of the red line plan and the production of additional ownership certificates.
26.The proposal is liable for the Mayor of London Community Infrastructure Levy (CIL). CIL is payable within 60 days of commencement of development. A Liability Notice will be sent to the applicant (or anyone else who has assumed liability) shortly and you are required to notify the Council of the commencement of the development before works begin. Further details with regard to CIL are available from the Council's website.
27.The planning obligations recommended in this report have been subject to the statutory tests set out in Regulation 122 of the Community Infrastructure Levy Regulations 2010 and the obligations are considered to have satisfied the following criteria:- (a) Necessary to make the development acceptable in planning terms; (b) Directly related to the development; and (c) Fairly and reasonably related in scale and kind to the development.