1.The development to which this permission relates must be commenced not later than three years from the date of this permission. Reason:- To comply with the requirements of Section 91 of the Town and Country Planning Act 1990 (as amended by Section 51 of the Planning and Compulsory Purchase Act 2004).
2.The development hereby permitted shall not be carried out otherwise than in complete accordance with the approved plans (as set out on page one of this decision notice). Reason:- For the avoidance of doubt and to ensure that the development is carried out as approved.
3.The proposed development hereby approved shall be constructed in accordance with the materials detailed on the application form unless otherwise agreed in writing by the Local Planning Authority. Reason: To ensure that the appearance of the proposed development will harmonise with the character of the surrounding area and comply with Local Plan policy 26.
4.Before the building(s) hereby permitted is first occupied, the area set aside for car parking shall be laid out and surfaced to the satisfaction of the Local Planning Authority and retained permanently thereafter for the accommodation of vehicles visiting the site and shall not be used for any other purpose. Reason:- To ensure that car parking accommodation is made permanently available to the standards adopted by the Local Planning Authority in the interest of highway safety, and that the development accords with the Local Plan policy 24 and London Plan Policy T6.1.
5.Before the building(s) hereby permitted is first occupied, a scheme of hard and soft landscaping to include details of boundary treatment, which shall include indications of all existing trees/hedges and shrubs on the site, and details of any to be retained, together with measures for the protection in the course of development shall be submitted to and approved by the Local Planning Authority. All planting, seeding or turfing comprised within the scheme shall be carried out in the first planting season following completion of the development and any trees or plants which within a period of 5 years from completion of the development die, are removed or become seriously damaged or diseased shall be replaced in the next planting season with others of a similar size and species, unless otherwise agreed in writing by the local Planning Authority. Reason:- Insufficient information has been supplied with the application to judge the appropriateness of the hard and soft landscaping proposed. Submission of a scheme prior to occupation will ensure that the development accords with Local Plan Policies 7, 26 and 27. It will also ensure accordance with Section 197 of the Town and Country Planning Act 1990.
6.All building operations in connection with the construction of external walls, roof, and foundations; site excavation or other external site works; works involving the use of plant or machinery; the erection of scaffolding; the delivery of materials; the removal of materials and spoil from the site, and the playing of amplified music shall only take place between the hours of 8.00am and 6.00pm Monday to Friday, and between 8.00am and 1.00pm on Saturdays and not at all on Sundays and Bank Holidays/Public Holidays. Reason:- To protect residential amenity, and in order that the development accords with Local Plan policy 34.
7.No works shall take place in relation to any of the development hereby approved until a Construction Method Statement to control the adverse impact of the development on the amenity of the public and nearby occupiers is submitted to and approved in writing by the Local Planning Authority. The Construction Method statement shall include details of: a) parking of vehicles of site personnel and visitors; b) storage of plant and materials; c) dust management controls; d) measures for minimising the impact of noise and ,if appropriate, vibration arising from construction activities; e) predicted noise and, if appropriate, vibration levels for construction using methodologies and at points agreed with the Local Planning Authority; f) scheme for monitoring noise and if appropriate, vibration levels using methodologies and at points agreed with the Local Planning Authorities; g) siting and design of temporary buildings; h) scheme for security fencing/hoardings, depicting a readily visible 24-hour contact number for queries or emergencies; i) details of disposal of waste arising from the construction programme, including final disposal points. The burning of waste on the site at any time is specifically precluded. And the development shall be carried out in accordance with the approved scheme and statement. Reason:- Insufficient information has been supplied with the application in relation to the proposed construction methodology. Submission of details prior to commencement will ensure that the method of construction protects residential amenity. It will also ensure that the development accords with Local Plan policies 23, 24 and 34.
8.Notwithstanding the provisions of the Town and Country Planning (General Permitted Development) (England) Order 2015, other than porches erected in accordance with the Order, no extension or enlargement (including additions to roofs) shall be made to the dwellinghouse(s) hereby permitted, or any detached building erected, without the express permission in writing of the Local Planning Authority. Reason:- In the interests of amenity and to enable the Local Planning Authority to retain control over future development, and in order that the development accords with Local Plan policies 7 and 26.
9.The hard surface hereby approved (including any sub-base) shall be made of porous materials or provision shall be made to direct run-off water from the hard surface to a permeable or porous area or surface within the curtilage of the dwellinghouse. Reason:- In order to ensure no water run-off from the hard surface which would contribute to risk of flooding (Local Plan Policy 32 and London Plan Policy SI 13).
10.Prior to the commencement of any works pursuant to this permission the developer shall submit for the written approval of the Local Planning Authority; a) A Phase I (Desktop Study) Report documenting the history of the site, its surrounding area and the likelihood of contaminant/s, their type and extent incorporating a Site Conceptual Model. b) A Phase II (Site Investigation) Report if the Phase I Report confirms the possibility of a significant risk to any sensitive receptors. This is an intrusive site investigation including factors such as chemical testing, quantitative risk assessment and a description of the sites ground conditions. An updated Site Conceptual Model should be included showing all the potential pollutant linkages and an assessment of risk to identified receptors. c) A Phase III (Remediation Strategy) Report if the Phase II Report confirms the presence of a significant pollutant linkage requiring remediation. A detailed remediation scheme to bring the site to a condition suitable for the intended use by removing unacceptable risks to all receptors must be prepared, and is subject to the approval in writing of the Local Planning Authority. The scheme must include all works to be undertaken, proposed remediation objectives and remediation criteria, timetable of works, site management procedures and procedure for dealing with previously unidentified any contamination. The scheme must ensure that the site will not qualify as contaminated land under Part 2A of the Environmental Protection Act 1990 in relation to the intended use of the land after remediation. d) Following completion of measures identified in the approved remediation scheme mentioned in 1(c) above, a "Verification Report" that demonstrates the effectiveness of the remediation carried out, any requirement for longer-term monitoring of contaminant linkages, maintenance and arrangements for contingency action, must be produced, and is subject to the approval in writing of the Local Planning Authority. Reason: To protect those engaged in construction and occupation of the development from potential contamination and in order that the development accords with policy 34 of the Local Plan 2021.
11.If, during development, contamination not previously identified is found to be present at the site then no further development (unless otherwise agreed in writing with the local planning authority) shall be carried out until a remediation strategy detailing how this unsuspected contamination shall be dealt with has been submitted to and approved in writing by the local planning authority. The remediation strategy shall be implemented as approved. b) Following completion of the remediation works as mentioned in (a) above, a 'Verification Report' must be submitted demonstrating that the works have been carried out satisfactorily and remediation targets have been achieved. Reason: To ensure that any previously unidentified contamination found at the site is investigated and satisfactorily addressed in order to protect those engaged in construction and occupation of the development from potential contamination.
12.Prior to the commencement of any development, an assessment shall be undertaken of the impact of: a) railways noise (in accordance with Technical memorandum, "Calculation of Railway Noise", 1995) b) vibration from the use of the railway lines Upon the site. Following this, a scheme detailing the measures to protect residents from railway noise and vibration is to be submitted to, approved in writing by the Local Planning Authority, implemented prior to occupancy taking place. Reason: To protect residents from transportation noise and vibration.
13.The building(s) shall be so constructed as to provide sound insulation of 45 DnT,w + Ctr dB (minimum value) against airborne noise to the satisfaction of the Local Planning Authority. Reason: To prevent noise nuisance to adjoining properties.
14.The proposed development shall be implemented in accordance with the Tree Protection Plan on Drawing No. OS 2525-22.1 and the Arboricultural Impact Assessment prepared by OpenSpaces Landscape Architecture, Ref OS 2529-22-Doc 1, dated November 2022, including any recommendations. Reason:- To ensure that the development accords with Policy 27 of the Havering Local Plan and Policy G7 of the London Plan. It will also ensure accordance with Section 197 of the Town and Country Planning Act 1990.
15.All dwellings hereby approved shall comply with Regulation 36 (2)(b) and Part G2 of the Building Regulations - Water Efficiency. Reason: In order to comply with Policy SI 5 of the London Plan.
16.Notwithstanding the provisions of the Town and Country Planning (General Permitted Development) (England) Order 2015, no window or other opening (other than those shown on the submitted and approved plan,) shall be formed in the flank wall(s) of the building(s) hereby permitted, unless specific permission under the provisions of the Town and Country Planning Act 1990 has first been sought and obtained in writing from the Local Planning Authority. Reason:- In order to ensure a satisfactory development that will not result in any loss of privacy or damage to the environment of neighbouring properties which exist or may be proposed in the future.
17.No building shall be occupied or use commenced until cycle storage is provided in accordance with the London Plan Policy T5. The cycle storage shall be permanently retained thereafter. Reason:- In the interests of providing a wide range of facilities for non-motor car residents and sustainability (London Plan (2021) Policy T5).
18.No building shall be occupied or use commenced until refuse and recycling facilities are provided in accordance with Policy 35 of the Local Plan. The refuse and recycling facilities shall be permanently retained thereafter. Reason:- To protect the amenity of occupiers of the development and also the locality generally (Local Plan Policy 35).
19.Prior to the first occupation of the development, details shall be submitted to and agreed in writing by the Local Planning Authority for the installation of Ultra-Low NOx boilers with maximum NOx Emissions less than 40 mg/kWh. Where any installations do not meet this emissions standard it should not be operated without the fitting of suitable NOx abatement equipment or technology as determined by a specialist to ensure comparable emissions. The installation of the boilers shall be carried out in strict accordance with the agreed details and shall thereafter be permanently retained. Following installation emissions certificates will need to be provided to the Local Planning Authority to verify boiler emissions. Reason:- To minimise the impact of building emissions on local air quality (Local Plan policies 33 ad 34 and London Plan Policy SI1.
20.No above ground works shall take place in relation to any of the development hereby approved until details of surface water drainage works are submitted to and approved in writing by the Local Planning Authority. Surface water drainage shall be provided in accordance with the approved details. Reason:- Surface water drainage works are required on site to prevent the risk of flooding. Submission of a scheme prior to commencement will ensure that the measures to be employed are technically sound and that the development accords with Local Plan Policy 32 and London Plan (2021) policy SI 12.
21.Minor (up to 9 units): All dwellings hereby approved shall be constructed to comply with Part M4(2) of the Building Regulations - Accessible and Adaptable Dwellings. Reason: In order to comply with national optional technical standards as required by Policy D7 of the London Plan.
22.Statement Required by Article 35 (2) of the Town and Country Planning (Development Management Procedure) (England) Order 2015: No significant problems were identified during the consideration of the application, and therefore it has been determined in accordance with paragraph 38 of the National Planning Policy Framework 2021.
23.In promoting the delivery of safer, stronger, sustainable places the Local Planning Authority fully supports the adoption of the principles and practices of the Secured by Design Award Scheme and Designing against Crime. Your attention is drawn to the free professional service provided by the Metropolitan Police Designing Out Crime Officers for North East London, whose can be contacted via DOCOMailbox.NE@met.police.uk or 0208 217 3813 . They are able to provide qualified advice on incorporating crime prevention measures into new developments.
24.This proposal would be liable for a Mayoral and Havering Community Infrastructure Levy payment as it would create one additional residential unit and would add a net additional 80sqm of residential floor space. Therefore the proposal would incur a Havering CIL charge of £15,625 and a Mayoral CIL charge of £3,125based on the calculation of £25 per square metre and £125 per square metre, subject to indexation.
25.Before occupation of the residential/commercial unit(s) hereby approved, it is a requirement to have the property/properties officially Street Named and Numbered by our Street Naming and Numbering Team. Official Street Naming and Numbering will ensure that that Council has record of the property/properties so that future occupants can access our services. Registration will also ensure that emergency services, Land Registry and the Royal Mail have accurate address details. Proof of having officially gone through the Street Naming and Numbering process may also be required for the connection of utilities. For further details on how to apply for registration see: https://www.havering.gov.uk/Pages/Services/Street-names-and-numbering.aspx
26.Changes to the public highway (including permanent or temporary access) - Planning approval does not constitute approval for changes to the public highway. Highway Authority approval will only be given after suitable details have been submitted considered and agreed. If new or amended access is required (whether temporary or permanent), there may be a requirement for the diversion or protection of third party utility plant or highway authority assets and it is recommended that early involvement with the relevant statutory undertaker takes place. The applicant must contact Engineering Services on 01708 433751 to discuss the scheme and commence the relevant highway approvals process. Please note that unauthorised work on the highway is an offence. Highway legislation - The developer (including their representatives and contractors) is advised that planning consent does not discharge the requirements of the New Roads and Street Works Act 1991 and the Traffic Management Act 2004. Formal notifications and approval will be needed for any highway works (including temporary works of any nature) required during the construction of the development. Please note that unauthorised work on the highway is an offence. Temporary use of the public highway - The developer is advised that if construction materials are proposed to be kept on the highway during construction works then they will need to apply for a licence from the Council. If the developer required scaffolding, hoarding or mobile cranes to be used on the highway, a licence is required and Street Management should be contacted to make the necessary arrangements. Please note that unauthorised use of the highway for construction works is an offence. Surface water management - The developer is advised that surface water from the development in both its temporary and permanent states should not be discharged onto the highway. Failure to prevent such is an offence.