1.The development to which this permission relates must be commenced not later than three years from the date of this permission. Reason:- To comply with the requirements of Section 91 of the Town and Country Planning Act 1990 (as amended by Section 51 of the Planning and Compulsory Purchase Act 2004).
2.The development hereby permitted shall not be carried out otherwise than in complete accordance with the approved plans (as set out on page one of this decision notice). Reason:- For the avoidance of doubt and to ensure that the development is carried out as approved.
3.Notwithstanding the details shown on the approved drawings, the development hereby approved shall not progress above damp proof course until samples/details of all the external finishing materials are submitted to and approved in writing by the Local Planning Authority and thereafter the development shall be constructed with the approved materials. Reason: - Insufficient information has been supplied with the application to judge the appropriateness of the external finishing materials to be used. Submission of samples prior to works above damp proof course will safeguard the appearance of the premises and the character of the immediate area and will ensure that the development accords with Policies 26 and 27 of the Local Plan 2021.
4.Prior to demolition works in relation to any of the development hereby approved a Construction Method Statement to control the adverse impact of the development on the amenity of the public and nearby occupiers shall be submitted to and approved in writing by the Local Planning Authority. The Construction Method statement shall include details of: a) parking of vehicles of site personnel and visitors; b) storage of plant and materials; c) dust management controls; d) measures for minimising the impact of noise and ,if appropriate, vibration arising from construction activities; e) predicted noise and, if appropriate, vibration levels for construction using methodologies and at points agreed with the Local Planning Authority; f) scheme for monitoring noise and if appropriate, vibration levels using methodologies and at points agreed with the Local Planning Authorities; g) siting and design of temporary buildings; h) scheme for security fencing/hoardings, depicting a readily visible 24-hour contact number for queries or emergencies; i) details of disposal of waste arising from the construction programme, including final disposal points. The burning of waste on the site at any time is specifically precluded. And the development shall be carried out in accordance with the approved scheme and statement. Reason:- Insufficient information has been supplied with the application in relation to the proposed construction methodology. Submission of details prior to commencement will ensure that the method of construction protects residential amenity. It will also ensure that the development accords with Local Plan policy 23, 24 and 34 and London Plan (2021) Policy T7.
5.All building operations in connection with the construction of external walls, roof, and foundations; site excavation or other external site works; works involving the use of plant or machinery; the erection of scaffolding; the delivery of materials; the removal of materials and spoil from the site, and the playing of amplified music shall only take place between the hours of 8.00am and 6.00pm Monday to Friday, and between 8.00am and 1.00pm on Saturdays and not at all on Sundays and Bank Holidays/Public Holidays. Reason:- To protect residential amenity, and in order that the development accords with Local Plan Policy 34.
6.No occupation of the new dwellings shall take place in relation to any of the development hereby approved until there has been submitted to and approved by the Local Planning Authority a scheme of hard and soft landscaping, which shall include indications of all existing trees and shrubs on the site, details of any to be retained, together with measures for the protection in the course of development and details of the removal of the existing hard landscaping within the front gardens to be replaced with soft landscaping to improve biodiversity within the site. All planting, seeding or turfing comprised within the scheme shall be carried out in the first planting season following completion of the development and any trees or plants which within a period of 5 years from completion of the development die, are removed or become seriously damaged or diseased shall be replaced in the next planting season with others of a similar size and species, unless otherwise agreed in writing by the Local Planning Authority. Reason:- Insufficient information has been supplied with the application to judge the appropriateness of the hard and soft landscaping proposed. Submission of a scheme prior to commencement will ensure that the development accords with Local Plan policy 27. It will also ensure accordance with Section 197 of the Town and Country Planning Act 1990.
7.Prior to above ground works commencing of the development hereby approved, details of all proposed walls, fences, including front garden boundary treatments shall be submitted to, and approved in writing by, the Local Planning Authority. The development shall then be carried out in accordance with the approved details and retained permanently thereafter to the satisfaction of the Local Planning Authority. Reason: Insufficient information has been supplied with the application to judge the appropriateness of any boundary treatment. Submission of this detail prior to commencement will protect the visual amenities of the development, prevent undue overlooking of adjoining property and ensure that the development accords with Local Plan policies 7, 26 and 27.
8.All hard surfaces hereby approved as part of the development (including any sub-base) shall be made of porous materials or provision shall be made to direct run-off water from the hard surface to a permeable or porous area or surface within the curtilage of the application site. Reason:- In order to ensure no water run-off from the hard surface which would contribute to risk of flooding (Local Plan policy 32 and London Plan (2021) Policy T7).
9.No works shall take place in relation to any of the development hereby approved until a scheme for the protection of tree(s) on/adjoining the site has been submitted to and agreed in writing by the Local Planning Authority. Such scheme shall contain details of the erection and maintenance of fences or walls around the trees, details of underground measures to protect roots, the control of areas around the trees and any other measures necessary for the protection of the trees. Such agreed measures shall be implemented before development commences and kept in place until the approved development is completed. Reason:- Insufficient information has been supplied with the application to demonstrate how the trees located on/adjoining the site will be adequately protected during construction. Submission of details prior to commencement will ensure that the measures to be employed are robust.
10.No above ground works shall take place in relation to any of the development hereby approved until details of the proposed Sustainability and Energy Strategy for the proposed scheme are submitted to the Local Planning Authority and approved in writing to demonstrate the delivery of a sustainable development on the site. Reason:- To ensure the delivery of a sustainable development in accordance with the National Planning Policy Framework 2021, policies GG65, SI 2 of The London Plan (2021) and Policy 36 of the Local Plan 2021
11.Prior to the commencement of any works pursuant to this permission the developer shall submit for the written approval of the Local Planning Authority; a) A Phase I (Desktop Study) Report documenting the history of the site, its surrounding area and the likelihood of contaminant/s, their type and extent incorporating a Site Conceptual Model. b) A Phase II (Site Investigation) Report if the Phase I Report confirms the possibility of a significant risk to any sensitive receptors. This is an intrusive site investigation including factors such as chemical testing, quantitative risk assessment and a description of the sites ground conditions. An updated Site Conceptual Model should be included showing all the potential pollutant linkages and an assessment of risk to identified receptors. c) A Phase III (Remediation Strategy) Report if the Phase II Report confirms the presence of a significant pollutant linkage requiring remediation. A detailed remediation scheme to bring the site to a condition suitable for the intended use by removing unacceptable risks to all receptors must be prepared, and is subject to the approval in writing of the Local Planning Authority. The scheme must include all works to be undertaken, proposed remediation objectives and remediation criteria, timetable of works, site management procedures and procedure for dealing with previously unidentified any contamination. The scheme must ensure that the site will not qualify as contaminated land under Part 2A of the Environmental Protection Act 1990 in relation to the intended use of the land after remediation. d) Following completion of measures identified in the approved remediation scheme mentioned in 1(c) above, a "Verification Report" that demonstrates the effectiveness of the remediation carried out, any requirement for longer-term monitoring of contaminant linkages, maintenance and arrangements for contingency action, must be produced, and is subject to the approval in writing of the Local Planning Authority. Reason: To protect those engaged in construction and occupation of the development from potential contamination and in order that the development accords with Policy 34 of the Local Plan 2021.
12.If, during development, contamination not previously identified is found to be present at the site then no further development (unless otherwise agreed in writing with the local planning authority) shall be carried out until a remediation strategy detailing how this unsuspected contamination shall be dealt with has been submitted to and approved in writing by the local planning authority. The remediation strategy shall be implemented as approved. a) Following completion of the remediation works as mentioned above, a 'Verification Report' must be submitted demonstrating that the works have been carried out satisfactorily and remediation targets have been achieved. Reason: - To ensure that any previously unidentified contamination found at the site is investigated and satisfactorily addressed in order to protect those engaged in construction and occupation of the development from potential contamination in accordance with Policy 34 of the Local Plan 2021.
13.The new dwellings hereby approved shall be designed to ensure that the internal water consumption does not exceed a maximum of 105 litres per day to comply with London Plan policy SI5 and Regulation 36 (2)(b) and Part G2 of the Building Regulations - Water Efficiency. Reason: In order to comply with Policy SI 5 of the London Plan (2021).
14.Notwithstanding the provisions of the Town and Country Planning (General Permitted Development) (England) Order 2015, no extension or enlargement (including porches and additions to roofs) shall be made to the dwellinghouse(s) hereby permitted, or any detached building erected, without the express permission in writing of the Local Planning Authority. Reason:- In the interests of amenity and to enable the Local Planning Authority to retain control over future development, and in order that the development accords with Local Plan Policies 7 and 26.
15.No above ground works shall take place in relation to any of the development hereby approved until details of surface water drainage works are submitted to and approved in writing by the Local Planning Authority. Surface water drainage shall be provided in accordance with the approved details. Reason:- Surface water drainage works are required on site to prevent the risk of flooding. Submission of a scheme prior to commencement will ensure that the measures to be employed are technically sound and that the development accords with Local Plan Policy 32 and London Plan (2021) policy SI 12.
16.Prior to the first occupation of the development, details shall be submitted to and agreed in writing by the Local Planning Authority for the installation of Ultra-Low NOx boilers with maximum NOx Emissions less than 40 mg/kWh. Where any installations do not meet this emissions standard it should not be operated without the fitting of suitable NOx abatement equipment or technology as determined by a specialist to ensure comparable emissions. The installation of the boilers shall be carried out in strict accordance with the agreed details and shall thereafter be permanently retained. Following installation emissions certificates will need to be provided to the Local Planning Authority to verify boiler emissions. Reason: To minimise the impact of building emissions on local air quality (Local Plan policies 33 ad 34 and London Plan Policy SI1.
17.Notwithstanding the plans hereby approved, the windows located on the side walls of each dwelling shown on plan ref. 119 Rev A shall be permanently glazed with obscure glass not less than LEVEL 4 on the standard scale of obscurity and shall thereafter be maintained. Reason:- In the interests of privacy.
18.Notwithstanding the provisions of the Town and Country Planning (General Permitted Development) (England) Order 2015, no window or other opening (other than those shown on the submitted and approved plan,) shall be formed in the flank wall(s) of the building(s) hereby permitted, unless specific permission under the provisions of the Town and Country Planning Act 1990 has first been sought and obtained in writing from the Local Planning Authority. Reason:- In order to ensure a satisfactory development that will not result in any loss of privacy or damage to the environment of neighbouring properties which exist or may be proposed in the future.
19.All dwellings hereby approved shall be constructed to comply with Part M4(2) of the Building Regulations - Accessible and Adaptable Dwellings. Reason: In order to comply with national optional technical standards as required by Policy D7 of the London Plan.
20.Before the building(s) hereby permitted is first occupied, provision shall be made within the site for one car parking space only per dwelling and thereafter this provision shall be made permanently available for use, unless otherwise agreed in writing by the Local Planning Authority. Reason:- To ensure that adequate car parking provision is made off street in the interests of highway safety.
21.The proposals would incur a Mayoral CIL contribution of £3,475 at a rate of £25 per sqm. The proposal is also liable for the Havering Community Infrastructure Levy (HCIL), which has a charging rate of £125 per square metre of net additional floor space in Zone A. The Havering Community Infrastructure Levy contribution would equate to £20,850. Each contribution would be subject to indexation. These charges are levied under s.206 of the Planning Act 2008. CIL is payable within 60 days of commencement of development. A Liability Notice will be sent to the applicant (or anyone else who has assumed liability) shortly and you are required to notify the Council of the commencement of the development before works begin. Further details with regard to CIL are available from the Council's website. You are also advised to visit the planning portal website where you can download the appropriate document templates at: http://www.planningportal.gov.uk/planning/applications/howtoapply/whattosubmit/cil
22.Statement Required by Article 35(2) of the Town and Country Planning (Development Management) Order 2015: No significant problems were identified during the consideration of the application, and therefore it has been determined in accordance with paragraph 38 of the National Planning Policy Framework.