The London Borough Of Havering - Home page

No.Condition Text
1.The development to which this permission relates must be commenced not later than three years from the date of this permission. Reason:- To comply with the requirements of Section 91 of the Town and Country Planning Act 1990 (as amended by Section 51 of the Planning and Compulsory Purchase Act 2004).
2.The development hereby permitted shall not be carried out otherwise than in complete accordance with the approved plans (as set out on page one of this decision notice). Reason:- The Local Planning Authority consider it essential that the whole of the development is carried out and that no departure whatsoever is made from the details approved, since the development would not necessarily be acceptable if partly carried out or carried out differently in any degree from the details submitted. Also, in order that the development accords with Development Control Policies Development Plan Document Policy DC61.
3.No works shall take place in relation to any of the development hereby approved until samples of the materials to be used to enclose the flue are submitted to and approved in writing by the Local Planning Authority and thereafter the development shall be constructed with the approved materials. Reason:- Insufficient information has been supplied with the application to judge the appropriateness of the materials to be used. Submission of samples prior to commencement will ensure that the appearance of the proposed development will harmonise with the character of the surrounding area and comply with Policy DC61 of the Development Control Policies Development Plan Document.
4.The development hereby permitted shall be implemented in accordance with the waste management scheme as previously approved under application Q0035.10 and shall be permanently maintained. Reason:- To protect the amenity of occupiers of nearby premises, and in order that the development accords with the Development Control Policies Development Plan Document Policy DC61.
5.Before the use commences suitable equipment to remove and/or disperse odours and odorous material should be fitted to the extract ventilation system in accordance with a scheme to be designed and certified by a competent engineer and after installation a certificate to be lodged with the Planning Authority. Thereafter, the equipment shall be properly maintained and operated within design specifications during normal working hours. Reason: Insufficient information has been supplied with the application to judge the technical specifications of the extract ventilation system. Submission of this detail prior to commencement of the use will protect the amenity of occupiers of nearby premises and ensure that the development accords with Development Control Policies Development Plan Document Policy DC61.
6.Before any works commence a scheme for any new plant or machinery shall be submitted to the local planning authority to achieve the following standard. Noise levels expressed as the equivalent continuous sound level LAeq (1 hour) when calculated at the boundary with the nearest noise sensitive premises shall not exceed LA90 -10dB and shall be maintained thereafter to the satisfaction of the Local Planning Authority. Reason:- To prevent noise nuisance to adjoining properties in accordance with the recommendations of Planning Policy Guidance Note 24 'Planning & Noise' 1994.
7.Before the uses commences a scheme to control the transmission of noise and vibration from any mechanical ventilation system installed shall be submitted to and approved in writing by the Local Planning Authority and implemented prior to the permitted use commencing. Thereafter, the equipment shall be properly maintained and operated during normal working hours. Reason:- Insufficient information has been supplied with the application to judge the technical specifications of the mechanical ventilation system. Submission of this detail prior to occupation in the case of new building works or prior to the use commencing in the case of changes of use protect the amenity of occupiers of nearby premises, and in order that the development accords with Development Control Policies Development Plan Document Policy DC61.
8.The premises shall not be used for the purposes hereby permitted other than between the hours of 07:00 and 18:00 any day of the week, excluding Bank or Public Holidays, without the prior consent in writing of the Local Planning Authority. Reason:- To enable the Local Planning Authority to retain control in the interests of amenity, and in order that the development accords with Development Control Policies Development Plan Document Policy DC61.
9.Statement Required by Article 35 (2) of the Town and Country Planning (Development Management Procedure) (England) Order 2015: No significant problems were identified during the consideration of the application, and therefore it has been determined in accordance with paragraphs 186-187 of the National Planning Policy Framework 2012.